In: Economics
a) Complete the following cost schedule by computing average
fixed cost and average variable cost.
Instructions: Enter your responses rounded to the
nearest whole number.
Output | Total Cost | Average Fixed Cost | Average Variable Cost |
0 | $600 | ----- | ----- |
1 | 800 | ||
2 | 1,050 | ||
3 | 1,400 | ||
4 | 1,800 | ||
5 | 2,300 |
Output | total cost | average fixed cost | average variable cost | |
0 | 600 | |||
1 | 800 | 600 | 200 | |
2 | 1050 | 300 | 225 | |
3 | 1400 | 200 | 266.6 | |
4 | 1800 | 150 | 300 | |
5 | 2300 | 120 | 340 |
Formula of average fixed cost= fixed cost/output
Formula of average variable cost,,= variable cost/output