Question

In: Operations Management

Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each...

  1. Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan consists of a housing assembly, two grills, a fan assembly, and an electrical unit. The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch, and a knob. The following table gives lead times, on-hand inventory, and scheduled receipts. See the following data table:
    1. Construct a product structure.
    2. Construct a time-phased product structure.
    3. Prepare a net material requirements plan.

COMPONENT

LEAD

ON-HAND

LOT

SCHEDULED

COMPONENT

TIME

INVENTORY

SIZE

RECEIPT

Fan

1

100

Housing

1

100

Frame

2

Supports (2)

1

50

100

Handle

1

400

500

Grills (2)

2

200

500

Fan Assembly

3

150

Hub

1

Blades (5)

2

100

Electrical Unit

1

Motor

1

Switch

1

20

12

Knob

1

25

200 knobs in week 2

Solutions

Expert Solution

Below is the product structure -

Below is the time phased structure -

Below is the MRP schedule -

Fan
Q = L4L
LT = 1
On Hand 1 2 3 4 5 6 7
Gross Requirement 0 0 0 0 0 0 1000
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 100 100 100 100 100 100 100 0
Net Requirements 0 0 0 0 0 0 900
Planned Order Receipts 0 0 0 0 0 0 900
Planned Order Releases 0 0 0 0 0 900 0
Housing Assembly
Q = L4L
LT = 1
Gross Requirement 0 0 0 0 0 900 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 100 100 100 100 100 100 0 0
Net Requirements 0 0 0 0 0 800 0
Planned Order Receipts 0 0 0 0 0 800 0
Planned Order Releases 0 0 0 0 800 0 0
Grill
Q = 500
LT = 2
Gross Requirement 0 0 0 0 0 1800 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 200 200 200 200 200 200 400 400
Net Requirements 0 0 0 0 0 1600 0
Planned Order Receipts 0 0 0 0 0 2000 0
Planned Order Releases 0 0 0 2000 0 0 0
Fan Assebly
Q = L4L
LT = 3
Gross Requirement 0 0 0 0 0 900 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 150 150 150 150 150 150 0 0
Net Requirements 0 0 0 0 0 750 0
Planned Order Receipts 0 0 0 0 0 750 0
Planned Order Releases 0 0 750 0 0 0 0
Electrical Unit
Q = L4L
LT = 1
Gross Requirement 0 0 0 0 0 900 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0
Net Requirements 0 0 0 0 0 900 0
Planned Order Receipts 0 0 0 0 0 900 0
Planned Order Releases 0 0 0 0 900 0 0
Frame
Q = L4L
LT = 2
Gross Requirement 0 0 0 0 800 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0
Net Requirements 0 0 0 0 800 0 0
Planned Order Receipts 0 0 0 0 800 0 0
Planned Order Releases 0 0 800 0 0 0 0
Suports
Q = 100
LT = 1
Gross Requirement 0 0 0 0 1600 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 50 50 50 50 50 50 50 50
Net Requirements 0 0 0 0 1550 0 0
Planned Order Receipts 0 0 0 0 1600 0 0
Planned Order Releases 0 0 0 1600 0 0 0
Handle
Q = 500
LT = 1
Gross Requirement 0 0 0 0 800 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 400 400 400 400 400 100 100 100
Net Requirements 0 0 0 0 400 0 0
Planned Order Receipts 0 0 0 0 500 0 0
Planned Order Releases 0 0 0 500 0 0 0
Hub
Q = L4L
LT = 1
Gross Requirement 0 0 750 0 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0
Net Requirements 0 0 750 0 0 0 0
Planned Order Receipts 0 0 750 0 0 0 0
Planned Order Releases 0 750 0 0 0 0 0
Blades
Q = 100
LT = 2
Gross Requirement 0 0 3750 0 0 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 50 50 50 50 50
Net Requirements 0 0 3750 0 0 0 0
Planned Order Receipts 0 0 3800 0 0 0 0
Planned Order Releases 3800 0 0 0 0 0 0
Motor
Q = L4L
LT = 1
Gross Requirement 0 0 0 0 900 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0
Net Requirements 0 0 0 0 900 0 0
Planned Order Receipts 0 0 0 0 900 0 0
Planned Order Releases 0 0 0 900 0 0 0
Switch
Q = 12
LT = 1
Gross Requirement 0 0 0 0 900 0 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 20 20 20 20 20 8 8 8
Net Requirements 0 0 0 0 880 0 0
Planned Order Receipts 0 0 0 0 888 0 0
Planned Order Releases 0 0 0 888 0 0 0
Knob
Q = 25
LT = 1
Gross Requirement 0 0 0 0 900 0 0
Scheduled Receipts 0 200 0 0 0 0 0
Projected on Hand 0 0 200 200 200 0 0 0
Net Requirements 0 0 0 0 700 0 0
Planned Order Receipts 0 0 0 0 700 0 0
Planned Order Releases 0 0 0 700 0 0 0

