In: Finance
Giant Equipment Ltd. is considering two projects to invest next year. Both projects have the same start-up costs. Project A will produce annual cash flows of $42,000 at the beginning of each year for eight years. Project B will produce cash flows of $48,000 at the end of each year for seven years. The company requires a 12% return. Required: a) Which project should the company select and why? b) Which project should the company select if the interest rate is 14% at the cash flows in Project B is also at the beginning of each year?
Question a: | ||||||
Calculation of NPV of the Projects | ||||||
Year | Project A | Project B | ||||
Cash Flow | Discount Factor@12% | Discounted Cash Flows | Cash Flow | Discount Factor@12% | Discounted Cash Flows | |
A | B | C = 1/(1+12%)^A | D = B*C | E | F = 1/(1+12%)^A | G = E*F |
0 | 42000 | 1 | 42000 | 1 | 0 | |
1 | 42000 | 0.892857143 | 37500 | 48000 | 0.892857143 | 42857.14286 |
2 | 42000 | 0.797193878 | 33482.1429 | 48000 | 0.797193878 | 38265.30612 |
3 | 42000 | 0.711780248 | 29894.7704 | 48000 | 0.711780248 | 34165.4519 |
4 | 42000 | 0.635518078 | 26691.7593 | 48000 | 0.635518078 | 30504.86776 |
5 | 42000 | 0.567426856 | 23831.9279 | 48000 | 0.567426856 | 27236.48907 |
6 | 42000 | 0.506631121 | 21278.5071 | 48000 | 0.506631121 | 24318.29382 |
7 | 42000 | 0.452349215 | 18998.667 | 48000 | 0.452349215 | 21712.76234 |
NPV | 233677.775 | 219060.3139 | ||||
NPV of Project A is higher than Project B | ||||||
Hence Project A should be selected | ||||||
Note: | ||||||
Cash Flow beginning of Year 1 means cash flow at year 0 | ||||||
Cash Flow beginning of Year 2 means cash flow at year 1 | ||||||
Question b: | ||||||
Calculation of NPV of the Projects | ||||||
Year | Project A | Project B | ||||
Cash Flow | Discount Factor@12% | Discounted Cash Flows | Cash Flow | Discount Factor@12% | Discounted Cash Flows | |
A | B | C = 1/(1+12%)^A | D = B*C | E | F = 1/(1+12%)^A | G = E*F |
0 | 42000 | 1 | 42000 | 48000 | 1 | 48000 |
1 | 42000 | 0.892857143 | 37500 | 48000 | 0.892857143 | 42857.14286 |
2 | 42000 | 0.797193878 | 33482.1429 | 48000 | 0.797193878 | 38265.30612 |
3 | 42000 | 0.711780248 | 29894.7704 | 48000 | 0.711780248 | 34165.4519 |
4 | 42000 | 0.635518078 | 26691.7593 | 48000 | 0.635518078 | 30504.86776 |
5 | 42000 | 0.567426856 | 23831.9279 | 48000 | 0.567426856 | 27236.48907 |
6 | 42000 | 0.506631121 | 21278.5071 | 48000 | 0.506631121 | 24318.29382 |
7 | 42000 | 0.452349215 | 18998.667 | 0 | 0.452349215 | 0 |
NPV | 233677.775 | 245347.5515 | ||||
NPV of Project B is higher than Project A | ||||||
Hence Project B should be selected | ||||||
Note: | ||||||
Cash Flow beginning of Year 1 means cash flow at year 0 | ||||||
Cash Flow beginning of Year 2 means cash flow at year 1 |