Problem 3
Anderson, Inc. provides the following data for the April – July
2019:
March |
April |
May |
June |
July |
|
Budgeted production units |
500 |
580 |
530 |
600 |
|
Ending Raw Materials Inventory |
663 lbs. |
Desired ending inventory:
Raw materials (pounds) = 30% of next month's
production needs
Pounds of raw material required for each finished Unit = 5 lbs
Raw material price = $8/lb
Direct labor hours per unit = 0.5 hrs
Direct labor rate = $12/hour
Required:
a. Prepare the Direct Materials Budget for April, May and June.
b. Prepare the Direct Labor Budget for April, May and June.