In: Operations Management
Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
| 
 Item: A  | 
 Order Policy: 100 units  | 
|||||||
| 
 Lead Time: 1 week  | 
||||||||
| 
 January  | 
 February  | 
|||||||
| 
 Quantity on Hand: 70  | 
 Week  | 
|||||||
| 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 6  | 
 7  | 
 8  | 
|
| 
 Forecast  | 
 65  | 
 70  | 
 65  | 
 40  | 
 45  | 
 45  | 
 45  | 
 50  | 
| 
 Customer orders (booked)  | 
 40  | 
 10  | 
 90  | 
 0  | 
 30  | 
 65  | 
 0  | 
 0  | 
| 
 Projected on-hand inventory  | 
||||||||
| 
 MPS quantity  | 
||||||||
Quantity on hand = 70 units
Order policy = 100 units
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Forecast | 65 | 70 | 65 | 40 | 45 | 45 | 45 | 50 | 
| Customer Orders (Booked) | 40 | 10 | 90 | 0 | 30 | 65 | 0 | 0 | 
| Projected on-hand inventory | 5 | 35 | 45 | 5 | 60 | 95 | 50 | 0 | 
| MPS Quantity | 0 | 100 | 100 | 0 | 100 | 100 | 0 | 0 | 
Explanation -
Projected on-hand inventory = Inventory from previous week - Current Week's Requirements
Current week's Requirements = Maximum (Forecast , Customer Orders)
MPS = New Order placed
Calculations : -
Week 1 -
Current week's requirements = Maximum(65,40) = 65
Projected on - hand inventory = 70 - 65 = 5
MPS = 0
Week 2 -
Current week's requirements = Maximum (70,10) = 70
Quantity in hand = 5
Hence, we need to place order for 100 units.
Hence, New quantity on hand = 100+5 = 105
Projected on-hand inventory = 105 - 70 = 35
MPS = 100 (Reason: order placed for 100 units in week 2)
Week 3 -
Current week's requirements = Maximum (65,90) = 90
Quantity in hand = 35
Hence, we need to place order for 100 units.
Hence, New quantity on hand = 100+35 = 135
Projected on-hand inventory = 135 - 90 = 45
MPS = 100 (Reason: order placed for 100 units in week 3)
Week 4 -
Current week's requirements = Maximum (40,0) = 40
Quantity in hand = 45
Projected on-hand inventory = 45 - 40 = 5
MPS = 0
Week 5-
Current week's requirements = Maximum (45,30) = 45
Quantity in hand = 5
Hence, we need to place order for 100 units.
Hence, New quantity on hand = 100+5 = 105
Projected on-hand inventory = 105 - 45 = 60
MPS = 100 (Reason: order placed for 100 units in week 5)
Week 6 -
Current week's requirements = Maximum (45,65) = 65
Quantity in hand = 60
Hence, we need to place order for 100 units.
Hence, New quantity on hand = 100+60 = 160
Projected on-hand inventory = 160 - 65 = 95
MPS = 100 (Reason: order placed for 100 units in week 6)
Week 7 -
Current week's requirements = Maximum(45,0) = 45
Projected on - hand inventory = 95 - 45 = 50
MPS = 0
Week 8 -
Current week's requirements = Maximum(50,0) = 50
Projected on - hand inventory = 50 - 50 = 0
MPS = 0