Question

In: Economics

Assume your employer, Company A, entered into a contract with Company B to supply 10,000 Widgets...

Assume your employer, Company A, entered into a contract with Company B to supply 10,000 Widgets and that the contract meets all of the requirements to be binding upon the parties. On the date that delivery is required, Company B contacts Company A and advises them that the widgets will not be available. Assume Company B is in breach. What are Company A's options? What would you recommend to your management team on how to proceed?"

Solutions

Expert Solution

A contract signed between the two parties imposes certain obligations which has to be fulfilled by the parties entering the contract. A 'Breach' of contract is a situation where one party fails to to fulfill any of its obligations. As stated in the question, Company B informed the Company A that the order would not be available on the date of delivery. In this situation, Company A has following options:

1. Company A can seek further details about the status of the order to assess how many widgets Company B can supply at the delivery date. If Company B has completed the order partially, Company A can provide further extension to Company B for a week or 15 days or a month upon their written request.

2. In case, Company B has not begin production of widgets at the delivery date, Company A can seek reasons behind the failure of delivery. Company A can terminate the contract with Company B after receiving the information as Company B has failed to fulfill their obligation. Company A can give the order of widgets to a new company. However, this will consume more time and effort.

3. Company A can take legal action against Company B for breach of contract, Company A can file civil lawsuit against Company B seeking damages or losses caused by Company B's failure to fulfill its obligation on time. However, legal action also requires time and effort.

The most feasible option would be option (1) as the other options will take time, money and effort of Company A.


Related Solutions

P11.7A (LO 4) On April 2, 2021, Pharma Company entered into a contract to supply medication...
P11.7A (LO 4) On April 2, 2021, Pharma Company entered into a contract to supply medication to Laxall Drug Stores, FOB shipping point, terms 2/30, n/45. The selling price of the medication is $40,000 and the medication cost Pharma Company $25,000. Pharma has a stated return policy that goods may be returned within 30 days. The medication was shipped on April 10, 2021. Pharma's management estimates returns using the expected value method and sales discounts are estimated using the most...
a) Buyer A has entered into a contract for the sale of goods with Seller B....
a) Buyer A has entered into a contract for the sale of goods with Seller B. Seller B has delivered nonconforming goods but has promised to cure the defects. After three months of waiting, Seller B has not cured the defect. What remedy does Buyer A have?   b) Buyer A has entered into a contract for the sale of goods with Seller B. Buyer A has breached the contract while the goods are in transit. What remedy does Seller B...
a)   Buyer A has entered into a contract for the sale of goods with Seller B....
a)   Buyer A has entered into a contract for the sale of goods with Seller B. The contract provides that Seller B will deliver the goods on May 1, 2010. On May 1, 2010, Seller B informs A that it will not be able to perform the contract. Assume Buyer A was going to pay $3,000 for the goods under the contract with Seller B. Seller C will sell Buyer A the goods for $4,000 plus a transportation cost of...
Buyer A has entered into a contract for the sale of goods with Seller B.
Buyer A has entered into a contract for the sale of goods with Seller B. The contract provides that Seller B will deliver the goods on May 1, 2010. On February 1, 2010, Seller B informs A that it will not be able to perform the contract. What has occurred and what remedies are available to A in this case?
Assume that your widget manufacturing company has a total annual demand of N widgets per year...
Assume that your widget manufacturing company has a total annual demand of N widgets per year evenly distributed across the year. Each widget cost $b dollars in material and manufacturing costs to make. Every time you do a production run to make some widgets, you incur a set-up cost of P dollars. Any widgets awaiting sale must be stored and thus incur an average storage fee of c dollars per widget per year. Let x be the size of each...
The National Division of Roboto Company is buying 10,000 widgets from an outside supplier at $30...
The National Division of Roboto Company is buying 10,000 widgets from an outside supplier at $30 per unit. Roboto's Overseas Division, which is producing and selling at full capacity (12,000 units), has the following sales and cost structure: Sales price per unit $45.00 Variable cost per unit 22.50 Fixed cost (at capacity) per unit 15.00 If the Overseas Division meets the outside supplier's price and sells the 10,000 widgets to National, the effect on overall company profits will be: A....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2013, the Plumbing Company entered into a contract to construct a road for San Diego...
In 2013, the Plumbing Company entered into a contract to construct a road for San Diego County for $12,000,000. The road was completed in 2015. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $3,000,000 $3,800,000 $2,700,000 Estimated costs to complete as of year-end 6,300,000 2,400,000 0 Billings during the year 3,700,000 4,000,000 4,300,000 Cash collections during the year 2,800,000 4,800,000 4,400,000 Calculate the amount of revenue and gross profit to be recognized...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT