In: Finance
China's Galanz built a new complex at the expected cost of 2
billion yuan in order to produce 12 million air-conditioning units
annually. The site was completed in 2004.
1 Make the following assumptions:
•The actual investment cost is either 1.9, 2.0, or 2.1 billion
yuan, with respective probabilities of 0.25,0.50, and 0.25.
•The plant operates for 15 years, with the salvage value being
either 50 million, 0, or-100 million(remediation costs) yuan at
that time, with probabilities of 0.20,0.50, and 0.30,
respectively.
•Finally, the net cash flow resulting from operations and sales is
60 yuan per unit. The number of units sold in each year is either 9
(0.1), 10 (0.2), 11 (0.3), or 12 (0.4) million. The figures
in
parentheses represent the probabilities of the given level of
production.
Assume that these are the only relevant cash flows and the interest rate is 18% per year.
a) Find an expression for the present worth (PW).
b) Find the expected value of the PW(if possible).
c) Find the standard deviation of the PW(if possible).
d)Find Pr(PW >0) (if possible).
e)Perform 200 simulations, and find the sample mean, standard deviation, as well as the probability that the investment will have a positive PW (point & interval estimates). Finally, summarize your process (which will naturally include all the appropriate steps) and results
Answers of question number a,b and d.
Time of project | 15 years | |||||||
Cost of Capital | 0.18 | |||||||
Cash Outflow (in Billion) | Probability | Cash Inflow by sales (in billion) | Probability | Salvage Value (in Billion) | Probability | |||
1.9 | 0.25 | 0.54 | 0.1 | 0.05 | 0.2 | |||
2 | 0.5 | 0.6 | 0.2 | 0 | 0.5 | |||
2.1 | 0.25 | 0.66 | 0.3 | -0.1 | 0.3 | |||
0.72 | 0.4 | |||||||
Cash Flows | 2 | 0.66 | -0.02 | |||||
Cash Flows at present value term | 2 | 3.36072 | -0.00167 | |||||
PW (in Billion ) | 11.88 | |||||||
PW (in Million ) | 11880 | |||||||
Pr(PW )(in Billion) | 1.35905 | |||||||
Pr(PW)( In Million) | 1359.05 |
answer of question no c) .Standard Deviation for PW cann't be calculated from the given data as cash outflow and cash inflow along with salvage value have probability of occurances.
Answer of e) As the all data is question are fixed as suitbale for calculation of Pr(PW).
so , Mean value is same as above .
Steps : See the calulated table all formuals are incorporated there.