The table below shows the net weekly demand of Audi Car model. The lead time to receive the door is 2 weeks. In week 0, there are 5 cars and 15 doors in inventory. It is expected to receive 30 reworked doors in week 10.
| 
 Week  | 
 8  | 
 9  | 
 10  | 
 11  | 
 12  | 
 13  | 
 14  | 
 15  | 
 16  | 
 17  | 
| 
 Net demand (car)  | 
 20  | 
 25  | 
 40  | 
 12  | 
 5  | 
 32  | 
 24  | 
 18  | 
 16  | 
 30  | 
Complete the following MRP table for the doors:
| 
 Week  | 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 6  | 
 7  | 
 8  | 
 9  | 
 10  | 
 11  | 
 12  | 
 13  | 
 14  | 
 15  | 
 16  | 
 17  | 
| 
 Gross Requirement  | 
|||||||||||||||||
| 
 Net Requirement  | 
|||||||||||||||||
| 
 Time-Phased Net Requirement  | 
|||||||||||||||||
| 
 Planned Order Release  | 