In: Accounting
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.32 per micron Direct labor: 1.4 hours per toy at $7.30 per hour During July, the company produced 5,300 Maze toys. The toy's production data for the month are as follows: Direct materials: 71,000 microns were purchased at a cost of $0.29 per micron. 24,625 of these microns were still in inventory at the end of the month. Direct labor: 7,920 direct labor-hours were worked at a cost of $62,568. Required: 1. Compute the following variances for July: (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Do not round intermediate calculations. Round final answer to the nearest whole dollar amount.) a. The materials price and quantity variances. b. The labor rate and efficiency variances.
Calculation of material variances
71,000 microns were purchased and 24,625 of these microns were still in inventory at the end of the month.
Hence, material consumed = 71,000 - 24,625
= 46,375 microns
Standard quantity = 7 microns per toy
Actual production = 5,300 toys
Hence, standard quantity for 5,300 toys = 5,300 x 7
= 37,100 microns
Standard quantity | Standard price | Actual quantity | Actual price | |
Direct material | 37,100 | $0.32 | 46,375 | $0.29 |
Direct material price variance = Actual quantity x (Standard price - Actual price)
= 46,375 x (0.32 - 0.29)
= $1,391.25 F
Direct material quantity variance = Standard price x (Standard quantity - Actual quantity)
= 0.32 x (37,100 - 46,375)
= $2,968 U
Calculation of labor cost variances
Direct labor: 1.4 hours per toy at $7.30 per hour
Hence, standard hours for 5,300 toys = 5,300 x 1.4
= 7,420
Actual direct labor cost = $62,568
Actual direct labor hours = 7,920
Hence, actual rate = 62,568/7,920
= $7.9
Standard hours | Standard rate | Actual hours | Actual rate | |
Direct labor | 7,420 | $7.30 | 7,920 | $7.9 |
Direct labor rate variance = Actual time x (Standard rate - Actual rate)
= 7,920 x (7.30 - 7.9)
= $4,752 U
Direct labor efficiency variance = Standard rate x (Standard time - Actual time)
= 7.30 x (7,420 - 7,920)
= $3,650 U
Kindly give a positive rating, if you are satisfied with the answer. Feel free to ask if you have any doubts. Thanks