In: Finance
You are analyzing the following two projects and have developed the following information.
Project A | Project B
Year | Cash flow | Cash flow
0 | -$50,000 | -$50,000
1 | $31,000 | $42,000
2 | $26,000 | $21,000
3 | $27,000 | $18,000
5. What is the crossover rate of the two projects?
6. Project A and B are mutually exclusive. Which project(s) should be chosen if the required return is 8%? Why?
7. Project A and B are independent. Which project(s) should be chosen if the required return is 8%? Why?
Crossover rate of the two projects;-
NPV of Project A = 31000/(1+r) + 26000/(1+r)^2 + 27000/(1+r)^3 - 50000
NPV of Project B = 42000/(1+r) + 21000/(1+r)^2 + 18000/(1+r)^3 - 50000
To determine crossover rate, NPV of both project should be compared i.e, NPV of project A = NPV of Project B
-> 31000/(1+r) + 26000/(1+r)^2 + 27000/(1+r)^3 - 50000 = 42000/(1+r) + 21000/(1+r)^2 + 18000/(1+r)^3 - 50000
-> by mutipling (1+r)^3 & dividing 1000 on both sides,
we get 31*(1+r)^2 + 26*(1+r) + 27 - 50*(1+r)^3 = 42*(1+r)^2 + 21*(1+r) + 18 - 50*(1+r)^3
-> 31*(1+2r+r^2) + 26*(1+r) + 27 = 42*(1+2r+r^2) + 21*(1+r) +18 - 50*(1+r)^3 + 50*(1+r)^3
-> 31+62r+31r^2+26+26r+27 = 42+84r+42r^2+21+21r+18
-> 0 = 42+84r+42r^2+21+21r+18-31-62r-31r^2-26-26r-27
-> 0 = -3+17r+11r^2 : 0 = 11r^2+17r-3 By solving this equation we will get r i.e. crossover rate
Project A and B are mutually exclusive. Which project(s) should be chosen if the required return is 8%?
Year | Project A cashflow | Project B cashflow | Present value factor @ 8% | Discounted cashflow A | Discounted cashflow B |
0 | $ (50,000) | $ (50,000) | 1.0000 | $ (50,000) | $ (50,000) |
1 | $ 31,000 | $ 42,000 | 0.9259 | $ 28,704 | $ 38,889 |
2 | $ 26,000 | $ 21,000 | 0.8573 | $ 22,291 | $ 18,004 |
3 | $ 27,000 | $ 18,000 | 0.7938 | $ 21,433 | $ 14,289 |
NPV | $ 22,428 | $ 21,182 |
Project A should should be chosen because it gives more NPV than project B.
Project A and B are independent. Which project(s) should be chosen if the required return is 8%? Why?
Both the project can be selected because it gives positive NPV. Now also since NPV of project A is more than NPV of project B, we 1st select project A & then project B.