In: Finance
XYZ company is considering a new machine that costs $300,000 and would reduce pre-tax manufacturing costs by $108,000 annually. XYZ would use the 3-year MACRS method to depreciate the machine, and management thinks the machine would have a value of $23,000 at the end of its 5-year operating life. The applicable depreciation rates are 33%, 45%, 15%, and 7%. The net operating working capital (NOWC) would increase by $25,000 initially, but it would be recovered at the end of the project's 5-year life. XYZ’s marginal tax rate is 40-percent, and a 10% WACC is appropriate for the project. a) Calculate the projects NPV, IRR, and Payback. b) Assume management is unsure about the $90,000 cost savings, and this figure could deviate by as much as +/- 15%. What would the NPV have to be under each of these situations?
Initial Cash Flow | |||||||||||||
Cost of Machine | $300,000 | ||||||||||||
Net working capital | $25,000.00 | ||||||||||||
Total | $325,000.00 | ||||||||||||
OPERATING CASH FLOW | |||||||||||||
A | B=0.4*A | C=A-B | |||||||||||
Before tax | Tax | After Tax | |||||||||||
Year | Savings | Expense (40%) | Profit | ||||||||||
1 | $108,000 | $43,200 | $64,800 | ||||||||||
2 | $108,000 | $43,200 | $64,800 | ||||||||||
3 | $108,000 | $43,200 | $64,800 | ||||||||||
4 | $108,000 | $43,200 | $64,800 | ||||||||||
5 | $108,000 | $43,200 | $64,800 | ||||||||||
DEPRECIATION TAX SHIELD | |||||||||||||
A | B=A*$300,000 | C=B*0.4 | |||||||||||
Depreciation | Amount of | Depreciation | |||||||||||
Year | Rate | Depreciation | Tax shield | ||||||||||
1 | 33.00% | $99,000 | $39,600 | ||||||||||
2 | 45.00% | $135,000 | $54,000 | ||||||||||
3 | 15.00% | $45,000 | $18,000 | ||||||||||
4 | 7.00% | $21,000 | $8,400 | ||||||||||
5 | 0% | $0 | $0 | ||||||||||
TERMINAL CASH FLOW | |||||||||||||
A | Salvage value of Machine | $23,000 | |||||||||||
B=A*0.4 | Tax on gain on salvage | $9,200 | |||||||||||
C=A-B | After tax salvage cash flow | $13,800 | A | B | C | D | E | F=B+C+D+E | G=E/(1.1^A) | ||||
D | Release of working capital | $25,000 | initial cash | Operating | Depreciation | Terminal | Net | Present value | Cumulative | ||||
E=C+D | TotalTerminal Cash Flow | $38,800 | Year | flow | cashflow | Tax shield | Cashflow | Cash flow | ofNet cashflow | Net Cash flow | |||
0 | ($325,000) | ($325,000) | ($325,000) | ($325,000) | |||||||||
Present Value (PV) of Cash Flow: | 1 | $64,800 | $39,600 | $104,400 | $94,909 | ($220,600) | |||||||
(Cash Flow)/((1+i)^N) | 2 | $64,800 | $54,000 | $118,800 | $98,182 | ($101,800) | |||||||
i=Discount Rate=WACC=10%=0.1 | 3 | $64,800 | $18,000 | $82,800 | $62,209 | ($19,000) | |||||||
N=Year of Cash Flow | 4 | $64,800 | $8,400 | $73,200 | $49,997 | $54,200 | |||||||
5 | $64,800 | $0 | $38,800 | $103,600 | $64,327 | $157,800 | |||||||
Total | $44,624 | ||||||||||||
NPV of the Project | $44,623.81 | ||||||||||||
IRR of the project | 15.46% | (Using IRR function of excel over Net Cash flow) | |||||||||||
Pay BackPeriod=(3+(19000/73200)) | 3.26 | Years | (Year at which Cumulative net cash flow=0) | ||||||||||
IF THE ANNUAL SAVINGS IS -15%(Note There is error in the question. Instead of $90,000base case savings , it should be $108,000 |
|