Question

In: Accounting

“I’m not sure we should lay out $295,000 for that automated welding machine,” said Jim Alder,...

“I’m not sure we should lay out $295,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $83,000 for software and installation, and another $46,800 per year just to maintain the thing. In addition, the manufacturer admits it would cost $46,000 more at the end of three years to replace worn-out parts.”

“I admit it’s a lot of money,” said Franci Rogers, the controller. “But you know the turnover problem we’ve had with the welding crew. This machine would replace six welders at a cost savings of $113,000 per year. And we would save another $7,400 per year in reduced material waste. When you figure that the automated welder would last for six years, I’m sure the return would be greater than our 19% required rate of return.”

“I’m still not convinced,” countered Mr. Alder. “We can only get $16,500 scrap value out of our old welding equipment if we sell it now, and in six years the new machine will only be worth $29,000 for parts. But have your people work up the figures and we’ll talk about them at the executive committee meeting tomorrow.”

Click here to view Exhibit 12B-1 and Exhibit 12B-2, to determine the appropriate discount factor(s) using tables.

Required:

1. Compute the annual net cost savings promised by the automated welding machine.

2a. Using the data from (1) above and other data from the problem, compute the automated welding machine’s net present value.

2b. Would you recommend purchasing the automated welding machine?

3. Assume that management can identify several intangible benefits associated with the automated welding machine, including greater flexibility in shifting from one type of product to another, improved quality of output, and faster delivery as a result of reduced throughput time. What minimum dollar value per year would management have to attach to these intangible benefits in order to make the new welding machine an acceptable investment?

Solutions

Expert Solution

1
Reduction in labor costs 113000
Reduction in material waste 7400
Total 120400
Less increased maintenance costs 46800
Annual net cost savings 73600
2a
Now 1 2 3 4 5 6
Cost of machine -295000
Software and installation -83000
Salvage value of old equipment 16500
Annual net cost savings 73600 73600 73600 73600 73600 73600
Replacement of parts -46000
Salvage value of new machine 29000
Total cash flows -361500 73600 73600 27600 73600 73600 102600
Discount factor (19%) 1 0.840 0.706 0.593 0.499 0.419 0.352
Present value -361500 61824 51962 16367 36726 30838 36115
Net present value -127668
2b
NO, as Net Present value is negative
3
Negative Net present value to offset 127668
Divide by PV factor 3.410 =(1-(1.19)^-6)/0.19
Annual intangible benefits 37439 or 37450

Related Solutions

“I’m not sure we should lay out $335,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $335,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $91,000 for software and installation, and another $4,700 every month just to maintain the thing. In addition, the manufacturer admits that it would cost $54,000 more at the end of three years to replace worn-out parts.”       “I admit it’s a lot of money,” said Franci Rogers, the...
“I’m not sure we should lay out $325,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $325,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $89,000 for software and installation, and another $54,000 per year just to maintain the thing. In addition, the manufacturer admits it would cost $52,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $78,000 for software and installation, and another $40,800 per year just to maintain the thing. In addition, the manufacturer admits it would cost $41,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $78,000 for software and installation, and another $40,800 per year just to maintain the thing. In addition, the manufacturer admits it would cost $41,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $300,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $300,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $84,000 for software and installation, and another $48,000 per year just to maintain the thing. In addition, the manufacturer admits it would cost $47,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $235,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $235,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $76,000 for software and installation, and another $38,400 per year just to maintain the thing. In addition, the manufacturer admits it would cost $39,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $330,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $330,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $90,000 for software and installation, and another $55,200 per year just to maintain the thing. In addition, the manufacturer admits it would cost $53,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $265,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $75,000 for software and installation, and another $37,200 per year just to maintain the thing. In addition, the manufacturer admits it would cost $38,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $360,000 for that automated welding machine,” said Jim Alder,...
“I’m not sure we should lay out $360,000 for that automated welding machine,” said Jim Alder, president of the Superior Equipment Company. “That’s a lot of money, and it would cost us $96,000 for software and installation, and another $62,400 per year just to maintain the thing. In addition, the manufacturer admits it would cost $59,000 more at the end of three years to replace worn-out parts.” “I admit it’s a lot of money,” said Franci Rogers, the controller. “But...
“I’m not sure we should lay out $290,000 for that automated welding machine,” said Jim Alder....
“I’m not sure we should lay out $290,000 for that automated welding machine,” said Jim Alder. “That’s a lot of money, and it would cost us $82,000 for software & installation, & another $3,800 every month just to maintain. In addition, the manufacturer admits that it would cost $45,000 more at the end of three years to replace worn-out parts.” Franci Rogers, the controller. “But you know the turnover problem we’ve had with the welding crew. This machine would replace...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT