In: Economics
1) The following table describes the costs of production for a firm.
Quantity | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
Average Total Cost | - | 600 | 325 | 240 | 205 | 196 | 200 |
TVC | 0 | ? | ? | 220 | ? | ? | ? |
What is the average variable cost at a production level of 4 units?
Group of answer choices
a 185
b 80
c 100
d 320
e None of these answers
2)
Suppose a firm faces the following costs:
Quantity | 0 | 1 | 2 | 3 | 4 | 5 |
TFC | 400 | 400 | 400 | 400 | 400 | 400 |
TC | 400 | 600 | 700 | 850 | 1100 | 1400 |
What is the average variable cost at a quantity of 4 units?
Group of answer choices
a 175
b 375
c 275
d 100
1) It is given that at Quantity= 3;
Average Total Cost = 240 and Total Variable cost = 220
Average Total Cost is calculated as :
Total Cost/Quantity
And Total Cost = Average Total cost× Quantity
Thus, at Quantity= 3;
Total Cost = 240 × 3 = 720
Now, We know that Total Cost= Total Variable cost+ Total Fixed cost
Given, At Quantity= 3;
Total Variable cost = 220 and Total cost= 720( as Calculated)
As, Total cost = Total Variable cost+ Total Fixed cost
Thus, 720 = 220 + Total Fixed cost
=> Total Fixed cost = 720 - 220 = 500
As Fixed cost is same at all levels of output/Quantity ; therefore total Fixed cost= 500 for all levels of output.
Now, To Calculate Total Variable cost first Total Cost is to be calculated which is calculated as Average Total cost× Quantity
And Total Fixed cost = 500
And Total Variable cost = Total cost- Total Fixed cost
Therefore at
Q =1,TC = 600×1 = 600,TFC = 500,TVC = 600-500=100
Q=2,TC = 325× 2= 650,TFC =500,TVC= 650-500=150
Q= 3,TC= 240×3 =720,TFC=500,TVC = 720-500= 220
Q= 4,TC =205×4 =820,TFC=500,TVC=820-500=320
Q= 5, TC= 196×5 =980,TFC=500,TVC=980-500=480
Q= 6,TC= 200×6 = 1200,TFC=500,TVC=1200-500= 700
Now, Average variable cost is calculated as Total Variable cost/Quantity.
Thus , At Q= 4;
Average Variable cost= 320/4= 80
Therefore,the correct answer is Option B
2. At Q = 4,
Given , Total cost= 1100
And Total Fixed cost = 400
We know,that
Total cost = Total Variable cost+ Total Fixed cost
=> Total Variable cost= Total cost - Total Fixed cost
So, At Q= 4
Total Variable cost = 1100 - 400 = 700
Also, Average variable cost is calculated as:
Total Variable cost/ Quantity
Therefore, Average variable cost at Q= 4 is:
700/4 = 175
Therefore,the correct answer is Option A.