Question

In: Finance

We are evaluating a project that costs $1,140,000, has a life of 10 years, and has...

We are evaluating a project that costs $1,140,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 36,000 units per year. Price per unit is $50, variable cost per unit is $20, and fixed costs are $720,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project.

a.

Calculate the accounting break-even point.

b-1.

Calculate the base-case cash flow and NPV.

b-2.

What is the sensitivity of NPV to changes in the sales figure?

c. What is the sensitivity of OCF to changes in the variable cost figure?

Solutions

Expert Solution

Part a:

So if the company produces 24000 units, it will reach the accounting break even

Part b-1: Following steps need to be taken:

  1. Calculate depreciation
  2. Calculate annual CF for years 1-10
    • Particulars Remark CF years 1-10
      Units sales Given 36000
      SP Given 50
      Sales SP x Unit sales 50 x 36000 = 1800000
      VC per unit Given 20
      Total Variable cost VC per unit x Unit sales 20 x 36000 = 720000
      Fixed cost Given 720000
      EBITDA Sales-Total Variable cost-Fixed Cost 1800000-720000-720000 = 360000
      Depreciation Calculated above $ 114,000.00
      EBT EBITDA-Depreciation $ 2,46,000.00
      Tax 23% x EBT $56,580.00
      EAT EBT-Tax $ 1,89,420.00
      Depreciation Added back as non cash 114000
      OCF EAT+Depreciation $ 3,03,420.00
  3. Calculate NPV
    • Year CF Discount Factor Discounted CF
      0 $   -11,40,000.00 1/(1+0.12)^0= 1 1*-1140000= $   -11,40,000.00
      1 $       3,03,420.00 1/(1+0.12)^1= 0.892857 0.892857142857143*303420= $       2,70,910.71
      2 $       3,03,420.00 1/(1+0.12)^2= 0.797194 0.79719387755102*303420= $       2,41,884.57
      3 $       3,03,420.00 1/(1+0.12)^3= 0.71178 0.711780247813411*303420= $       2,15,968.36
      4 $       3,03,420.00 1/(1+0.12)^4= 0.635518 0.635518078404831*303420= $       1,92,828.90
      5 $       3,03,420.00 1/(1+0.12)^5= 0.567427 0.567426855718599*303420= $       1,72,168.66
      6 $       3,03,420.00 1/(1+0.12)^6= 0.506631 0.506631121177321*303420= $       1,53,722.01
      7 $       3,03,420.00 1/(1+0.12)^7= 0.452349 0.452349215336893*303420= $       1,37,251.80
      8 $       3,03,420.00 1/(1+0.12)^8= 0.403883 0.403883227979369*303420= $       1,22,546.25
      9 $       3,03,420.00 1/(1+0.12)^9= 0.36061 0.36061002498158*303420= $       1,09,416.29
      10 $       3,03,420.00 1/(1+0.12)^10= 0.321973 0.321973236590696*303420= $           97,693.12
      NPV = Sum of all Discounted CF $       5,74,390.67
    • So NPV =  $574,390.67
    • Positive NPV suggests we should invest in the project

Part b-2: Lets increase and decrease the sales by 1% and see the impact of the same on NPV

Following is the table showing the change in OCF:

Particulars Base Case 1% -1%
Units sales 36000 36000 36000
SP 50 50.5 49.5
Sales 1800000 1818000 1782000
VC per unit 20 20 20
Total Variable cost 720000 720000 720000
Fixed cost 720000 720000 720000
EBITDA 360000 378000 342000
Depreciation $ 1,14,000.00 114000 114000
EBT $ 2,46,000.00 $    2,64,000.00 $ 2,28,000.00
Tax $     56,580.00 $       60,720.00 $     52,440.00
EAT $ 1,89,420.00 $    2,03,280.00 $ 1,75,560.00
Depreciation 114000 114000 114000
OCF $ 3,03,420.00 $    3,17,280.00 $ 2,89,560.00

NPV Calculation is as follows:

