In: Accounting
Problem #1
You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is 7 months and the total cost of the materials was estimated at $250,000. The scheduled percent complete (PC) of the work and the material consumption for each month is as follows:
Month |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Monthly Scheduled PC |
10% |
10% |
20% |
25% |
15% |
15% |
5% |
This means on month 1, 10% of the work and materials is supposed to be used, on month 2 another 10% and so on and on.
At the end of month #5, earned value analysis is performed and it is found that only 35% of the work has been completed. The other available information is as follows:
Using the above-mentioned information, calculate the following:
1. Original BAC (Budget At Completion)
BAC | ||
Particulars | Amount | Basis |
Labour Cost | $ 720,000.00 | (12000*60) |
Material | $ 250,000.00 | |
$ 970,000.00 |
2. BCWS (Budgeted Cost of Work Scheduled)
Work Scheduled to be completed till the time Earned Value Calculation is Made i.e, end of 5th Month
Month | Scheduled PC |
1 | 10% |
2 | 10% |
3 | 20% |
4 | 25% |
5 | 15% |
80% |
For 80% Work Scheduled to be completed Budgeted Cost was
Original BAC * Scheduled Percentage Completion
$ 970,000.00 * 80%
$ 776,000.00
3. BCWP (Budgeted Cost of Work Performed)
Till the End of 5th Month only 35% of Worked has been performed as analysed through Earned Value Calculation.
Therefore BCWP :
Original BAC * Actual Percentage Completion
$ 970,000.00 * 35%
$ 339,500.00
4. ACWP (Actutal Cost of Work Performed)
It means actual cost incurred in performing the Actual Percentage Completion
Therefore as per Question:
60% of the man-hours were spent by the end of the 5th month : 12,000 * 60% * 60 = $ 432,000.00
40% of the materials were consumed by the end of the 5th month : 250,000 * 40% = 100,000.00
Total ACWP = $ 532,000
5. SV (Schedule Variance)
BCWP - BCWS
$ 339,500.00 - $ 776,000.00
($ 436,500.00)
6. CV (Cost Variance)
BCWP - ACWP
$ 339,500.00 - $ 532,000
($ 192,500.00)
7. SPI (Schedule Performance Index)
BCWP / BCWS
$ 339,500.00 / $ 776,000.00
43.75 %