Question

In: Accounting

Montreal Ltd. is a manufacturer of custom equipment and applies overhead to jobs on the basis...

Montreal Ltd. is a manufacturer of custom equipment and applies overhead to jobs on the basis of direct Required: labour hours. Montreal Ltd. estimated $840,000 overhead costs and 10,000 direct labour hours for the year. c. Calculate the work in process inventory on January 31, 2015: Montreal Ltd. had 2 jobs in work in process inventory on January 1, 2015. The company started 2 more jobs during January. The following data was provided for January: d. Calculate the finished goods inventory on January 31, 2015. Job 102 Job 103 Job 104 Job 105 e. Calculate the cost of goods sold for January. Balance Jan. 1, 2015 $36,480 $19,020 $0 $0 Direct Materials $34,420 $45,800 $30,480 $16,420 f. Assume Montreal Ltd. applies 40% markup on cost. What is the selling price of Job 103? Direct Labour Cost $23,000 $32,500 $19,500 $9,720 Direct Labour Hours 4,600 6,500 3,900 1,944 By January 31, 2015, Job 102 and Job 103 were completed and Job 103 was sold. The rest of the jobs remained in process. Required: a. Calculate the plantwide overhead rate per direct labour hour. Overhead Direct Labor Hour b. Complete the job order cost sheets for all four jobs in January. Job 102 Job 103 Job 104 Job 105 Beginning Balance Direct Materials Direct Labour Overhead Applied Total Cost 2.5

Solutions

Expert Solution

Required:
a) plantwide overhead rate = $840,000/10,000 direct labour $             84.00 per  Direct Labor Hour
b)
Complete the job order cost sheets for all four jobs in January.
Job 102 Job 103 Job 104 Job 105
Beginning Balance $      36,480.00 $   19,020.00 $                -    $                -   
Direct Materials $      34,420.00 $   45,800.00 $   30,480.00 $   16,420.00
Direct Labour $      23,000.00 $   32,500.00 $   19,500.00 $     9,720.00
Overhead Applied (Direct labour hours x $84) $    386,400.00 $ 546,000.00 $ 327,600.00 $ 163,296.00
Total Cost             $    480,300.00 $ 643,320.00 $ 377,580.00 $ 189,436.00
c)
Work in process inventory on January 31, 2015: Total cost of j Job 104 + job 105   $    567,016.00
d)  finished goods inventory on January 31, 2015 = Job 102 + Job 103 $ 1,123,620.00
e ) cost of goods sold for January. = job 103 $    643,320.00
f. Assume Montreal Ltd. applies 40% markup on cost. What is the selling price of Job 103?
selling price of Job 103 = $643,320 x (1 + 40%) $    900,648.00

Related Solutions

Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred and 130,000 hours are used. Collapse question part (a) Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $ per machine hour
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $456,789 4 for the year, and machine usage is estimated at 126,000 hours For the year, $432450 of overhead costs are incurred and 125,500 hours are used. What is the predetermined overhead rate What is the amount of overhead applied Has it been over or underapplied? Prepare the adjusting entry to adjust the cost of goods sold
The company applies overhead cost to jobs on the basis of machine-hours worked. For the current...
The company applies overhead cost to jobs on the basis of machine-hours worked. For the current year, the company estimated that it would work 75,000 machine-hours and incur $450,000 in manufacturing overhead cost. The following transactions were recorded for the year: a. Raw materials were purchased on account, $ 410,000 b. Raw materials were requisitioned for use in production, $ 380,000 ($360,000 direct materials and $20,000 indirect materials). c. The following costs were incurred for employees services: direct labor, $...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.30 per machine-hour was based on a cost formula that estimates $213,900 of total manufacturing overhead for an estimated activity level of 93,000 machine-hours. Required: 1. Assume that during the year the company works only 88,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $111,800 of manufacturing overhead for an estimated allocation base of $86,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 137,000 Direct...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $530,640 $774,700 Estimated direct labor hours for year 12,700 Estimated machine hours for year 24,120 Actual factory overhead costs for...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis...
Sundance Solar Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct labor hours, and machine hours are as follows: Factory 1 Factory 2 Estimated factory overhead cost for fiscal year beginning March 1 $1,337,500 $847,000 Estimated direct labor hours for year 24,200 Estimated machine hours for year 53,500 Actual factory overhead costs for...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $800,000 of manufacturing overhead for an estimated allocation base of $500,000 direct material dollars to be used in production. The company has provided the following data for the just completed year:    Purchase of raw materials $ 510,000...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $120,400 of manufacturing overhead for an estimated allocation base of $86,000 direct material dollars to be used in production. The company has provided the following data for the just completed year: Purchase of raw materials $ 133,000 Direct...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $124,600 of manufacturing overhead for an estimated allocation base of $89,000 direct material dollars to be used in production. The company has provided the following data for the just completed year:     Purchase of raw materials$130,000 Direct labor...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT