Question

In: Finance

Suppose the expected net benefits from a project are continuously rising with calendar time. Suppose also...

Suppose the expected net benefits from a project are continuously rising with calendar time. Suppose also that you expect the present value of the initial costs of the project to fall over time, (evaluated at the time it starts operations), if the project is postponed. Will this cause the optimum time to start the project to be delayed or to be started earlier? Explain why.

Solutions

Expert Solution

Since the expected net benefits from a project increase with calendar time, the benefits from delaying the project by a unit period are more than if the project is started immediately.

Also, the PV of the costs would fall on delaying the project, then the NPV of the project (calculated as PV of benefits - PV of costs) would be higher if the project is delayed than if the project is started immediately. This is based on the assumption that the discount rate is not high enough to reduce the NPV of starting the project later below the NPV of starting the project today.

So,

Expected benefits (t+1) > Expected benefits (t)

PV of costs (t+1) < PV of costs (t)

NPV (t) = PV (Expected Benefits (t)) - PV of costs (t)

NPV (t+1) = PV (Expected Benefits (t+1)) - PV of costs (t+1)

Clearly NPV(t+1) > NPV(t).

However NV(t+1) is evaluated one period later and NPV(t) is evaluated immediately.

Also present value of NPV(t+1) = NPV(t+1)/(1+r)

if r is not big enough, then PV of NPV(t+1) > NPV(t)

So, in that case the optimum time to start the project is delayed.


Related Solutions

MUST show Excel calculation for payback Expected Net Cash Flows Time Project A Project B 0...
MUST show Excel calculation for payback Expected Net Cash Flows Time Project A Project B 0 ($375) ($575) 1 ($300) $190 2 ($200) $190 3 ($100) $190 4 $600 $190 5 $600 $190 6 $926 $190 7 ($200) $0 f.   What is the regular payback period for these two projects? Project A Time period 0 1 2 3 4 5 6 7 Cash flow (375) (300) (200) (100) 600 600 926 (200) Cumulative cash flow -$375 -$675 -$875 -$975 -$375 $225...
For project A, the cash flow effect from the change in net working capital is expected...
For project A, the cash flow effect from the change in net working capital is expected to be 500 dollars at time 2 and the level of net working capital is expected to be 2,600 dollars at time 1. What is the level of current assets for project A expected to be at time 2 if the level of current liabilities for project A is expected to be 1,900 dollars at time 2?
For project A, the cash flow effect from the change in net working capital is expected...
For project A, the cash flow effect from the change in net working capital is expected to be 100 dollars at time 2, the level of net working capital is expected to be 1,500 dollars at time 0, and the level of net working capital is expected to be 1,200 dollars at time 2. What is the cash flow effect from the change in net working capital expected to be at time 1? For project A, the change in net...
For project A, the cash flow effect from the change in net working capital is expected...
For project A, the cash flow effect from the change in net working capital is expected to be -500 dollars at time 2 and the level of net working capital is expected to be 1,500 dollars at time 2. What is the level of current liabilities for project A expected to be at time 1 if the level of current assets for project A is expected to be 7,100 dollars at time 1? For project A, the cash flow effect...
For project A, the cash flow effect from the change in net working capital is expected...
For project A, the cash flow effect from the change in net working capital is expected to be 300 dollars at time 2 and the level of net working capital is expected to be 2,500 dollars at time 2. What is the level of current liabilities for project A expected to be at time 1 if the level of current assets for project A is expected to be 6,600 dollars at time 1?
For project A, the cash flow effect from the change in net working capital is expected...
For project A, the cash flow effect from the change in net working capital is expected to be 300 dollars at time 2 and the level of net working capital is expected to be 1,500 dollars at time 1. What is the level of current liabilities for project A expected to be at time 2 if the level of current assets for project A is expected to be 4,600 dollars at time 2?
Suppose that the government reduces corporate taxes, thereby increasing the net expected profit from investment projects...
Suppose that the government reduces corporate taxes, thereby increasing the net expected profit from investment projects run by businesses. Adjust the Supply and demand graph below to illustrate how this corporate tax cut affects the bond market.
One research project will cost $500,000 today and is expected to yield benefits of $50,000 at...
One research project will cost $500,000 today and is expected to yield benefits of $50,000 at the end of each of the next 30 years. A second project will cost $400,000 and yield a single cash flow of $800,000 in 6 years. What is the difference in the IRR’s of these research projects?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 12%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they are mutually exclusive?...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $4,000 per year for 5 years. Project L costs $21,000 and is expected to produce cash flows of $8,000 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, PIs, and Pay Back Period assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT