In: Accounting
Kansas Supplies is a manufacturer of plastic parts that uses the weighted-average process costing method to account for costs of production. It produces parts in three separate departments: Molding, Assembling, and Packaging. The following information was obtained for the Assembling Department for the month of April.
Work in process on April 1 had 111,000 units made up of the following:
Amount | Degree of Completion | |||||
Prior department costs transferred in from the Molding Department | $ | 155,400 | 100 | % | ||
Costs added by the Assembling Department | ||||||
Direct materials | $ | 99,900 | 100 | % | ||
Direct labor | 45,007 | 70 | % | |||
Manufacturing overhead | 25,026 | 50 | % | |||
$ | 169,933 | |||||
Work in process, April 1 | $ | 325,333 | ||||
During April, 511,000 units were transferred in from the Molding Department at a cost of $715,400. The Assembling Department added the following costs:
Direct materials | $ | 440,910 | |
Direct labor | 215,903 | ||
Manufacturing overhead | 117,264 | ||
Total costs added | $ | 774,077 | |
Assembling finished 411,000 units and transferred them to the Packaging Department.
At April 30, 211,000 units were still in work-in-process inventory. The degree of completion of work-in-process inventory at April 30 was as follows:
Direct materials | 90 | % |
Direct labor | 80 | |
Manufacturing overhead | 30 | |
Required:
a. Prepare a production cost report using FIFO. (Round "Cost per equivalent unit" to 2 decimal places.)
Solution a:
Kansas Supplier | |||||
Assembling Department | |||||
Computation of Equivalent unit (FIFO) | |||||
Particulars | Physical units | Prior department costs | Material | Labor | Manufacturing Overhead |
Units to be accounted for: | |||||
Beginning WIP Inventory | 111000 | ||||
Units started this period | 511000 | ||||
Total unit to be accounted for | 622000 | ||||
Units Accounted for: | |||||
Units completed and transferred out | |||||
From beginning inventory Prior department and material - 0% Labor - 30% Overhead - 50% |
111000 | 0 | 0 | 33300 | 55500 |
Started and completed currently | 300000 | 300000 | 300000 | 300000 | 300000 |
Units in ending WIP Prior department - 100% Material - 90% Labor - 80% Overhead - 30% |
211000 | 211000 | 189900 | 168800 | 63300 |
Total units accounted for | 622000 | 511000 | 489900 | 502100 | 418800 |
Kansas Supplier | |||||
Assembling Department | |||||
Computation of Cost per Equivalent unit | |||||
Particulars | Total cost | Prior department costs | Material | Labor | Manufacturing Overhead |
Current period cost | $1,489,477.00 | $715,400.00 | $440,910.00 | $215,903.00 | $117,264.00 |
Equivalent units | 511000 | 489900 | 502100 | 418800 | |
Cost per equivalent unit | $1.40 | $0.90 | $0.43 | $0.28 |
Kansas Supplier | |||||
Assembling Department | |||||
Producton cost report - FIFO | |||||
Particulars | Total cost | Prior department costs | Material | Labor | Manufacturing Overhead |
Cost Accounted for : | |||||
Cost assigned to unit transferred out: | |||||
Cost from beginning WIP Inventory | $325,333.00 | $155,400.00 | $99,900.00 | $45,007.00 | $25,026.00 |
Current cost added to complete beginning WIP: | |||||
Prior department cost | $0.00 | $0.00 | |||
Material | $0.00 | $0.00 | |||
Labor (33300*0.43) | $14,319.00 | $14,319.00 | |||
Manufacturing overhead (55500*0.28) | $15,540.00 | $15,540.00 | |||
Total Cost from beginning inventory | $355,192.00 | $155,400.00 | $99,900.00 | $59,326.00 | $40,566.00 |
Current cost of unit started and completed: | |||||
Prior department cost (300000*1.40) | $420,000.00 | $420,000.00 | |||
Material (300000*0.90) | $270,000.00 | $270,000.00 | |||
Labor (300000*0.43) | $129,000.00 | $129,000.00 | |||
Manufacturing overhead (300000*0.28) | $84,000.00 | $84,000.00 | |||
Total cost of unit started and completed | $903,000.00 | $420,000.00 | $270,000.00 | $129,000.00 | $84,000.00 |
Total cost of unit transferred out | $1,258,192.00 | $575,400.00 | $369,900.00 | $188,326.00 | $124,566.00 |
Cost assigned to ending WIP: | |||||
Prior department cost (211000*1.40) | $295,400.00 | $295,400.00 | |||
Material (189900*0.90) | $170,910.00 | $170,910.00 | |||
Labor (168800*0.43) | $72,584.00 | $72,584.00 | |||
Manufacturing overhead (63300*0.28) | $17,724.00 | $17,724.00 | |||
Total ending WIP inventory | $556,618.00 | $295,400.00 | $170,910.00 | $72,584.00 | $17,724.00 |
Total cost accounted for | $1,814,810.00 | $870,800.00 | $540,810.00 | $260,910.00 | $142,290.00 |