Problem 9-20 (Algo) Critique a Report; Prepare a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4] TipTop Flight...

Problem 9-20 (Algo) Critique a Report; Prepare a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4]

TipTop Flight School offers flying lessons at a small municipal airport. The school’s owner and manager has been attempting to evaluate performance and control costs using a variance report that compares the planning budget to actual results. A recent variance report appears below:

TipTop Flight School
Variance Report
For the Month Ended July 31
Actual
Results
Planning
Budget
Variances
Lessons 145 140
Revenue $ 33,110 $ 32,200 $ 910 F
Expenses:
Instructor wages 8,510 8,400 110 U
Aircraft depreciation 4,350 4,200 150 U
Fuel 2,470 1,960 510 U
Maintenance 2,010 1,900 110 U
Ground facility expenses 1,465 1,480 15 F
Administration 3,265 3,340 75 F
Total expense 22,070 21,280 790 U
Net operating income $ 11,040 $ 10,920 $ 120 F

After several months of using these reports, the owner has become frustrated. For example, she is quite confident that instructor wages were very tightly controlled in July, but the report shows an unfavorable variance.

The planning budget was developed using the following formulas, where q is the number of lessons sold:

Cost Formulas
Revenue $230q
Instructor wages $60q
Aircraft depreciation $30q
Fuel $14q
Maintenance $500 + $10q
Ground facility expenses $1,200 + $2q
Administration $3,200 + $1q

  
Required:

2. Complete the flexible budget performance report for the school for July. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)

Solutions

Expert Solution


Related Solutions

Problem 9-22 Critique a Report; Prepare a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] TipTop Flight...
Problem 9-22 Critique a Report; Prepare a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] TipTop Flight School offers flying lessons at a small municipal airport. The school’s owner and manager has been attempting to evaluate performance and control costs using a variance report that compares the planning budget to actual results. A recent variance report appears below: TipTop Flight School Variance Report For the Month Ended July 31 Actual Results Planning Budget Variances Lessons 225 220 Revenue $ 60,400 $...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several...
Problem 9-25 Critiquing a Variance Report; Preparing a Performance Report [LO9-1, LO9-2, LO9-3, LO9-4, LO9-6] Several years ago, Westmont Corporation developed a comprehensive budgeting system for planning and control purposes. While departmental supervisors have been happy with the system, the factory manager has expressed considerable dissatisfaction with the information being generated by the system. A report for the company's Assembly Department for the month of March follows: Assembly Department Cost Report For the Month Ended March 31 Actual Results Planning...
Exercise 9-14 (Algo) Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company...
Exercise 9-14 (Algo) Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company that owns and operates a large automatic car wash facility near Montreal. The following table provides data concerning the company’s costs: Fixed Cost per Month Cost per Car Washed Cleaning supplies $ 0.60 Electricity $ 1,100 $ 0.10 Maintenance $ 0.15 Wages and salaries $ 4,900 $ 0.30 Depreciation $ 8,100 Rent $ 2,200 Administrative expenses $ 1,800 $ 0.03 For example, electricity costs...
Exercise 9-17 Flexible Budget Performance Report [LO9-1, LO9-2, LO9-3, LO9-4] AirQual Test Corporation provides on-site air...
Exercise 9-17 Flexible Budget Performance Report [LO9-1, LO9-2, LO9-3, LO9-4] AirQual Test Corporation provides on-site air quality testing services. The company has provided the following cost formulas and actual results for the month of February: Fixed Component per Month Variable Component per Job Actual Total for February Revenue $ 275 $ 38,500 Technician wages $ 8,100 $ 7,950 Mobile lab operating expenses $ 4,800 $ 33 $ 9,590 Office expenses $ 2,400 $ 2 $ 2,550 Advertising expenses $ 1,590...
Problem 9-18 (Algo) Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by...
Problem 9-18 (Algo) Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step...
Exercise 9-14 Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company that...
Exercise 9-14 Prepare a Flexible Budget Performance Report [LO9-4] Lavage Rapide is a Canadian company that owns and operates a large automatic car wash facility near Montreal. The following table provides data concerning the company’s costs: Fixed Cost per Month Cost per Car Washed Cleaning supplies $ 0.80 Electricity $ 1,200 $ 0.09 Maintenance $ 0.15 Wages and salaries $ 4,500 $ 0.40 Depreciation $ 8,200 Rent $ 1,800 Administrative expenses $ 1,600 $ 0.02 For example, electricity costs are...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT