Question

In: Accounting

Problem #1 You have a construction project that requires 12,000 man-hours at a rate of $60...

Problem #1

You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is 7 months and the total cost of the materials was estimated at $250,000. The scheduled percent complete (PC) of the work and the material consumption for each month is as follows:

Month

1

2

3

4

5

6

7

Monthly Scheduled PC

10%

10%

20%

25%

15%

15%

5%

This means on month 1, 10% of the work and materials is supposed to be used, on month 2 another 10% and so on and on.     

At the end of month #5, earned value analysis is performed and it is found that only 35% of the work has been completed. The other available information is as follows:

  • 60% of the man-hours were spent by the end of the 5th month.
  • 40% of the materials were consumed by the end of the 5th month.
  • A change order estimated at $30,000 was issued and approved at the end of month # 6.
  • The material costs escalated by 35% after the 5th month.
  • 30% of the cost of material consumed by the end of the 4th month was escalated by 20%.

Using the above-mentioned information, calculate the following:

  1. Original BAC
  2. BCWS
  3. BCWP
  4. ACWP
  5. SV
  6. CV
  7. DCWP
  8. Expenditure variance
  9. SPI
  10. EAC considering the same rate of progress

Solutions

Expert Solution

1. Original BAC (Budget At Completion)

BAC
Particulars Amount Basis
Labour Cost $ 720,000.00 (12000*60)
Material $ 250,000.00
$ 970,000.00

2. BCWS (Budgeted Cost of Work Scheduled)

Work Scheduled to be completed till the time Earned Value Calculation is Made i.e, end of 5th Month

Month Scheduled PC
1 10%
2 10%
3 20%
4 25%
5 15%
80%

For 80% Work Scheduled to be completed Budgeted Cost was

Original BAC * Scheduled Percentage Completion

$ 970,000.00 * 80%

$ 776,000.00

3. BCWP (Budgeted Cost of Work Performed)

Till the End of 5th Month only 35% of Worked has been performed as analysed through Earned Value Calculation.

Therefore BCWP :

Original BAC * Actual Percentage Completion

$ 970,000.00 * 35%

$ 339,500.00

4. ACWP (Actutal Cost of Work Performed)

It means actual cost incurred in performing the Actual Percentage Completion

Therefore as per Question:

60% of the man-hours were spent by the end of the 5th month : 12,000 * 60% * 60 = $ 432,000.00

40% of the materials were consumed by the end of the 5th month : 250,000 * 40% = 100,000.00

Total ACWP = $ 532,000

5. SV (Schedule Variance)

BCWP - BCWS

$ 339,500.00 - $ 776,000.00

($ 436,500.00)

6. CV (Cost Variance)

BCWP - ACWP

$ 339,500.00 - $ 532,000

($ 192,500.00)

7. SPI (Schedule Performance Index)

BCWP / BCWS

$ 339,500.00 / $ 776,000.00

43.75 %


Related Solutions

Red Man Construction is constructing a building. Construction began on January 1 and was completed on...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable prepare all entries that are necessary
Red Man Construction is constructing a building. Construction began on January 1 and was completed on...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. what amount of interest should be charged...
You have embark on a genomic library construction project. What is the strategy that you will...
You have embark on a genomic library construction project. What is the strategy that you will be taking to ensure successful cloning of genomics inserts into the pGLO vector - you are well acquainted with this plasmid molecule? You have been provided with a map of the pGLO plasmid. a) Where in the plasmid vector molecule would you insert the genomics fragments that you isolated and what restriction enzymes would you choose? b) how would you determine that indeed you...
You have 60 hours a week available to spend either working or leisure. You can work...
You have 60 hours a week available to spend either working or leisure. You can work at a wage of $5 per hour. Your parents also provide you an allowance of $100 per week, no matter how much you work. Your only source of income is the allowance plus your wage earnings. a) in a carefully labelled diagram, draw your consumption-leisure budget constraint. show an equilibrium where you choose to work 40 hours per week b) in an effort to...
(2) Red Man Construction is constructing a building. Construction began on January 1 and was completed...
(2) Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What amount of interest should be...
Question 1: You are currently evaluating a new project for your company. The project requires an...
Question 1: You are currently evaluating a new project for your company. The project requires an initial investment in equipment RM 90,000 and an investment in working capital of RM10,000 at the beginning (t=0). The project is expected to produce sales revenues of RM120, 000 for three years. Manufacturing costs are estimated to be 60% of the revenues. The asset is depreciated over the project’s life using straight-line depreciation method. At the end of the project (t=3), you can sell...
You are investing in a project that requires an initial investment of $500,000. The project will...
You are investing in a project that requires an initial investment of $500,000. The project will last for 10 years with the following additional cash flows (CF) at the end of each year: If the discount rate is 10%, calculate the payback periods in Excel for both the methods below; Years 1 2 3 4 5 6 7 8 9 10 CF -500,000 80,000 100,000 100,000 120,000 140,000 150,000 150,000 150,000 150,000 a) Payback Method [10] b) Discounted Payback Method...
You are a project manager. You are estimating cash flows of a potential project that requires...
You are a project manager. You are estimating cash flows of a potential project that requires an investment of $250,000 in a machine, including installation cost, and $40,000 in working capital which will be fully captures at the end of the project. The machine has the estimated life of 5 years and will be depreciated vie simplified straight-line method. The project is expected to raise the firm's revenues by $330,000 and costs by $125,000 annually. Since the trend of the...
Project Evaluation This is a comprehensive project evaluation problem bringing together much of what you have...
Project Evaluation This is a comprehensive project evaluation problem bringing together much of what you have learned in this and previous chapters. Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a five-year project. The company bought some...
Project Evaluation. This is a comprehensive project evaluation problem bringing together much of what you have...
Project Evaluation. This is a comprehensive project evaluation problem bringing together much of what you have learned in this and previous chapters. Suppose you have been hired as a financial consultant to Defense Electronics, Inc. (DEI), a large, publicly traded firm that is the market share leader in radar detection systems (RDSs). The company is looking at setting up a manufacturing plant overseas to produce a new line of RDSs. This will be a five-year project. The company bought some...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT