In: Accounting
Percentage-of-Completion and Completed Contract Methods
Philbrick Company signed a three-year contract to provide sales training to the employees of Elliot Company. The contract price is $1,200 per employee and the estimated number of employees to be trained is 400. The expected number to be trained in each year and the expected training costs follow.
Number of Employees |
Training Costs Incurred |
|
---|---|---|
2016 | 125 | $60,000 |
2017 | 200 | 75,000 |
2018 | 75 | 40,000 |
Total | 400 | $175,000 |
Required
For each year, compute the revenue, expense, and gross profit
reported assuming revenue is recognized using the following
method.
(Do not round until your final answers. Round your answers to two
decimal places.)
1. Percentage-of-completion method, where percentage-of-completion is determined by the number of employees trained.
Revenue | Expense | Gross Profit | |
---|---|---|---|
2016 | Answer | Answer | Answer |
2017 | Answer | Answer | Answer |
2018 | Answer | Answer | Answer |
Total | Answer | Answer | Answer |
2. Percentage-of-completion method, where percentage-of-completion is determined by the costs incurred.
Revenue | Expense | Gross Profit | |
---|---|---|---|
2016 | Answer | Answer | Answer |
2017 | Answer | Answer | Answer |
2018 | Answer | Answer | Answer |
Total | Answer | Answer | Answer |
3. Completed contract method.
Revenue | Expense | Gross Profit | |
---|---|---|---|
2016 | Answer | Answer | Answer |
2017 | Answer | Answer | Answer |
2018 | Answer | Answer | Answer |
Total | Answer | Answer | Answer |
Answer 1 | ||||||||
Percentage of completeion is determined by the number of employees trained | ||||||||
Number of employees to be trained | Estimated number of employees to be trained under contract | % of Completion | ||||||
2016 | 125 | 400 | 31.25% | |||||
2017 | 200 | 400 | 50.00% | |||||
2018 | 75 | 400 | 18.75% | |||||
Applying % of completeion to total contract price i.e. $480000 ($1200 * 400) , we drived the following answer | ||||||||
Revenue | Expense | Gross Profit | ||||||
2016 | $150,000 | $60,000 | $90,000 | |||||
2017 | $240,000 | $75,000 | $165,000 | |||||
2018 | $90,000 | $40,000 | $50,000 | |||||
Answer 2 | ||||||||
Percentage of completeion is determined by the cost incurred | ||||||||
Training cost incurred | Total estimated cost to be incurred under contract | % of Completion | ||||||
2016 | $60,000.00 | $175,000.00 | 34.29% | |||||
2017 | $75,000.00 | $175,000.00 | 42.86% | |||||
2018 | $40,000.00 | $175,000.00 | 22.86% | |||||
Applying % of completeion to total contract price i.e. $480000 ($1200 * 400) , we drived the following answer | ||||||||
Revenue | Expense | Gross Profit | ||||||
2016 | $164,571 | $60,000 | $104,571 | |||||
2017 | $205,714 | $75,000 | $130,714 | |||||
2018 | $109,714 | $40,000 | $69,714 | |||||
Answer 3 | ||||||||
Completed contract method | ||||||||
Revenue | Expense | Gross Profit | ||||||
2016 | $0 | $60,000 | -$60,000 | |||||
2017 | $0 | $75,000 | -$75,000 | |||||
2018 | $480,000 | $40,000 | $440,000 | |||||