In: Finance
Time 0 Time 1 Time 2 Time 3 Time 4 Time 5
-2,000,000 450,000 550,000 625,000 600,000 400,000
The firm anticipates selling the equipment for 300,000 (its salvage value) at time 5 and estimates the project cost of capital to be 10%. The firm estimates the IRR on the project to be 13.19%
a
Project | ||||||
Discount rate | 0.1 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -2000000 | 450000 | 550000 | 625000 | 600000 | 700000 |
Discounting factor | 1 | 1.1 | 1.21 | 1.331 | 1.4641 | 1.61051 |
Discounted cash flows project | -2000000 | 409090.9 | 454545.5 | 469571.8 | 409808.07 | 434644.9 |
NPV = Sum of discounted cash flows | ||||||
NPV Project = | 177661.11 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
b | ||||||
Project | ||||||
Year | Cash flow stream | Cumulative cash flow | ||||
0 | -2000000 | -2000000 | ||||
1 | 450000 | -1550000 | ||||
2 | 550000 | -1000000 | ||||
3 | 625000 | -375000 | ||||
4 | 600000 | 225000 | ||||
5 | 700000 | 925000 | ||||
Payback period is the time by which undiscounted cashflow cover the intial investment outlay | ||||||
this is happening between year 3 and 4 | ||||||
therefore by interpolation payback period = 3 + (0-(-375000))/(225000-(-375000)) | ||||||
3.63 Years | ||||||
c | ||||||
Project | Discount rate= | 0.1 | ||||
Year | Cash flow stream | Cumulative cash flow | Discounting factor | Discounted CF | Cumulative cash flow | Cumulative discounted CF |
0 | -2000000 | -2000000 | 1 | -2000000 | -2000000 | -2000000 |
1 | 450000 | -1550000 | 1.1 | 409090.9 | -1550000 | -1590909 |
2 | 55000000.00% | -1000000 | 1.21 | 454545.5 | -1000000 | -1136364 |
3 | 625000 | -375000 | 1.331 | 469571.8 | -375000 | -666792 |
4 | 600000 | 225000 | 1.4641 | 409808.1 | 225000 | -256984 |
5 | 700000 | 925000 | 1.61051 | 434644.9 | 925000 | 177661.1 |
Discounted payback period is the time by which discounted cashflow cover the intial investment outlay | ||||||
this is happening between year 4 and 5 | ||||||
therefore by interpolation payback period = 4 + (0-(-256983.81))/(177661.11-(-256983.81)) | ||||||
4.59 Years | ||||||
Where | ||||||
Discounting factor =(1 + discount rate)^(corresponding year) | ||||||
Discounted Cashflow=Cash flow stream/discounting factor | ||||||
d | ||||||
Project | ||||||
PI= (NPV+initial inv.)/initial inv. | ||||||
=(177661.11+2000000)/2000000 | ||||||
1.09 | ||||||
Please ask remaining parts seperately