Question

In: Accounting

ACTIVITY BASED ACCOUNTING The Columbus Company produces only two products: a major computer part and cell...

ACTIVITY BASED ACCOUNTING

The Columbus Company produces only two products: a major computer part and cell phones. The company uses a normal cost system and overhead costs are currently allocated using a plant-wide overhead rate based on direct labor hours. Outside cost consultants have recommended, however, that the company use activity-based costing to charge overhead to products.

The company expects to produce 3,900 computer parts and 2,220 cell phones during the next year. Each computer part requires 2.25 direct labor hours to produce and each cell phone requires 0.75 hour to produce.

The direct material and direct labor costs included in the two products are as follows:

Item

Computer Part

Cell-Phone

Direct Material (per

unit)

$29

$19.20

Direct Labor (per unit)

$18.10

$ 4.50

Budgeted (Estimated) Total Factory Overhead Data For the year:

Activity

Budgeted Overhead Dollars

Estimated Volume Level

Production Setups

$79,300

22 setups

Material Handling

$69,900

4,900 lbs.

Packaging and

Shipping

$119,400

5,925 boxes

Total Factory Overhead

$268,600

Based on an analysis of the three overhead activities, it was estimated that the two products would require these activities as follows for the year:

Activity

Computer Parts

Cell Phones

Overall Totals

Production Setups

5 setups

15 setups

20 setups

Material Handling

1,000 lbs.

4,000 lbs.

5,000 lbs.

Packaging and Shipping

4,000 boxes

2,000 boxes

6,000 boxes

Required:

  1. Calculate the cost of each product using a plant-wide rate based on direct labor hours.
  1. Calculate the activity cost rates for (a) setups, (b) material handling and (c) packaging and shipping.
  1. Cost out the two products using an activity-based costing system.

Solutions

Expert Solution

1 OH Rate $25.73
(Total Budgeted Overhead Dollars/Total Budgeted Direct Labor Hours)
($268,600/10,440)
Total budgeted DLH
3,900 computer parts x 2.25 DLH per part           8,775
2,220 cell phones x 0.75 DLH per phone           1,665
        10,440
Computer Parts Cell Phones
Direct Material $29.00 $19.20
Direct labor $18.10 $4.50
Manufacturing Overhead $57.90 $19.30
Total Unit cost $105.00 $43.00
2
Cost Item Budgeted Overhead Estimated Volume Activity Cost
Production Setups $79,300              22 3604.55
Material Handling $69,900         4,900 14.27
Packaging and Shipping $119,400         5,925 20.15
3 Computer Parts Cell Phones
Direct Material $113,100.00 $42,624.00
Direct labor $70,590.00 $9,990.00
Manufacturing Overhead
Production Setups $18,022.75 $54,068.25
Material Handling $14,270.00 $57,080.00
Packaging and Shipping $80,600.00 $40,300.00
Total cost $296,582.75 $204,062.25
Total Units Produced           3,900         2,220
Total Cost Per Unit $76.05 $91.92

Related Solutions

Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell...
Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $524,800. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information about cell phones and tablet PCs...
Alrex company is using an activity-based costing (ABC) system. The company produces and sells two products:...
Alrex company is using an activity-based costing (ABC) system. The company produces and sells two products: Basic and Pro. The company consists of two departments: Production (where all manufacturing activities are taken) and Marketing (which engages in selling and admin activity only). The ABC system includes in unit product costs all costs easily associated with units. In addition, in the ABC system, there are four major indirect activities: Machine Setups, Special Processing, Factory Supervision, and Customer Relation. The prices, direct...
Assume a company that uses activity-based costing (ABC) has only two products – A and B....
Assume a company that uses activity-based costing (ABC) has only two products – A and B. The company does not have any organization-sustaining activities or unused capacity costs. The company’s total manufacturing overhead cost of $56,000 has been allocated to the three activities shown below: Setups Machining Packing Orders Activity measure quantity: Product A 20 1,000 150 Activity measure quantity: Product B 20 ? 350 Overhead cost per activity cost pool ? ? $ 10,000 Activity rate    $ 150 per...
ACCT4210–Cost and Managerial Accounting Problem 4: Activity-based costing Rome, Inc., produces two products, Product A and...
ACCT4210–Cost and Managerial Accounting Problem 4: Activity-based costing Rome, Inc., produces two products, Product A and Product B. If currently allocates overhead costs using direct-labor hours, but the controller has recommended an activity-based costing (ABC) system using the following data: Activity Level Activity Cost-Driver Base Cost Product A Product B Production setup Number of setups $ 90,000 11 19 Materials handling & requisition Number of parts per unit $ 15,000 6 18 Packaging & shipping Number of units shipped $...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing...
Plaid Manufacturing Co. produces two products: G1 and M1. The company uses an activity based costing system. The following are the activities, budgeted total cost and cost drivers per activity for the year 20x9: Activity Budgeted Cost Cost Base Cost Base Volume Assembly $861050 # of DL hours 36332 Inspection $669581 # of units 20525 Plaid Manufacturing has budgeted to produce 3,000 units of G1. G1 requires 17790 hours of direct labour. What is the overhead cost per unit for...
SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and...
SCS Co. uses activity-based costing in their manufacturing process. The company produces two products, ABC and XYZ. SCS has provided their costing department the following information from this year’s budget relating to the production of these two products: ABC XYZ Units to be produced 4,000 6,000 Machine-hours expected 100 200 Direct labor-hours expected 200 300 Materials handling (number of moves) 60 70 Machine setups (number of setups) 20 15 The following costs are expected to be incurred throughout the year,...
Macpherson Limited produces two products: Standard and Deluxe. The company uses an activity-based costing system. Macpherson...
Macpherson Limited produces two products: Standard and Deluxe. The company uses an activity-based costing system. Macpherson produces 8,000 units of Standard and 2,000 units of Deluxe. The company uses two activity cost pools, with estimated total cost and activity as follows: Expected Activity Activity Cost Pool Estimated Cost Standard Deluxe #1 $12,000 500 250 #2 $24,000 400 1,200         What is the cost per unit of Macpherson under activity-based costing? a. $15.00 b. $11.00 c. $16.00 d. $1.75 What is the...
R4 Friends Co. (R4F) uses activity-based costing in their manufacturing process. The company produces two products,...
R4 Friends Co. (R4F) uses activity-based costing in their manufacturing process. The company produces two products, ABC and XYZ. R4F has provided their costing department the following information from this year’s budget relating to the production of these two products: ABC XYZ Units to be produced 40,000 60,000 Machine-hours expected 1,000 2,000 Direct labor-hours expected 2,000 3,000 Materials handling (number of moves) 600 700 Machine setups (number of setups) 200 150 The following costs are expected to be incurred throughout...
Jennifer Company has two products: A and B. The company uses activity-based costing
Jennifer Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows: The activity rate under the activity based costing system for Supporting customers is closest to:
CVP with Activity-Based Costing and Multiple Products Busy-Bee Baking Company produces a variety of breads. The...
CVP with Activity-Based Costing and Multiple Products Busy-Bee Baking Company produces a variety of breads. The plant manager would like to expand production into sweet rolls as well. The average price of a loaf of bread is $1. Anticipated price for a package of sweet rolls is $1.50. Costs for the new level of production are as follows: Cost Driver Unit Variable Cost Level of Cost Driver Loaf of bread $0.65           —           Package of sweet rolls $0.93           —           Setups $300          ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT