In: Accounting
Okay Accents Company manufactures and sells three styles of bathroom faucets: Nickel, Chrome, and White. Production takes 25, 25, and 10 machine hours to manufacture 1,000-unit batches of nickel, chrome, and white faucets, respectively. The following additional data apply:
NICKEL CHROME WHITE
Projected sales in units 32,000 50,000 40,000
PER UNIT data:
Selling price $35 $20 $30
Direct materials $ 8 $ 4 $ 8
Direct labor $15 $ 3 $ 9
Overhead cost based on direct labor hours
(traditional system) $13 $ 3 $ 9
Hours per 1000-unit batch:
Direct labor hours 40 10 30
Machine hours 25 25 10
Setup hours 1.5 0.5 1.0
Inspection hours 30 20 20
Total overhead costs and activity levels for the year are estimated as follows
Activity Overhead costs Activity levels
Direct labor hours 2,900 hours
Machine hours 2,400 hours
Setups $465,500 95 setup hours
Inspections $405,000 2,700 inspection hours
Total $870,500
a. Using the traditional system, determine the operating profit
or loss per unit for the nickel style of faucet.
b. Determine the activity-cost-driver rate for setup costs and
inspection costs.
Using the ABC system, for the nickel style of faucet:
c. compute the estimated overhead costs per unit.
d. compute the estimated operating profit per unit.
Solution:
Part a – Operating Profit or loss per unit for nickel style of faucet using traditional costing
Nickel |
|
Selling Price |
$35 |
Manufacturing Cost per unit: |
|
Direct materials |
$8 |
Direct Labor |
$15 |
Overhead Cost per unit |
$13 |
Manufacturing Cost Per Unit |
$36 |
Operating Profit or (Loss) per unit |
($1) |
Part b – Activity Cost Driver Rate for setup costs and inspection costs
Activity Cost Driver Rate for Setup Costs = Total Setup Costs / Number of setup hours
= $465,500 / 95 Setup hours
= $4,900 per setup hour
Activity Cost Drive Rate for Inspection Costs = Total Inspection Costs / Number of Inspection Hours
= $405,000 / 2700 Inspection Hours
= $150 per inspection hour
Part c – Estimated Overhead Cost per unit (ABC System)
Allocation of Overhead |
NICKEL |
||
Expected Usage of Activity per 1000-Unit Batch |
Activity Cost Driver Rate |
Assigned Overhead |
|
Setup |
1.5 |
$4,900 |
$7,350 |
Inspection |
30 |
$150 |
$4,500 |
Total Allocated Overheads |
$11,850 |
||
Number of Units in a Batch |
1,000 Units |
||
Overhead Costs Per Unit (Total Allocated Overheads / Units) |
$11.85 |
Overhead Cost Per Unit for Nickel = $11.85
Part d – Estimated Operating Profit per unit (ABC System) – NICKEL
Nickel |
|
Selling Price |
$35.00 |
Manufacturing Cost per unit: |
|
Direct materials |
$8.00 |
Direct Labor |
$15.00 |
Overhead Cost per unit |
$11.85 |
Manufacturing Cost Per Unit |
$34.85 |
Operating Profit or (Loss) per unit |
$0.15 |
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you