In: Operations Management
Which of the following should be included in a project charter?
A. Title and objective
B. Funding and major risks
C. Milestone schedule and key deliverables
D. Key assumptions and constraints
E. Approval and reporting requirements
F. All of the above
All of following should be included in a project charter:
✓ F) all of the above
(Project charter is an important document that highlights the title, objectives, deliverables, milestone, budget, and other stated options. It helps the management to understand the project work in a brief way.)