Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:
Direct materials: 4 pounds at $10 per pound | $ | 40 |
Direct labor: 2 hours at $13 per hour | 26 | |
Variable overhead: 2 hours at $9 per hour | 18 | |
Total standard cost per unit | $ | 84 |
The planning budget for March was based on producing and selling 29,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs:
Direct laborers worked 59,000 hours at a rate of $14 per hour.
Total variable manufacturing overhead for the month was $564,040.
______________________________
5. If Preble had purchased 174,000 pounds of materials at $8.50 per pound and used 160,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
6. If Preble had purchased 174,000 pounds of materials at $8.50 per pound and used 160,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
7. What direct labor cost would be included in the company’s planning budget for March?
8. What direct labor cost would be included in the company’s flexible budget for March?