In: Accounting
First-In, First-Out Method; Equivalent Units
Aztec Inc. produces soft drinks. Mixing is the first department, and its output is measured in gallons. Aztec uses the FIFO method. All manufacturing costs are added uniformly. For July, the mixing department provided the following information:
Production: | ||
Units in process, July 1, 80% complete | 60,000 gallons | |
Units completed and transferred out | 390,000 gallons | |
Units in process, July 31, 75% complete | 24,000 gallons | |
Costs: | ||
Work in process, July 1 | $ 96,000 | |
Costs added during July | 780,000 |
Required:
1. Calculate the equivalent units for
July.
equivalent units
2. Calculate the unit cost. Round your answer
to the nearest cent.
$per unit
3. Assign costs to units transferred out and EWIP using the FIFO method. Note: Do not round interim computations.
Cost of units transferred out | $ |
Ending work in process | $ |
Answer :-
1)The equivalent units for July are as follows :-
Equivalent Units | |||
Particular | Total Units | % completed this period | Equivalent Units |
Units in process, July 1 |
60,000 | 20% | 12,000 |
Units started and completed (Units completed and transferred out - Unit in Process,July 1 = 390,000 - 60,000) |
330,000 | 100% | 330,000 |
Units in process, July 31, 75% complete | 24,000 | 75% | 18,000 |
Total Equivalents Unit of Production | 414,000 | 360,000 |
Equivalents Unit of Production = 360,000 units
2)Unit cost = Cost added during July / Total Equivalents Unit of Production
Cost added during July = $780,000
Total Equivalents Unit of Production = 360,000 units
Unit Cost = $780,000 / 360,000 units = $2.16666 per unit
Unit Cost = $2.17 per unit (approx.)
3)Costs to units transferred out and EWIP using the FIFO method are as follows :-
Costs to Units Transferred out = Work in Process,July 1 costs + Cost to finish Units in process, July 1+ Cost of units started and completed
Work in Process , July 1 Costs = $96,000
Cost to Finish Unit in Process , July 1 = Equivalents Units in Process,July 1 × Unit cost per unit
Cost to Finish Unit in Process, July 1 = 12,000 units × $2.16666 = $26,000
Cost of Units Started and Completed = Equivalents Unit started and completed × Unit Cost
Cost of Units Started and Completed = 330,000 units × $2.16666 = $715,000
Cost of Units Transferred out = $96,000 +$26,000 + $715,000
Cost of Units Transferred out = $837,000
Ending Work in Process = Equivalents Units in Process , July 31 × Unit Cost
Ending Work in Process = 18,000 × $2.16666
Ending Work in Process = $39,000