Av-Y6 Company operates three service departments,
administration, maintenance, and personnel and
two production departments, assembly and packaging.
Information for the three service departments is
given below:
Admin Maint Person
Directly traced overhead $65,000 $33,000 $74,000
Square feet occupied 2,000 3,500 3,000
Number of employees 42 24 30
Maintenance hours 2,500 2,000 4,000
Information for the two production departments is
given below:
Assembly Packaging
Directly traced overhead $167,030 $114,090
Square feet occupied 2,100 1,400
Number of employees 36 18
Maintenance hours 6,400 1,600
Direct labor hours 20,000 18,000
Machine hours 10,000 15,000
Av-Y6 Company uses the sequential method of allocation.
Information on the allocation bases and activities for
each department are given below.
Administration department costs are allocated on the basis
of square feet occupied, maintenance department costs are
allocated on the basis of maintenance hours, and personnel
department costs are allocated on the basis of number of
employees. In the second stage, assembly department overhead
costs are assigned to products based on machine hours.
Calculate the pre-determined overhead rate based on machine
hours used in the assembly department.
we shall first allocate cost to product department in sequence given
| Admin | Main | Person | Assembly | packaging | Total allocation base | |
| Direct cost | $65,000 | $33,000 | $74,000 | $167,030 | ||
| Administration cost | 22,750[3500/10,000]*65000 | $19,500[3000/10000]*65000 | $13,650[$65,000*2,100]/10,000 | square feet 10,000[3500+3000+2100+1400] | ||
| Total Maintenace cost to be allocated | $55,750[$33,000+22,750] | |||||
| Main cost | $18,583[$55,750/12,000]*4000 | $29,733[$55,750/12,000]*6,400 | Maintenance hours 12000[4000+6,400+1,600] | |||
| Total Personnel cost to be allocated | $112,083[$18,583+$19,500+$74,000] | |||||
| Personnel cost | $74,722[$112,083/54]*36 | $37,361[18/54]*112,083 | 54 Number of employees [36+18] | |||
| Total cost | $285,135[74722+29733+13650+167030] |
Predetermined OH Rte(Assembly)=Total cost/Machine hour
=$285,135/10,000
=$28.51 per MH