Question

In: Accounting

Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...

Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows:

Standard
Hours
Standard Rate
per Hour
Standard
Cost
30 minutes $6.00 $3.00

During August, 10,650 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $62,835 for the month.

Required:

1. What is the standard labor-hours allowed (SH) to makes 19,800 Jogging Mates?

2. What is the standard labor cost allowed (SH Ɨ SR) to make 19,800 Jogging Mates?

3. What is the labor spending variance?

4. What is the labor rate variance and the labor efficiency variance?

5. The budgeted variable manufacturing overhead rate is $4.30 per direct labor-hour. During August, the company incurred $53,250 in variable manufacturing overhead cost. Compute the variable overhead rate and efficiency variances for the month.

(For requirements 3 through 5, indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Do not round intermediate calculations.)

Solutions

Expert Solution


Related Solutions

Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 30 minutes $6.40 $3.20 During August, 10,340 hours of direct labor time were needed to make 19,100 units of the Jogging Mate. The direct labor cost totaled $64,108 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $5.80 $2.61 During August, 9,405 hours of direct labor time were needed to make 19,500 units of the Jogging Mate. The direct labor cost totaled $53,609 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 24 minutes $5.60 $2.24 During August, 8,310 hours of direct labor time were needed to make 19,200 units of the Jogging Mate. The direct labor cost totaled $45,705 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.20 $2.79 During August, 9,150 hours of direct labor time were needed to make 19,200 units of the Jogging Mate. The direct labor cost totaled $54,900 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.40 $2.88 During August, 9,395 hours of direct labor time were needed to make 19,100 units of the Jogging Mate. The direct labor cost totaled $58,249 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $6.20 $2.79 During August, 9,430 hours of direct labor time were needed to make 19,600 units of the Jogging Mate. The direct labor cost totaled $56,580 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 24 minutes $6.00 $2.40 During August, 8,730 hours of direct labor time were needed to make 19,900 units of the Jogging Mate. The direct labor cost totaled $50,634 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $5.80 $2.61 During August, 9,570 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $53,592 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 30 minutes $6.00 $3.00 During August, 10,560 hours of direct labor time were needed to make 19,800 units of the Jogging Mate. The direct labor cost totaled $61,248 for the month. Required: 1. What is the standard labor-hours allowed...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to...
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 27 minutes $5.80 $2.61 During August, 9,475 hours of direct labor time were needed to make 19,700 units of the Jogging Mate. The direct labor cost totaled $54,008 for the month. Required: 1. What is the standard labor-hours allowed...