Question

In: Operations Management

Two examples of massively mismanaged projects are TAURUS and the “Big Dig.” The first, formally called...

Two examples of massively mismanaged projects are TAURUS and the “Big Dig.” The first, formally called the London Stock Exchange Automation Project, cost $575 million before it was finally abandoned. Although most IT projects have a reputation for cost overruns, delays, and under performance, TAURUS set a new standard. But even TAURUS paled next to the biggest, most expensive public works project in U.S. history—Boston’s 15-year-long Central Artery/Tunnel Project. Called the Big Dig, this was perhaps the poorest and most felonious case of project mismanagement in decades. From a starting $2 billion budget to a final price tag of $15 billion, the Big Dig cost more than the Panama Canal, Hoover Dam, or Interstate 95, the 1,919-mile highway between Maine and Florida.

Questions 1. Explain why it faced such problems.

2. How and why do project managers allow such massive endeavors to fall into such a state?

3. What do you think are the causes?

Solutions

Expert Solution

The two projects that are being discussed in the case are Taurus and Big dig.

Taurus was a project focused on automating the stock exchange of UK. The project was initiated for an initial cost of 75 Million. The project got delayed due to multiple reasons and was finally abandoned after the cost and loses rose to 575 million.

The Big dig project was a project initiated to project initiated in Boston at an initial cost of 2 billion to connect the road network. The project was grossly mismanaged and the loses accumulated to 15 billion dollars.

1. One major reason why the Taurus project failed was due to the miscalculation in creation of the centralized data hub which would act as the repository for all data transactions. Such a change would have resulted in loss of jobs to large number of middlemen who were making huge profits using the manual methods. There was huge resistance to the new technology adoptment from the parties involved. Also the system was designed based on a model implemented in US. The engineers envisaged that the change from US model to UK model by swift adopting the regulatory and policy changes would be an easy task but it was not so. The major reasons for the big dig to fail were the following:

• Tunnel leaks

• Collapse of infrastructure

• Higher operational and overhead costs

The tunnel which was being dug faced lot of water leakage issues. The construction team tried to rectify them by using short term methods but it was not successful. During the construction of the tunnel, there was a fatal collapse of the ceiling too which was due to usage of substandard materials.

Looking at both the cases, there are few glaring issues which caused the problems. One of them was that the project team did not do a thorough study of the proposed solution. Also the vendors who were involved were not critically analyzed to check the materials and solutions being deployed.

2. One reason the project managers could not manage the issues was down to not planning the projects well enough, not anticipating the risks and proactively take risk mitigation approaches. For any project to succeed, there are two major areas the project teams should focus on.

• Identify possible risks and plan mitigation strategies

• Track all issues and take corrective actions as soon as possible

It is often the case that in spite of huge amount of time being invested for project planning, there will be deviations from the actual plan during execution. In reality, most of the projects globally tend to move away from the project baseline easily. While moving away from the planned due date may not be a great concern, additional resources being put to rectify the solution might cause major concerns for the project sponsors and leaders. It could be the same issue in case of Taurus and Big Dig. Someone rom project team might have identified the problems but the leadership might not have taken adequate actions to help in the issue. Also it could be possible that no one could anticipate such issues that arose during the project execution. Another reason which could have contributed to the failure of project was vendor mismanagement. The vendors and the materials should always be audited and should pass through quality checks to ensure operational issues do not rise.

3. Few major causes of the project failure for Taurus and Bid Dig are as given below:

• Lack of adequate project planning

• Lack of audit checks for vendors and materials

• No risk assessment or identification done to reduce risks

• No mitigation strategies prepared to tackle risks

• No tracking of critical issues during project execution

• There was no proper governance from experts who were involved in the project

• Underlying issues which were not rectified before initiation of project

• Lack of change management approach to ensure all stakeholders are on the same page


Related Solutions

Explain the importance of creating a project charter to formally initiate projects
Explain the importance of creating a project charter to formally initiate projects
JavaScript Write a function called "first" that takes in two arguments - the first is an...
JavaScript Write a function called "first" that takes in two arguments - the first is an argument called arr that is an array of numbers, the second is an optional number argument called num(hint: you'll need a default value - look back at the slides). If "num" was not passed in (since it's optional), the "first" function will return an array containing the first item of the array. If a value for "num" was given, the "first" function will return...
Big Inc. is considering Two Projects X and Y, whose cash flows are shown below. These...
Big Inc. is considering Two Projects X and Y, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. WACC: 8.00% Year 0 1 2 3 4 CFx −$1,100 $450 $500 $100 $100 CFy −$2,750 $625 $725 $800 $1,400 What are the MIRR’s? Discuss the importance of the MIRR method over IRR. If these projects are mutually exclusive...
Big toys manufacture a toy truck called “Big Red” that they distribute to retailers. The company...
Big toys manufacture a toy truck called “Big Red” that they distribute to retailers. The company is now planning for the third quarter of 2020. In order to keep production and shipments moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each month must be equal to 5,000 units plus 30 percent of the next month’s sales. The finished goods inventory on June 30 is budgeted to be 17,000 units....
Explain what is meant by “big data”. Write three examples for Big Data.
Explain what is meant by “big data”. Write three examples for Big Data.
You receive two job offers in the same big city. The first job is close to...
You receive two job offers in the same big city. The first job is close to your​ parents' house, and they have offered to let you live at home for a year so you​ won't have to incur expenses for​ housing, food, or cable and Internet. This job pays $ 40,000 per year. The second job is far away from your​ parents' house, so​ you'll have to rent an apartment with parking​($ 12,000 per​ year), buy your own food ​($...
You receive two job offers in the same big city. The first job is close to...
You receive two job offers in the same big city. The first job is close to your​ parents' house, and they have offered to let you live at home for a year so you​ won't have to incur expenses for​housing, food, or cable and Internet. This job pays $45,000 per year. The second job is far away from your​ parents' house, so​you'll have to rent an apartment with parking ​($12,500 per​ year), buy your own food ​($2,250 per​ year), and...
(a) Explain the difference between big-O and big-theta, and give examples of each to show the...
(a) Explain the difference between big-O and big-theta, and give examples of each to show the difference. (b) How can we say that two functions have the same asymptotic complexity, using big-theta notation? (c) Rank the following functions in order of increasing complexity (rate of growth), and indicate which functions have the same asymptotic complexity. x2; x log(x); 2x; log(x) + 7; 92x2 + 57x + 3921; 4x; 27x2 + 8x3; 22x+5; log(x42); 3x + 12.
2. Gurdreep is analyzing two projects. The first requires a $ 24,000 initial investment and returns...
2. Gurdreep is analyzing two projects. The first requires a $ 24,000 initial investment and returns $12,000 a year for four years. The second project requires a $30,000 initial investment and returns $14,000 a year for four years. What is the crossover point for these two projects? i need answer now on copy write
examples of cost improvement projects in a nursing unit
examples of cost improvement projects in a nursing unit
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT