Question

In: Finance

You are analyzing the following two projects and have developed the following information. Project A |...

You are analyzing the following two projects and have developed the following information.

Project A | Project B

Year | Cash flow | Cash flow

0 | -$50,000 | -$50,000

1 | $31,000 | $42,000

2 | $26,000 | $21,000

3 | $27,000 | $18,000

5. What is the crossover rate of the two projects?

6. Project A and B are mutually exclusive. Which project(s) should be chosen if the required return is 8%? Why?

7. Project A and B are independent. Which project(s) should be chosen if the required return is 8%? Why?

Solutions

Expert Solution

Crossover rate of the two projects;-

NPV of Project A = 31000/(1+r) + 26000/(1+r)^2 + 27000/(1+r)^3 - 50000

NPV of Project B = 42000/(1+r) + 21000/(1+r)^2 + 18000/(1+r)^3 - 50000

To determine crossover rate, NPV of both project should be compared i.e, NPV of project A = NPV of Project B

-> 31000/(1+r) + 26000/(1+r)^2 + 27000/(1+r)^3 - 50000 = 42000/(1+r) + 21000/(1+r)^2 + 18000/(1+r)^3 - 50000

-> by mutipling (1+r)^3 & dividing 1000 on both sides,

we get 31*(1+r)^2 + 26*(1+r) + 27 - 50*(1+r)^3 = 42*(1+r)^2 + 21*(1+r) + 18 - 50*(1+r)^3

-> 31*(1+2r+r^2) + 26*(1+r) + 27 = 42*(1+2r+r^2) + 21*(1+r) +18 - 50*(1+r)^3 + 50*(1+r)^3

-> 31+62r+31r^2+26+26r+27 = 42+84r+42r^2+21+21r+18

-> 0 = 42+84r+42r^2+21+21r+18-31-62r-31r^2-26-26r-27

-> 0 = -3+17r+11r^2 : 0 = 11r^2+17r-3 By solving this equation we will get r i.e. crossover rate

Project A and B are mutually exclusive. Which project(s) should be chosen if the required return is 8%?

Year Project A cashflow Project B cashflow Present value factor @ 8% Discounted cashflow A Discounted cashflow B
0 $        (50,000) $ (50,000)                 1.0000 $      (50,000) $       (50,000)
1 $         31,000 $       42,000                 0.9259 $       28,704 $        38,889
2 $         26,000 $       21,000                 0.8573 $       22,291 $        18,004
3 $         27,000 $       18,000                 0.7938 $       21,433 $        14,289
NPV $      22,428 $      21,182

Project A should should be chosen because it gives more NPV than project B.

Project A and B are independent. Which project(s) should be chosen if the required return is 8%? Why?

Both the project can be selected because it gives positive NPV. Now also since NPV of project A is more than NPV of project B, we 1st select project A & then project B.


Related Solutions

Desai Industries is analyzing an average risk project, and the following data have been developed Unit...
Desai Industries is analyzing an average risk project, and the following data have been developed Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also beconstant, but variable costs should rise with inflation. The project should last for 3 years, it will bedepreciated on a straight line basis, and there will be no salvage value. This is just one of many projectsfor the firm, so any losses can be used to offset gains...
You are analyzing a project and have prepared the following data:                                &n
You are analyzing a project and have prepared the following data:                                     Year                             Cash flow                                        0                                 -$169,000                                        1                                  $ 46,200                                        2                                  $ 87,300                                        3                                  $ 41,000                                        4                                  $ 39,000            Required payback period        2.5 years            Required AAR                              7.25 percent                   Required return                                   8.50 percent C-1 What is the payback period? Should you accept the project? C-2 What is the profitability index of...
Below information is for Question 1 & 2: You are analyzing a project and have gathered...
Below information is for Question 1 & 2: You are analyzing a project and have gathered the following data: Year Cash Flow o -$175,000 1 $56,000 2 $61,800 3 $72,000 4 $75,000 Required payback period of 2.5 year Required return 14.5% 1. Based on the net present value of__________, you should_________the project. (please show work). A. $12,995.84; accept B. -$15,030.75; reject C. -$12,995.84; reject D. $9,283.60; accept 2. Based on the payback period of ______ years for this project, you...
Waste Management Inc. is analyzing an average-risk project, and the following data have been developed. Unit...
Waste Management Inc. is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price will increase with inflation. Fixed costs will also be constant, but variable costs will rise with inflation. The project should last for 3 years, and there will be no salvage value. This is just one project for the firm, so any losses can be used to offset gains on other firm projects. What is the project's...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. No change in net operating working capital wouThis is just one of many projects for the firm, so...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years. Under the new tax law, the equipment for the project is eligible for 100% bonus depreciation, so it will be fully depreciated at t = 0. At the end of the project’s life,...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years. Under the new tax law, the equipment for the project is eligible for 100% bonus depreciation, so it will be fully depreciated at t = 0. At the end of the project’s life,...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales...
Poulsen Industries is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. No change in net operating working capital would be required. This is just one of many projects for...
Shultz Business Systems is analyzing an average-risk project, and the following data have been developed. Unit...
Shultz Business Systems is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. This is just one of many projects for the firm, so any losses can be used to...
Shultz Business Systems is analyzing an average-risk project, and the following data have been developed. Unit...
Shultz Business Systems is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price should increase with inflation. Fixed costs will also be constant, but variable costs should rise with inflation. The project should last for 3 years, it will be depreciated on a straight-line basis, and there will be no salvage value. This is just one of many projects for the firm, so any losses can be used to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT