Question

In: Finance

- Langton Inc. is considering Projects S and L, whose cash flows are shown below. These...

- Langton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone? In other words, what's the NPV of the chosen project versus the maximum possible NPV? You must show each project's IRR as well as its NPV. The firm's cost of capital is 7%.

Year CF from S CF from L
0 -1200 -2650
1 550 725
2 700 750
3 200 800
4 300 1400

What is the crossover point for the two projects? What is the significance of this?

Solutions

Expert Solution

Computation of NPV:

NPV = PV of future cash flows – Initial investment

Year

Cash Flow (CS)

Computation of PV Factor

PV Factor @ 7 % (F)

PV (CS x F)

0

-$ 1,200

1/ (1+0.07)0

1

-$ 1,200.00

1

$ 550

1/ (1+0.07)1

0.934579439252336

$ 514.01869

2

$ 700

1/ (1+0.07)2

0.873438728273212

$ 611.40711

3

$ 200

1/ (1+0.07)3

0.816297876890852

$ 163.25958

4

$ 300

1/ (1+0.07)4

0.762895212047525

$ 228.86856

NPV

$ 317.55394

NPV of Project L is $ 317.55

Year

Cash Flow (CL)

Computation of PV Factor

PV Factor @ 7 % (F)

PV (CL x F)

0

-$ 2,650

1/ (1+0.07)0

1

-$ 2,650.00

1

$ 725

1/ (1+0.07)1

0.934579439252336

$ 677.57009

2

$ 750

1/ (1+0.07)2

0.873438728273212

$ 655.07905

3

$ 800

1/ (1+0.07)3

0.816297876890852

$ 653.03830

4

$ 1,400

1/ (1+0.07)4

0.762895212047525

$ 1,068.05330

NPV

$ 403.74074

NPV of Project L is $ 403.74

Computation of IRR:

Project S:

Computation of NPV of Project S at discount rate of 20 %.

Year

Cash Flow (CS)

Computation of PV Factor

PV Factor @ 20 % (F)

PV (CS x F)

0

-$ 1,200

1/ (1+0.2)0

1

-$ 1,200.00

1

$ 550

1/ (1+0.2)1

0.833333333333333

$ 458.33333

2

$ 700

1/ (1+0.2)2

0.694444444444445

$ 486.11111

3

$ 200

1/ (1+0.2)3

0.578703703703704

$ 115.74074

4

$ 300

1/ (1+0.2)4

0.482253086419753

$ 144.67593

NPVS1

$ 4.86111

As NPV is positive let’s compute NPV at discount rate of 21 %.

Year

Cash Flow (CS)

Computation of PV Factor

PV Factor @ 21 % (F)

PV (CS x F)

0

-$ 1,200

1/ (1+0.21)0

1

-$ 1,200.00

1

$ 550

1/ (1+0.21)1

0.826446280991736

$ 454.54545

2

$ 700

1/ (1+0.21)2

0.683013455365071

$ 478.10942

3

$ 200

1/ (1+0.21)3

0.564473930053777

$ 112.89479

4

$ 300

1/ (1+0.21)4

0.466507380209733

$ 139.95221

NPV S2

-$ 14.49813

IRR S = R1 + [NPVS1 x (R2 – R1)/ (NPVS1 – NPVS2)]

    = 20 % + [$ 4.86111 x (22 % – 21 %)/ ($ 4.86111 – (- $ 14.49813)]

    = 20 % + [$ 4.86111 x 1 %/ ($ 4.86111 + $ 14.49813)]

    = 20 % + ($ 0.0486111/ $ 19.35924)

    = 20 % + 0.002511

    = 20 % + 0.2511 % = 20.25 %

IRR of Project S is 20.25 %

Project L:

Computation of NPV of Project L at discount rate of 12 %.

Year

Cash Flow (CL)

Computation of PV Factor

PV Factor @ 12 % (F)

PV (CL x F)

0

-$ 2,650

1/ (1+0.12)0

1

-$ 2,650.00

1

$ 725

1/ (1+0.12)1

0.892857142857143

$ 647.32143

2

$ 750

1/ (1+0.12)2

0.797193877551020

$ 597.89541

3

$ 800

1/ (1+0.12)3

0.711780247813411

$ 569.42420

4

$ 1,400

1/ (1+0.12)4

0.635518078404831

$ 889.72531

NPVL1

$ 54.36634

As NPV is positive let’s compute NPV at discount rate of 13 %.

Year

Cash Flow (CL)

Computation of PV Factor

PV Factor @ 13 % (F)

PV (CL x F)

0

-$ 2,650

1/ (1+0.13)0

1

-$ 2,650.00

1

$ 725

1/ (1+0.13)1

0.884955752212389

$ 641.59292

2

$ 750

1/ (1+0.13)2

0.783146683373796

$ 587.36001

3

$ 800

1/ (1+0.13)3

0.693050162277696

$ 554.44013

4

$ 1,400

1/ (1+0.13)4

0.613318727679377

$ 858.64622

NPVL2

-$ 7.96072

IRR L = R1 + [NPVL1 x (R2 – R1)/ (NPVL1 – NPVL2)]

    = 12 % + [$ 54.36634 x (13 % – 12 %)/ ($ 54.36634 – (- $ 7.96072)]

    = 12 % + [$ 54.36634 x 1 %/ ($ 54.36634 + $ 7.96072)]

    = 12 % + ($ 0.5436634 / $ 62.32706)

    = 12 % + 0.008722751

    = 12 % + 0.8722751 % = 12.87 %

IRR of Project L is 12.87 %

Project L should be accepted based on NPV decision.

Project S should be accepted based on IRR decision.

Forgone value if we choose Project S based on IRR rule = $ 403.74 - $ 317.55 = $ 86.19

Computation of Crossover rate:

Year

Cash Flow (CL)

Cash Flow (CS)

Cash Flow CL - CS

0

-$ 2,650

-$ 1,200

-$ 1,450

1

$ 725

$ 550

$ 175

2

$ 750

$ 700

$ 50

3

$ 800

$ 200

$ 600

4

$ 1,400

$ 300

$ 1,100

Computation of NPV at discount rate of 8 %

Year

Cash Flow

CL - CS

Computation of PV Factor

PV Factor @ 8 % (F)

PV (CL - CS x F)

0

-$ 1,450

1/ (1+0.08)0

1

-$ 1,450.00

1

$ 175

1/ (1+0.08)1

0.925925925925926

$ 162.03704

2

$ 50

1/ (1+0.08)2

0.857338820301783

$ 42.86694

3

$ 600

1/ (1+0.08)3

Related Solutions

Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost WACC 11.75% 0 1 2 3 4 CFs...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Poston Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Poston Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive (must choose one or the other), equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? You must calculate the IRR and NPV for both projects select the project with the higher IRR and then calculate how much less the NPV is by selecting the project with...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT