In: Finance
Your company has been approached to bid on a contract to sell 3,700 voice recognition (VR) computer keyboards a year for four years. Due to technological improvements, beyond that time they will be outdated and no sales will be possible. The equipment necessary for the production will cost $3.3 million and will be depreciated on a straight-line basis to a zero salvage value. Production will require an investment in net working capital of $90,000 to be returned at the end of the project, and the equipment can be sold for $270,000 at the end of production. Fixed costs are $635,000 per year, and variable costs are $150 per unit. In addition to the contract, you feel your company can sell 9,000, 9,900, 12,000, and 9,300 additional units to companies in other countries over the next four years, respectively, at a price of $285. This price is fixed. The tax rate is 40 percent, and the required return is 10 percent. Additionally, the president of the company will undertake the project only if it has an NPV of $100,000. |
What bid price should you set for the contract? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
Solution
Bid Price | $ 279.22 | ||||
0 | 1 | 2 | 3 | 4 | |
Unit | 9000 | 9900 | 12000 | 9300 | |
Investment | -$ 3,300,000 | ||||
NWC | -$ 90,000 | $ 90,000 | |||
Salvage | $ 270,000 | ||||
Sales | $ 3,598,114 | $ 3,854,614 | $ 4,453,114 | $ 3,683,614 | |
VC | -$1,905,000 | -$2,040,000 | -$2,355,000 | -$1,950,000 | |
FC | -$ 635,000 | -$ 635,000 | -$ 635,000 | -$ 635,000 | |
Depreciation | -$ 825,000 | -$ 825,000 | -$ 825,000 | -$ 825,000 | |
EBT | $ 233,114 | $ 354,614 | $ 638,114 | $ 273,614 | |
Tax (40%) | -$ 93,246 | -$ 141,846 | -$ 255,246 | -$ 109,446 | |
Profits | $ 139,868 | $ 212,768 | $ 382,868 | $ 164,168 | |
Cash Flows | -$ 3,390,000 | $ 964,868 | $ 1,037,768 | $ 1,207,868 | $ 1,241,168 |
NPV | $ 100,037 |
We need to find the bid price such that the NPV of the project is equal to $100,000
Sales (year 1) = 9,000 x 285 + 3,700 x Bid Price
Variable Cost VC (year 1) = 150 x (9000 + 3700) = 1,905,000
FC = 635,000
Depreciation = 3,300,000 / 4 = 825,000
Profits = EBT x (1 - tax rate)
Cash Flows = Profits + Depreciation + Investment + NWC + After-tax salvage value
NPV = NPV(10%, CF1...CF4) + CF0
Start with a bid price of $285.00 and calculate the NPV of the project. If it is much higher than $100,000 decrease the bid price and recalculate the NPV. Using trial and error method or excel solver, we get at bid price = $279.22, the NPV of $100,037.
Hence, you should set a bid price of $279.22 for the contract.