Year CF Discount Factor Discounted CF
0 $   -11,40,000.00 1/(1+0.12)^0= 1 1*-1140000= $   -11,40,000.00
1 $       3,17,280.00 1/(1+0.12)^1= 0.892857 0.892857142857143*317280= $       2,83,285.71
2 $       3,17,280.00 1/(1+0.12)^2= 0.797194 0.79719387755102*317280= $       2,52,933.67
3 $       3,17,280.00 1/(1+0.12)^3= 0.71178 0.711780247813411*317280= $       2,25,833.64
4 $       3,17,280.00 1/(1+0.12)^4= 0.635518 0.635518078404831*317280= $       2,01,637.18
5 $       3,17,280.00 1/(1+0.12)^5= 0.567427 0.567426855718599*317280= $       1,80,033.19
6 $       3,17,280.00 1/(1+0.12)^6= 0.506631 0.506631121177321*317280= $       1,60,743.92
7 $       3,17,280.00 1/(1+0.12)^7= 0.452349 0.452349215336893*317280= $       1,43,521.36
8 $       3,17,280.00 1/(1+0.12)^8= 0.403883 0.403883227979369*317280= $       1,28,144.07
9 $       3,17,280.00 1/(1+0.12)^9= 0.36061 0.36061002498158*317280= $       1,14,414.35
10 $       3,17,280.00 1/(1+0.12)^10= 0.321973 0.321973236590696*317280= $       1,02,155.67
NPV = Sum of all Discounted CF $       6,52,702.76
Year CF Discount Factor Discounted CF
0 $   -11,40,000.00 1/(1+0.12)^0= 1 1*-1140000= $   -11,40,000.00
1 $       2,89,560.00 1/(1+0.12)^1= 0.892857 0.892857142857143*289560= $       2,58,535.71
2 $       2,89,560.00 1/(1+0.12)^2= 0.797194 0.79719387755102*289560= $       2,30,835.46
3 $       2,89,560.00 1/(1+0.12)^3= 0.71178 0.711780247813411*289560= $       2,06,103.09
4 $       2,89,560.00 1/(1+0.12)^4= 0.635518 0.635518078404831*289560= $       1,84,020.61
5 $       2,89,560.00 1/(1+0.12)^5= 0.567427 0.567426855718599*289560= $       1,64,304.12
6 $       2,89,560.00 1/(1+0.12)^6= 0.506631 0.506631121177321*289560= $       1,46,700.11
7 $       2,89,560.00 1/(1+0.12)^7= 0.452349 0.452349215336893*289560= $       1,30,982.24
8 $       2,89,560.00 1/(1+0.12)^8= 0.403883 0.403883227979369*289560= $       1,16,948.43
9 $       2,89,560.00 1/(1+0.12)^9= 0.36061 0.36061002498158*289560= $       1,04,418.24
10 $       2,89,560.00 1/(1+0.12)^10= 0.321973 0.321973236590696*289560= $           93,230.57
NPV = Sum of all Discounted CF $       4,96,078.58

Sensitivity of NPV is shown in the below table:

Particulars Base Case 1% -1%
Sales $           18,00,000.00 $           18,18,000.00 $           17,82,000.00
NPV $             5,74,390.67 $             6,52,702.76 $             4,96,078.58
Percentage change 652701.76/574390.67 -1 =14% 496078.58/574390.67 -1 = -14%

So with a change of 1% in the sales, the NPV changes by 14% in the same direction as sales.

Part C:

Particulars Base Case 1% -1%
Units sales 36000 36000 36000
SP 50 50 50
Sales $ 18,00,000.00 $ 18,00,000.00 $ 18,00,000.00
VC per unit 20 20.2 19.8
Total Variable cost 720000 727200 712800
Fixed cost 720000 720000 720000
EBITDA 360000 352800 367200
Depreciation $    1,14,000.00 114000 114000
EBT $    2,46,000.00 $    2,38,800.00 $    2,53,200.00
Tax $       56,580.00 $       54,924.00 $       58,236.00
EAT $    1,89,420.00 $    1,83,876.00 $    1,94,964.00
Depreciation 114000 114000 114000
OCF $    3,03,420.00 $    2,97,876.00 $    3,08,964.00
Percentage change 2,97,876.00/3,03,420.00 -1 = -1.83% 3,08,964.00/3,03,420.00-1 = 1.83%

So with a change of 1% in the Variable coast per unit, the OCF changes by 1.83% in the opposite direction.


Related Solutions

We are evaluating a project that costs $1,140,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,140,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 36,000 units per year. Price per unit is $50, variable cost per unit is $20, and fixed costs are $720,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 47,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $820,000 per year. The tax rate is 21 percent and we require a return of 16 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $730,000 per year. The tax rate is 25 percent and we require a return of 15 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,080,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $730,000 per year. The tax rate is 25 percent and we require a return of 15 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,100,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 47,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $820,000 per year. The tax rate is 21 percent and we require a return of 16 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,180,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,180,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 59,000 units per year. Price per unit is $45, variable cost per unit is $25, and fixed costs are $750,000 per year. The tax rate is 25 percent and we require a return of 14 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,160,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,160,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 24 percent and we require a return of 13 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $972,000, has a life of twelve years, and has...
We are evaluating a project that costs $972,000, has a life of twelve years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 117,000 units per year. Price per unit is $35, variable cost per unit is $25, and fixed costs are $989,496 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $743,000, has a life of eight years, and has...
We are evaluating a project that costs $743,000, has a life of eight years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $37, variable cost per unit is $20, and fixed costs are $749,687 per year. The tax rate is 22 percent, and we require a return of 21 percent on this project. The projections given for price,...
We are evaluating a project that costs $709,000, has a life of fifteen years, and has...
We are evaluating a project that costs $709,000, has a life of fifteen years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 96,000 units per year. Price per unit is $43, variable cost per unit is $21, and fixed costs are $723,889 per year. The tax rate is 23 percent, and we require a return of 16 percent on this project. The projections given for price,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT