please advise on the tendering and contractual arrangements for
the construction of a 5-star hotel in Tung Chung new town. Since
the proposed project is to be a major development, the Client is
anxious on the cost aspects
The client wishes to have indication of the amount of investment
and is concerned o the cost-control aspect. He also intends to
commence the work at a reasonable time.
Suggest to the Client with reason, a suitable contractual
arrangement for his consideration. (at less 350 words)
Hotel construction contracts are one of the important and powerful tools to help developers comply with brand guidelines.
Overall, hotel developers can:
Standard of Care
· In general, standard form contracts do not specifically and sufficiently state any "standard of care" to be applied to contractors.
· Without an express standard of care provided in the construction contract, the law will imply one which may not be what the parties intended. Hence, hotel developers should ensure their construction contracts include a standard of care that specifies the applicable laws, codes and rules that apply to the project, and confirm that certain provisions required by law to be contained in the contract are complied with and expressly included.
· For instance, the hotel developer may want to include a reference to the applicable building code, applicable city, county or association codes, or minority business enterprise language, if applicable. Additionally, hotel brand standards, LEED (green building) requirements, or other project-specific requirements, should also be included as applicable.
Substantial Completion, Final Completion
Though standard form construction contracts generally do include basic requirements for substantial completion of the construction work, such as the owner's receipt of beneficial occupancy of the project, it is advisable to include additional requirements with which the contractor must comply before it is entitled to receive payment of retainage and/or final payment.
It is often the case that many owners require the contractor to provide, as a condition precedent to substantial completion:
In addition to adding these types of conditions to its construction contracts, a hotel developer should also consider making compliance with the applicable brand standards an express condition precedent to substantial and final completion.
Some hotel flags may even want to require that brand representatives inspect the project and sign off on substantial and/or final completion.
If a hotel developer wants these conditions to be required of its contractor, then these terms must be expressly provided in the contract, or the owner may end up being required to pay retainage and/or make final payment without receiving these key close-out documents and/or brand representative approvals.
Punch List, Startup Processes
Some hotel brands may require the brand representative be involved in and sign off on the punch list and start up processes. Even if this is not a brand requirement, it is a good practice to include such a provision as the brand representative will have experience with hotel equipment and brand standards and requirements.
Uncovering issues during the punch list phase and before final payment is released will make contractor compliance easier than it otherwise would be after final payment has been made.
Real world examples illustrate how including brand approval for the punch list helps make sure the project is completed correctly. In one instance, the contractor installed a shower head on the wall adjacent to the shower door. This was not in compliance with brand standards as the brand required the shower head be placed on the wall opposite the shower door for safety and convenience purposes.
However, the plans cited in the example were silent about the location of the shower head. Because the contract provided for a brand representative’s sign off on the punch list, the developer was able to rely on the contract language to withhold final payment until the shower heads in each room were reinstalled in the proper location.
Brand Requirements as an Exhibit
Any specific brand standards that may be included in a brand construction standards' manual should be included as an exhibit and attached to the contract. Those should consider standards related to life safety, fire protection, mechanical, electrical and plumbing requirements. These elements will help define all brand standards that the contractor is required to perform, and for which the owner is obligated to pay.
Not including these standards as part of the contract can create ambiguities about what the parties intended and lead to change order disputes during construction and disputes with the brand post construction.
A detailed, comprehensive and specific outline of the applicable brand standards to be complied with can eliminate project delays, budget overruns and costly litigation with the contractor and the applicable brand.
Insurance, indemnity requirements Make sure to check any applicable brand agreements and documents such as franchise, license and management agreements for brand insurance and indemnity requirements.
Many brand agreements have specific insurance coverage and deductible limit requirements. Additionally, brand agreements and documents may require that the hotel brand/franchisor be named as an additional insured on the project’s commercial general liability and builder’s risk policies.
Moreover, the additional insured status is commonly given through an additional insured endorsement. Hotel brand agreements and documents may require the hotel brand be named as an indemnified party in the hotel design and construction contracts. Thus, the developer should make sure the construction contract complies with these requirements.
In sum, including applicable brand standards throughout the construction contract can help the hotel developer comply with brand requirements and eliminate project delays, budget overruns and costly litigation.
Since the client wants to have an indication of the amount of investment. The clear indication in this regard is how many keys the clients want to go for, cost per key on hotel industry is number of sellable rooms or units). A Hilton franchise might be about 250,000 USD per key. This cost covers everything from civil works to Building Construction to Guestroom furnishing and finishing. Typically, a 5-Star like the Marriot can go up to 300,000 USD per key. These turnkey projects can have a strong tendering process wherein many rounds of negotiation can be conducted with the BOQ in hand depicting the deletions in the BOQ and alter the same as per its one’s own requirement.
For cost control aspect, along with the above-mentioned clauses, client can also enter clauses wherein a third party would be hired for monitoring of actual materials brought in at the site along with the labour register wherein actual number of wage days will be captured. In any scenario, if the developer raises any concerns on the escalation of prices for the contract, the client can any day refer to third party’s monitoring records and avoid any disputes and cost increases in the contract