In: Accounting
Job Cost Sheet
Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On October 1, Remnant Carpet Company gave Jackson Consulting an estimate of $3,136 to carpet the consulting firm’s newly leased office. The estimate was based on the following data:
Estimated direct materials:
40 meters at $35 per meter$ 1,400
Estimated direct labor:
24 hours at $20 per hour480
Estimated factory overhead (75% of direct labor cost)360
Total estimated costs$2,240
Markup (40% of production costs)896
Total estimate$3,136
On October 3, Jackson Consulting signed a purchase contract, and the delivery and installation were completed on October 10.
The related materials requisitions and time tickets are summarized as follows:
Materials Requisition No.Description Amount
11220 meters at $35$700
11424 meters at $35840
Time Ticket No.Description Amount
H1012 hours at $20$240
H1116 hours at $20320
Required:
Enter amounts as positive numbers.
1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.
2. Record the costs incurred, and complete the job order cost sheet.
JOB ORDER COST SHEET
CustomerJackson Consulting DateOctober 1
Date wantedOctober 10
Date completedOctober 10
Job. No.
ESTIMATE
Direct MaterialsDirect LaborSummary
Amount Amount Amount
40 Meters at $35$24 Hours at $20$Direct Materials$
Direct Labor
Factory Overhead
Total$Total$Total cost$
ACTUAL
Direct MaterialsDirect LaborSummary
Mat. Req. No.DescriptionAmountTime Ticket No.DescriptionAmountItemAmount
11220 Meters at $35$H1012 Hours at $20$Direct Materials$
Direct Labor
11424 Meters at $35H1116 Hours at $20Factory Overhead
Total $Total $Total Cost$
Feedback
1 & 2. Include the estimated and actual direct materials and direct labor. Include the estimated and applied factory overhead.
What is the best explanation for the variances between actual costs and estimated costs. (For this purpose, assume that the additional meters of material used in the job were spoiled, the factory overhead rate has proven to be satisfactory, and an inexperienced employee performed the work.)
The direct materials cost exceeded the estimate by $140 because 4 meters of materials were spoiled. The direct labor cost exceeded the estimate by $80 because an additional 4 hours of labor were used by an inexperienced employee. The factory overhead cost exceeded the estimate because an additional $60 of factory overhead was allocated because of the increase in direct labor.
Management didn't provide enough direction to complete tasks on budget.
The direct materials cost exceeded the estimate by $75 because 3 meters of materials were spoiled.
The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee.
Select the correct answer from the above choices.
a
JOB ORDER COST SHEET | |||||||
ESTIMATE | |||||||
Direct Materials | Direct Labor | Summary | |||||
Amount | Amount | Amount | |||||
40 sq. ft. at $35 | 1400 | 24 Hours at $20 | 480 | Direct Materials | 1400 | ||
Direct Labor | 480 | ||||||
Factory Overhead | 360 | ||||||
Total | 1400 | 480 | Total cost | 2240 | |||
ACTUAL | |||||||
Direct Materials | Direct Labor | Summary | |||||
Mat. Req. No. | Description | Amount | Time Ticket No. | Description | Amount | Item | Amount |
112 | 20 sq. ft. at $35 | 700 | H10 | 12 Hours at $20 | 240 | Direct Materials | 1540 |
114 | 24 sq. ft. at $35 | 840 | H11 | 16 Hours at $20 | 320 | Direct Labor | 560 |
Factory Overhead | 420 | ||||||
Total | 1540 | Total | 560 | Total cost | 2520 |
a. The direct materials cost exceeded the estimate by $140 because 4 square feet of materials were spoiled. The direct labor cost exceeded the estimate by $80 because an additional 4 hours of labor were used by an inexperienced employee. The factory overhead cost exceeded the estimate because an additional $60 of factory overhead was allocated because of the increase in direct labor.