Related Solutions

"A manufacturing company has just received an order with the following financial data. All dollar values...
"A manufacturing company has just received an order with the following financial data. All dollar values are given in constant dollars, and inflation will impact the annual revenue, annual operating cost, and the salvage value. The two-year project requires immediately purchasing equipment for $59,000. The equipment falls into the MACRS 5-year class. The machine will be sold for $19,000 at the end of two years. The project will bring in additional annual revenue of $99,000, but it is expected to...
"A manufacturing company has just received an order with the following financial data. All dollar values...
"A manufacturing company has just received an order with the following financial data. All dollar values are given in constant dollars, and inflation will impact the annual revenue, annual operating cost, and the salvage value. The two-year project requires immediately purchasing equipment for $56,000. The equipment falls into the MACRS 5-year class. The machine will be sold for $22,000 at the end of two years. The project will bring in additional annual revenue of $82,000, but it is expected to...
"A manufacturing company has just received an order with the following financial data. All dollar values...
"A manufacturing company has just received an order with the following financial data. All dollar values are given in constant dollars, and inflation will impact the annual revenue, annual operating cost, and the salvage value. The two-year project requires immediately purchasing equipment for $56,000. The equipment falls into the MACRS 5-year class. The machine will be sold for $22,000 at the end of two years. The project will bring in additional annual revenue of $82,000, but it is expected to...
A company is advertising 20 jobs and has received 75 appli- cations. One of the criteria...
A company is advertising 20 jobs and has received 75 appli- cations. One of the criteria to rank applicants is the score of an aptitude test. The test assesses different skills of the applicants such as analytical and verbal skills. The test is scored from 200 to 800. During the time interval 2016–2019, on applications for similar jobs, the mean test score was 556.04 while the stan- dard deviation was 120.45. Based on this information, find the probability that an...
20. The Company has a $48,000 pure discount bond that comes due in one year. The...
20. The Company has a $48,000 pure discount bond that comes due in one year. The risk-free rate of return is 3 percent. The firm's assets are expected to be worth either $45,000 or $55,000 in one year. Currently, these assets are worth $50,000. What is the current value of the firm's debt? $43,724.75 $47,681.49 $46,277.13 $45,582.52 $44,106.59
Your firm has recently received an order for 500 units priced at $200 each from a...
Your firm has recently received an order for 500 units priced at $200 each from a distributor in Toronto (Canada). To fill the order, you have two options: Import polyester from a supplier in Monterrey (Mexico) to your manufacturing plant in Nashville (USA). Transform the polyester into carpet (1 unit of polyester = 1 unit of carpet), then transport the carpet to Toronto. Doing this comes at the following costs: Price of polyester from your Mexican supplier: 500 MEX (pesos)...
Anna is a 29-year-old G2P1 who has just had a 20-week routine anatomy ultrasound. The physician...
Anna is a 29-year-old G2P1 who has just had a 20-week routine anatomy ultrasound. The physician informed her that there were some “soft markers” for Down syndrome and that genetic amniocentesis is available if she wants to have it. Please answer all questions Anna asks if the ultrasound shows that the fetus has Down syndrome. How can the nurse explain the “soft markers” for Down syndrome? What counseling should Anna receive about amniocentesis? Anna decided to go home and discuss...
Special Order Pope Company manufactures a variety of hiking boots and has received a special one-time-only...
Special Order Pope Company manufactures a variety of hiking boots and has received a special one-time-only order from a new customer. Pope has sufficient idle capacity to accept the special order to manufacture 1,000 pairs of boots at a price of $50.00 per pair. Pope’s normal selling price is $65.00 per pair of boots. Variable manufacturing costs are $35.00 per pair and fixed manufacturing costs are $12.00 a pair. Pope’s variable selling expense for its normal line of boots is...
Bluebird Mfg. has received a special one-time order for 15,000 bird feeders at $2.10 per unit....
Bluebird Mfg. has received a special one-time order for 15,000 bird feeders at $2.10 per unit. Bluebird currently produces and sells 75,000 units at $6.10 each. This level represents 80% of its capacity. These bird feeders would be marketed under the wholesaler’s name and would not affect Bluebird’s sales through its normal channels. Production costs for these units are $3.45 per unit, which includes $1.80 variable cost and $1.65 fixed cost. If Bluebird accepts this additional business, the effect on...
7. A consulting firm has received 2 Super Bowl playoff tickets from one of its clients....
7. A consulting firm has received 2 Super Bowl playoff tickets from one of its clients. To be fair, the firm is randomly selecting two different employee names to "win" the tickets. There are 8 secretaries, 7 consultants and 5 partners in the firm. Which of the following statements is not true? A) The probability of a secretary winning a ticket on the first draw is 8/20. B) The probability of a secretary winning a ticket on the second draw...