Please show the each calculate step, thank you
A company has identified the following budgeted overhead costs
and budgeted cost drivers for next year:
Activity
Budgeted Activity cost
Cost Driver
Quantity
Material Handling
$120,000
Number of moves
3,000
Ordering costs
70,000
Number of orders
50,000
Maintenance
200,000
Machine hours
80,000
Power
310,000
Kilowatt hours
310,000
Total Activity Cost
$700,000
The following job completed during the year:
Job 400
Direct Materials
$22,000
Direct labor
$6,000
Units completed
4,000
Direct labor...