In: Accounting
The capital investment committee of Arches Landscaping Company is considering two capital investments. The estimated income from operations and net cash flows from each investment are as follows:
Front-End Loader | Greenhouse | |||||||||
Year | Income from Operations |
Net Cash Flow |
Income from Operations |
Net Cash Flow |
||||||
1 | $35,700 | $116,000 | $75,000 | $186,000 | ||||||
2 | 35,700 | 116,000 | 57,000 | 157,000 | ||||||
3 | 35,700 | 116,000 | 29,000 | 110,000 | ||||||
4 | 35,700 | 116,000 | 12,000 | 75,000 | ||||||
5 | 35,700 | 116,000 | 5,500 | 52,000 | ||||||
Total | $178,500 | $580,000 | $178,500 | $580,000 |
Each project requires an investment of $420,000. Straight-line depreciation will be used, and no residual value is expected. The committee has selected a rate of 10% for purposes of the net present value analysis.
Present Value of $1 at Compound Interest | |||||
Year | 6% | 10% | 12% | 15% | 20% |
1 | 0.943 | 0.909 | 0.893 | 0.870 | 0.833 |
2 | 0.890 | 0.826 | 0.797 | 0.756 | 0.694 |
3 | 0.840 | 0.751 | 0.712 | 0.658 | 0.579 |
4 | 0.792 | 0.683 | 0.636 | 0.572 | 0.482 |
5 | 0.747 | 0.621 | 0.567 | 0.497 | 0.402 |
6 | 0.705 | 0.564 | 0.507 | 0.432 | 0.335 |
7 | 0.665 | 0.513 | 0.452 | 0.376 | 0.279 |
8 | 0.627 | 0.467 | 0.404 | 0.327 | 0.233 |
9 | 0.592 | 0.424 | 0.361 | 0.284 | 0.194 |
10 | 0.558 | 0.386 | 0.322 | 0.247 | 0.162 |
Required:
1a. Compute the average rate of return for each investment. If required, round your answer to one decimal place.
Average Rate of Return | |
Front-End Loader | % |
Greenhouse | % |
1b. Compute the net present value for each investment. Use the present value of $1 table above. If required, use the minus sign to indicate a negative net present value.
Front-End Loader | Greenhouse | |
Present value of net cash flow | $ | $ |
Amount to be invested | $ | $ |
Net present value | $ | $ |
2. Prepare a brief report for the capital investment committee, advising it on the relative merits of the two investments.
The front-end loader has a net present value because cash flows occur in time compared to the greenhouse. Thus, if only one of the two projects can be accepted, the would be the more attractive.
Requirement-1(a) |
Front-End Loader |
Average rate of return = Average annual net profit / Average Investment |
= 35,700 / 210,000 |
= 0.17 x 100 = 17% |
Average annual net profit = total net profit / useful life |
= 178,500/ 5 |
= 35,700 |
Average investment = Initial Investment + salvage value / 2 |
= 420,000 + 0 / 2 |
= 210,000 |
Greenhouse |
Average rate of return = Average annual net profit / Average Investment |
= 35,700 / 210,000 |
= 0.17 x 100 = 17% |
Average annual net profit = total net profit / useful life |
= 178,500/ 5 |
= 35,700 |
Average investment = Initial Investment + salvage value / 2 |
= 420,000 + 0 / 2 |
= 210,000 |
Average rate of return |
|
Front-End Loader |
17% |
Greenhouse |
17% |
Requirement-1(b) |
|||
Front-End Loader |
|||
Year |
cash flow |
Discount factor (10%) |
discounted cash flow |
1 |
116,000 |
0.909 |
105444 |
2 |
116,000 |
0.826 |
95816 |
3 |
116,000 |
0.751 |
87116 |
4 |
116,000 |
0.683 |
79228 |
5 |
116,000 |
0.621 |
72036 |
Total net present value |
439640 |
Front-End Loader |
NPV = present value - initial investment |
= 439,640 - 420,000 |
= 19,640 |
Greenhouse |
|||
Year |
cash flow |
Discount factor (10%) |
discounted cash flow |
1 |
186,000 |
0.909 |
169074 |
2 |
157,000 |
0.826 |
129682 |
3 |
110,000 |
0.751 |
82610 |
4 |
75,000 |
0.683 |
51225 |
5 |
52,000 |
0.621 |
32292 |
Total net present value |
464883 |
Greenhouse |
NPV = present value - initial investment |
= 464,833 - 420,000 |
= 44,833 |
Front-End Loader |
Greenhouse |
|
present value of net cash flow |
439,640 |
464,833 |
Amount to be invested |
420,000 |
420,000 |
net present value |
19,640 |
44,833 |
Requirement-2
Average rate of return of both the projects are equal but Net present value of Greenhouse is higher than Front-End Loader so, the company should accept the project of Greenhouse.