Question

In: Economics

The highway department must select one of two repair options for a 10-mile of a four-lane...

The highway department must select one of two repair options for a 10-mile of a four-lane highway. The analysis period is 8 years and interest rate (MAAR) is 8%

Option 1 Option 2
Initail Cost 5,300,000 3,000,000
Annual cost 300,000 400,000
Lifetime 8 years 4 years

a) Using Present worth analysis, find the best repair option.

b) Using Annual worth analysis, find the repair option.

c) Using incremental rate of return analysis, find the best repair option. Use the shortcut of cheking at the MARR only.

(Please do not use Excel, Thank you)

Solutions

Expert Solution


Related Solutions

A class I two lane highway is on level terrain with passing permitted throughout. The highway...
A class I two lane highway is on level terrain with passing permitted throughout. The highway has 11 ft lanes with 4 ft shoulders. There are 16 access points per mile. The base FFS is 60 mi/h. The highway is oriented north and south, and during the peak hour, 440 vehicles are going northbound and 360 vehicles are going southbound. If the PHF is 0.87 and there are 4% large trucks, 3% buses, and 1% recreational vehicles, what is the...
Consider a 12 - mile segment of an existing four - lane freeway having very restricted...
Consider a 12 - mile segment of an existing four - lane freeway having very restricted geometry with rolling terrain. Peak hour volume is 2000 veh/h and the flow consist of 12% trucks and 3% recreational vehicles. The traffic is commuter type with peak hour factor 0.92. The freeway segment can be accessed by 6 on - ramps and has 8 off - ramps. Freeway consists of two lanes in each direction of 11 feet width with lateral clearance of...
A crew of mechanics at the Highway Department garage repair vehicles that break down at an...
A crew of mechanics at the Highway Department garage repair vehicles that break down at an average of 10 vehicles per hour (approximately Poisson in nature). The mechanic crew can service an average of 2 vehicles every 10 minutes with a repair time distribution that approximates an exponential distribution. The crew cost is approximately $50 per hour. The cost associated with lost productivity from the breakdown is estimated at $80 per vehicle per hour (or any fraction thereof). Which is...
A two-lane rural highway, four-leg intersection will have its stop control replaced by a signal control....
A two-lane rural highway, four-leg intersection will have its stop control replaced by a signal control. Compute the expected average total crash frequency (all types, all severities) after the change for the following conditions: 
 Expected average crash frequency before change: 23 total crashes/yr AADT on minor road: 1500 veh/day
 AADT on major road: 5000 veh/day 
 Please show all work and formulas used. Thanks! Submitting this again this the last person didn't even answer the question at all. Not sure what...
A four-lane undivided multilane highway (two lanes in each direction) has 3.4 m lanes and 1.5...
A four-lane undivided multilane highway (two lanes in each direction) has 3.4 m lanes and 1.5 m shoulders. At one point along the highway there is a 4% upgrade that is 1 km long. There are 15 access points along this grade. The peak-hour traffic volume has 2500 passenger cars and 200 trucks and buses (no recreational vehicles), and 720 of these vehicles arrive in the most congested 15-min period. This traffic stream is primarily commuters. The measured free-flow speed...
A Class I two-lane highway is on level terrain with passing permitted throughout. The highway has...
A Class I two-lane highway is on level terrain with passing permitted throughout. The highway has 3.6 m lanes with 1.1 m shoulders. There are 13 access points per kilometer. The base FFS is 96.5 km/hr. During the peak hour, 500 vehicles are traveling in the analysis direction and 400 vehicles are traveling in the opposing direction. If the PHF is 0.8 and there are 7% large trucks, 7% buses, and 7% recreational vehicles, what is the level of service?
Last Tuesday the Belmont Fire Department was dispatched to the westbound lane of State Highway 123...
Last Tuesday the Belmont Fire Department was dispatched to the westbound lane of State Highway 123 for an accident involving a dump truck on fire. Engine 2 responded with a crew of five, followed shortly after by Engine 3 with a crew of four. Engine 2 arrived to find an overturned dump truck with the cab fully involved and the driver self-extricated. Engine 2’s crew pulled one of the front bumper lines and started their fire attack. They were followed...
A four-lane divided highway in suburban area has the following criteria: • Average grade is less...
A four-lane divided highway in suburban area has the following criteria: • Average grade is less than 2% (level Terrain) • Posted speed 55 MPH • 11 ft lanes, 4 ft left and 4 ft right clearance • 9% heavy vehicle • Access spacing is 500 ft • Directional Design Hour Volume = 2600 vph • PHF = 0.92 Find the level of service for the highway
Draw a typical cross section for a two-lane highway and explain the principal components.
Draw a typical cross section for a two-lane highway and explain the principal components.
A two-lane highway is currently operating at its two-way capacity in rolling terrain. The traffic stream...
A two-lane highway is currently operating at its two-way capacity in rolling terrain. The traffic stream consists of cars and trucks only. A recent traffic count revealed 720 vehicles (total, both directions) arriving in the most congested 15- min interval. What is the percentage of trucks in the traffic stream based on the ATS service measure? Given: ATS: fG=0.99 when it is rolling terrain, vp>1200 ET= 1.5 when it is rolling terrain, vp>1200
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT