Question

In: Operations Management

1. "Step X of a project has been budgted for 600. It is 50% complete. You...

1. "Step X of a project has been budgted for 600. It is 50% complete. You have spent 400 so far. Are you overbudget or underbudget. If you are underbudget, indicate the amount as a negative number. If you are overbudget, indicate the amount as a positive number (no plus)."

2. "Step X of a project has been budgted for 600. It is 90% complete. You have spent 400 so far. Are you overbudget or underbudget. If you are underbudget, indicate the amount as a negative number. If you are overbudget, indicate the amount as a positive number (no plus)."

3. "A project has 3 steps, Step 1 is 200 overbudget. Step 2 is 500 underbudget. Step 3 is 100 overbudget. Is the project overbudget or underbudget. Enter a negative number for underbudget. Enter a positive number for overbudget (no plus)."

4. "A project has 3 steps, Step 1 is 900 overbudget. Step 2 is 500 underbudget. Step 3 is 100 overbudget. Is the project overbudget or underbudget. Enter a negative number for underbudget. Enter a positive number for overbudget (no plus)."

5. "Step X normally takes 4 weeks and $800. You can crash it to 2 weeks and it cost $ 1200. What is the weekly crash cost? If this impossible, enter -999."

6. "Step X normally takes 4 weeks and $800. You can crash it to 2 weeks and it cost $ 1800. What is the weekly crash cost? If this impossible, enter -999."

7. "Step X normally takes 1 weeks and $800. You can crash it and it will cost $ 1200. What is the weekly crash cost? If this impossible, enter -999."

8. "Step X normally takes 4 weeks and $800. You can crash it to 4 weeks and it cost $ 1200. What is the weekly crash cost? If this impossible, enter -999."

9. "Step X: EST = 5, LST = 8, LFT = 9, What is EFT? (Enter -999 if node is impossible) "

10. "Step X: EST = 5, LST = 8, LFT = 7. What is the EFT? (If the node is in error, enter -999)"

11. "Step X: EST = 8, LST = 12, LST = 9, LFT = 12. What is slack? (enter -999 for impossible nodes) "

Solutions

Expert Solution

  1. Budgeted cost for 50% completed project = 50% of $600 = $300

Expenditure made so far = $400

We are therefore overbudget by = $400 - $300 = $100

OVERBUDGET = $100

2.Budgeted cost for the 90% completed project = 90% of $600 = $540

Expenditure made so far = $400

We are therefore underbudget by = $540 - $400 = $140

UNDERBUDGET = - $140

3. Total amount of overbudget = $200 + $100 = $300

Total amount of underbudget = $500

Project is net underbudgetby = $500 - $300 = 4200

UNDERBUDGT = - $200

4. Total amount of overbudget = $900 + $100 = $1000

Total amount of underbudget = $500

Project is overbudget by = $1000 - $500 = $500

5. Weekly crashing cost

= ( Crash cost – Normal cost ) / ( Normal duration weeks – Crash duration weeks )

= ( 1200 – 800 ) / ( 4 -2 )

= 400/2

= $200

6. Weekly crashing cost

= ( Crash cost – Normal cost ) / ( Normal duration weeks – Crash duration weeks )

= ( 1800 – 800 ) / ( 4 – 2 )

= 1000/2

= $500

7. The step is crashed from 1 week it means it will complete in ZERO weeks. Assuming a step can be completed in ZERO time ( read ‘negligible time’) ,

Weekly crashing cost

= ( Crash cost – Normal cost ) / ( Normal duration weeks – Crash duration weeks )

= ( 1200 – 800 ) / ( 1 – 0)

= $400

8. Crashing of a step means reducing duration of the step. It is thus not possible to crash a project of normal duration of 4 weeks to same number of weeks i.e with no reduction in duration.

Answer is : IMPOSSIBLE ( - 999)

9. Slack = LST – EST = 8 – 5 = 3

Also

Slack = LFT – EFT

Or EFT = LFT – Slack = 9 – 3 = 6

EFT = 6

10. LFT stands for Late Finish time and LST stands for Late Start time .

Given ,

LFT = 7 and LST = 8

Since LFT should always occur after LST ,

It must be that LFT > LST

However that is not the case here.

Therefore answer is : ERROR ( - 999)

11. There cannot be two different values of Late start Time ( LST ) for the same step . Therefore Slack cannot be calculated.

Answer : IMPOSSIBLE ( - 999)


Related Solutions

STEP 1: You are doing research on balance and fitness. To complete this research you will...
STEP 1: You are doing research on balance and fitness. To complete this research you will need a watch with a second hand. Identify a random sample of n = 12 men and n = 8 women. You must answer this question: How do you establish that this sample is truly random? STEP 2: Have each subject perform the following task: Have the subjects stand with their hands at their side, raise one knee, cross their ankle over the other...
Solve STEP BY STEP using power series about x = -1, 4(x+1)^2 y'' - 2(x+1)(x+3) y'...
Solve STEP BY STEP using power series about x = -1, 4(x+1)^2 y'' - 2(x+1)(x+3) y' + (x+4) y = 0. note, solve by power series, variable transformation by letting: w= x+1 = 0
solve step by step using power series solution, about x = -1, 4 (x+1)^2 y'' -...
solve step by step using power series solution, about x = -1, 4 (x+1)^2 y'' - 2(x+1)(x+3)y' + (x+4) y =0
You are an analyst at a bank that has been asked to look into a project...
You are an analyst at a bank that has been asked to look into a project that is being undertaken by ABC Corp with a life of 10 years. The project will return cash flows of $2 million every year for 5 years and 4 million for the remaining 5 years after an initial investment of $10 million. The firm has a beta of 0.5 and the expected return of the market is 11%. There are currently 20000 shares outstanding...
Imagine that you are project engineer that has been asked to project (forecast) a cash flow...
Imagine that you are project engineer that has been asked to project (forecast) a cash flow for a new project. What would you do for the following: a. Can the forecasts be biased in any way? b. If so, in what direction and why do you think that’s the case? c. How can a manager and/or their firm neutralize the bias?
What if you were a project engineer that has been asked to project (forecast) a cash...
What if you were a project engineer that has been asked to project (forecast) a cash flow for a new project. What would you do for the following: a. Can the forecasts be biased in any way? b. If so, in what direction and why do you think that’s the case? c. How can a manager and/or their firm neutralize the bias?
please solve this systems of equations step by step, you rock: 8.3z=3.6-5.6y 8.3z=5.7+1-(1.2+3.2)x z=x+y
please solve this systems of equations step by step, you rock: 8.3z=3.6-5.6y 8.3z=5.7+1-(1.2+3.2)x z=x+y
Question 1 Suppose that you have been appointed the project manager for a project to develop...
Question 1 Suppose that you have been appointed the project manager for a project to develop an online booking system for a multi-doctor medical practice that will replace an existing desktop system. The key functionality that is required is as follows: • Patient registration • Patient login • Book first available appointment with any doctor • Book an appointment at a time of the patient’s choosing with a doctor of their choice. What development methodologies should you consider? How would...
You are a project manager who has been assigned to a new project that would require  “Porting...
You are a project manager who has been assigned to a new project that would require  “Porting of the existing backend server code-base that currently runs on the OS platform ABC to another OS platform XYZ so that the backend sever code-base would run on XYZ OS platform as well the OS platform ABC, when finished”.  Both of the OS platforms are used heavily by the company and are well understood by the technical staff. The functionalities would remain the same and...
Step 1: Complete the following in the “General Journal” tab at the bottom of the Janie’s...
Step 1: Complete the following in the “General Journal” tab at the bottom of the Janie’s Cupcakes, Inc. Student Workbook). The following events occur in July 2014: • July 1 – You take $10,000 from your personal savings account and buy common stock in Janie’s Cupcakes, Inc.. • July 1 – Paid $4000 on a lease for bakery space. The lease is for 1 year, and requires first and last month’s rent up front. Lease period is effective July 1st...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT