Question

In: Finance

Tri-Star, Inc., has the following mutually exclusive projects. a. Calculate the NPV, IRR, MIRR, TPB and...

Tri-Star, Inc., has the following mutually exclusive projects.

a. Calculate the NPV, IRR, MIRR, TPB and DPB for the projects.

b. Suppose the company's traditional payback period cutoff is two years. Which of these two projects should be chosen on that basis? Explain why

c. Suppose the company uses the NPV rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent? Explain why

d. Suppose the company uses the IRR rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent? Explain why

e. Suppose the company uses the MIRR rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent? Explain why

Year Project A Project B
0 (15,300) (10,700)
1 8,700 5,300
2 7,400 4,300
3 3,100 4,800

Solutions

Expert Solution

1). NPV for Project A:

Formula Year (n) 0 1 2 3
Cash flow    -15,300.00     8,700.00 7,400.00 3,100.00
1/(1+d)^n Discount factor @15%              1.000           0.870         0.756         0.658
Cash flow*discount factor Discounted cash flow    -15,300.00     7,565.22 5,595.46 2,038.30
Sum of all discounted cash flows NPV          -101.02

2). NPV for Project B:

Formula Year (n) 0 1 2 3
Cash flow -10,700.00 5,300.00 4,300.00     4,800.00
1/(1+d)^n Discount factor @15%            1.000         0.870         0.756           0.658
Cash flow*discount factor Discounted cash flow -10,700.00 4,608.70 3,251.42     3,156.08
Sum of all discounted cash flows NPV          316.19

3). IRR for Project A = 14.54%

4). IRR for Project B = 16.81%

5). MIRR for Project A (using the required rate of return 15% as the re-investment rate) = 14.75%

6). MIRR for Project B (using the required rate of return 15% as the re-investment rate) = 16.12%

Note: IRR and MIRR has been calculted using excel functions IRR & MIRR.

7). Payback Period (PB) for Project A:

Formula Year (n) 0 1 2 3
Cash flow    -15,300.00     8,700.00 7,400.00 3,100.00
Cumulative cash flow          -15,300 -6,600.00      800.00 3,900.00

Cumulative cash flow turns positive in Year 2, so fraction of the year = last year's cumulative cash flow/this year's cash flow

= 6,600/7,400 = 0.89

Thus, PB = 1 + 0.89 = 1.89 years

8).  Payback Period (PB) for Project B:

Formula Year (n) 0 1 2 3
Cash flow -10,700.00    5,300.00    4,300.00     4,800.00
Cumulative cash flow -10,700.00 -5,400.00 -1,100.00     3,700.00

Cumulative cash flow turns positive in Year 3, so fraction of the year = last year's cumulative cash flow/this year's cash flow

= 1,100/4,800 = 0.23

Thus, PB = 2 + 0.23 = 2.23 years

9). Discounted Payback Period (DPB) for Project A:

Formula Year (n) 0 1 2 3
Cash flow    -15,300.00     8,700.00    7,400.00 3,100.00
1/(1+d)^n Discount factor @15%              1.000           0.870          0.756         0.658
Cash flow*discount factor Discounted cash flow    -15,300.00     7,565.22    5,595.46 2,038.30
Cumulative discounted cash flow    -15,300.00 -7,734.78 -2,139.32     -101.02

Cumulative discounted cash flow never turns positive within the life of the project so as per DPB, Project A is not viable.

10). Discounted Payback Period (DPB) for Project B:

Formula Year (n) 0 1 2 3
Cash flow -10,700.00    5,300.00    4,300.00     4,800.00
1/(1+d)^n Discount factor @15%            1.000          0.870          0.756           0.658
Cash flow*discount factor Discounted cash flow -10,700.00    4,608.70    3,251.42     3,156.08
Cumulative discounted cash flow -10,700.00 -6,091.30 -2,839.89        316.19

Cumulative discounted cash flow turns positive in Year 3, so fraction of the year = last year's cumulative discounted cash flow/this year's discounted cash flow  

= 2,839.89/3,156.08 = 0.90

Thus, DPB = 2 + 0.90 = 2.9 years.

b). If the company's traditional PB period cutoff is 2 years then Project A should be chosen as it has a PB of 1.89 years.

c). Using NPV, Project B should be chosen since Project A has a negative NPV.

d). Using IRR, Project B should be chosen, since it has a higher IRR compared to Project A.

e). Using MIRR, Project B should be chosen, since it has a higher MIRR compared to Project A.


Related Solutions

Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive...
Please calculate the payback period, IRR, MIRR, NPV, and PI for the following two mutually exclusive projects. The required rate of return is 15% and the target payback is 4 years. Explain which project is preferable under each of the four capital budgeting methods mentioned above: Table 1 Cash flows for two mutually exclusive projects Year Investment A Investment B 0 -$5,000,000 -5,000,000 1 $1,500,000 $1,250,000 2 $1,500,000 $1,250,000 3 $1,500,000 $1,250,000 4 $1,500,000 $1,250,000 5 $1,500,000 $1,250,000 6 $1,500,000...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,800 –$ 9,200 1 8,400 3,900 2 7,000 3,400 3 2,100 5,800 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B Project A If the appropriate discount rate is 10...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 15,000 –$ 10,300 1 9,500 5,000 2 8,100 4,500 3 2,100 6,900 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A ___ years Project B ___ years Based on the payback period, which project should the company accept? Project B or A? Project B Project A If...
​NPV versus IRR [LO1, 5] Bruin, Inc., has identified the following two mutually exclusive projects:
NPV versus IRR [LO1, 5] Bruin, Inc., has identified the following two mutually exclusive projects:a. What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will the company choose if it applies the NPV decision rule?
Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR...
Consider the following two mutually exclusive projects.  Project A has an NPV of $0.5 billion, an IRR of 16% and a payback period of 4 years.  Project B has an NPV of $600 million, and IRR of 15% and a Payback period of 3 years. Which project should be chosen?
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.52 $260 $15 $10 Project L -$1,000 $0 $250 $380 $811.10 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $0 $250 $400 $775.11 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $5 $240 $380 $844.53 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $896.53 $250 $5 $5 Project L -$1,000 $10 $260 $380 $821.65 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT