Question

In: Accounting

Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...

Av-Y6 Company operates three service departments,
administration, maintenance, and personnel and
two production departments, assembly and packaging.

Information for the three service departments is
given below:

                              Admin      Maint      Person
Directly traced overhead    $65,000     $33,000    $74,000 
Square feet occupied          2,000       3,500      3,000
Number of employees              42          24         30  
Maintenance hours             2,500       2,000      4,000

Information for the two production departments is
given below:

                              Assembly          Packaging
Directly traced overhead      $167,030           $114,090  
Square feet occupied             2,100              1,400
Number of employees                 36                 18 
Maintenance hours                6,400              1,600
Direct labor hours              20,000             18,000
Machine hours                   10,000             15,000

Av-Y6 Company uses the sequential method of allocation.
Information on the allocation bases and activities for
each department are given below.

Administration department costs are allocated on the basis
of square feet occupied, maintenance department costs are
allocated on the basis of maintenance hours, and personnel
department costs are allocated on the basis of number of
employees. In the second stage, assembly department overhead
costs are assigned to products based on machine hours.

Calculate the pre-determined overhead rate based on machine
hours used in the assembly department.

Solutions

Expert Solution

we shall first allocate cost to product department in sequence given

Admin Main Person Assembly packaging Total allocation base
Direct cost $65,000 $33,000 $74,000 $167,030
Administration cost 22,750[3500/10,000]*65000 $19,500[3000/10000]*65000 $13,650[$65,000*2,100]/10,000 square feet 10,000[3500+3000+2100+1400]
Total Maintenace cost to be allocated $55,750[$33,000+22,750]
Main cost $18,583[$55,750/12,000]*4000 $29,733[$55,750/12,000]*6,400 Maintenance hours 12000[4000+6,400+1,600]
Total Personnel cost to be allocated $112,083[$18,583+$19,500+$74,000]
Personnel cost $74,722[$112,083/54]*36 $37,361[18/54]*112,083 54 Number of employees [36+18]
Total cost $285,135[74722+29733+13650+167030]
Predetermined OH Rte(Assembly)=Total cost/Machine hour
=$285,135/10,000
=$28.51 per MH

Please upvote if you find this helpful.Incase of query please comment.


Related Solutions

Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $68,000 $46,000 $77,000 Square feet occupied 2,000 3,500 3,000 Number of employees 36 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,060 $120,090 Square feet occupied 2,100 1,400 Number of employees 42 18 Maintenance hours...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $68,000 $46,000 $77,000 Square feet occupied 2,000 3,500 3,000 Number of employees 36 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,060 $120,090 Square feet occupied 2,100 1,400 Number of employees 42 18 Maintenance hours...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and Maintenance). During July, the following costs and service department usage ratios were recorded. Supplying Department Using Department Engineering Administration Maintenance Fabrication Assembly Engineering 0 40 % 0 15 % 45 % Administration 20 % 0 25 % 45 % 10 % Maintenance 0 30 % 0 15 % 55 % Direct cost $ 42,000 $ 248,550 $ 45,000 $ 230,000 $ 80,000 Required: Allocate...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and Maintenance). During July, the following costs and service department usage ratios were recorded. Supplying Department Using Department Engineering Administration Maintenance Fabrication Assembly Engineering 0 40 % 0 15 % 45 % Administration 20 % 0 25 % 45 % 10 % Maintenance 0 30 % 0 15 % 55 % Direct cost $ 42,000 $ 248,550 $ 45,000 $ 230,000 $ 80,000 Required: Allocate...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and...
Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and Maintenance). During July, the following costs and service department usage ratios were recorded. Supplying Department Using Department Engineering Administration Maintenance Fabrication Assembly Engineering 0 50 % 0 10 % 40 % Administration 10 % 0 20 % 50 % 20 % Maintenance 0 50 % 0 20 % 30 % Direct cost $ 24,000 $ 179,500 $ 25,000 $ 185,000 $ 50,000    Required:...
ABC Company operates two service departments, quality control and maintenance, and two production departments, cutting and...
ABC Company operates two service departments, quality control and maintenance, and two production departments, cutting and finishing. Service department costs are allocated to production departments using a sequential two-stage allocation method. Quality control department costs are allocated on the basis of number of inspections and maintenance department costs are allocated on the basis of machine hours. In the second stage, departmental overhead rates for the two production departments are calculated using direct labor hours as the activity for each department....
1.Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and...
1.Midland Resources has two production departments (Fabrication and Assembly) and three service departments (Engineering, Administration, and Maintenance). During July, the following costs and service department usage ratios were recorded: Supplying Department Using Department Engineering Administration Maintenance Fabrication Assembly Engineering 0 50 % 0 10 % 40 % Administration 10 % 0 20 % 50 % 20 % Maintenance 0 20 % 0 20 % 60 % Direct cost $ 22,000 $ 193,300 $ 25,000 $ 180,000 $ 50,000    Required:...
a. Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and...
a. Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and Cafeteria. Direct costs for each department and the proportion of service costs used by the various departments for the month of August follow: Proportion of Services Used by Department Direct Costs Maintenance Cafeteria Machining Assembly Machining $ 98,000 Assembly 74,400 Maintenance 46,000 — 0.2 0.6 0.2 Cafeteria 37,000 0.6 — 0.1 0.3 Exercise 11-27 (Algo) Cost Allocation: Direct Method (LO 11-2) Required: Compute the...
Boston Corporation has two production departments, Assembly and Machining, and two service departments, Personnel and Cafeteria....
Boston Corporation has two production departments, Assembly and Machining, and two service departments, Personnel and Cafeteria. Direct costs for each department and the proportion of service costs used by the various departments for the month of July, 2020 are as follows: Proportion of Services Used by: Department Direct costs Personnel Cafeteria Machining Assembly Personnel $ 30,000 0.40 0.30 0.30 Cafeteria $ 50,000 0.20 0.50 0.30 Machining $ 80,000 Assembly $ 70,000 Required: (use ANOTHER sheet to show your work AND...
Frederick Company has two service departments (Cafeteria Services & Maintenance). Frederick has two production departments (Assembly...
Frederick Company has two service departments (Cafeteria Services & Maintenance). Frederick has two production departments (Assembly Department & Packaging Department.) Frederick uses a step allocation method where Cafeteria Services is allocated to all departments and Maintenance Services is allocated to the production departments. All allocations are based on total employees. Cafeteria Services has costs of $250,000 and Maintenance has costs of $280,000 before any allocations. What amount of Maintenance total cost is allocated to the Packaging Department? (round to closest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT