In: Operations Management
Two examples of massively mismanaged projects are TAURUS and the “Big Dig.” The first, formally called the London Stock Exchange Automation Project, cost $575 million before it was finally abandoned. Although most IT projects have a reputation for cost overruns, delays, and under performance, TAURUS set a new standard. But even TAURUS paled next to the biggest, most expensive public works project in U.S. history—Boston’s 15-year-long Central Artery/Tunnel Project. Called the Big Dig, this was perhaps the poorest and most felonious case of project mismanagement in decades. From a starting $2 billion budget to a final price tag of $15 billion, the Big Dig cost more than the Panama Canal, Hoover Dam, or Interstate 95, the 1,919-mile highway between Maine and Florida.
Questions 1. Explain why it faced such problems.
2. How and why do project managers allow such massive endeavors to fall into such a state?
3. What do you think are the causes?
The two projects that are being discussed in the case are Taurus
and Big dig.
Taurus was a project focused on automating the stock exchange of
UK. The project was initiated for an initial cost of 75 Million.
The project got delayed due to multiple reasons and was finally
abandoned after the cost and loses rose to 575 million.
The Big dig project was a project initiated to project initiated in
Boston at an initial cost of 2 billion to connect the road network.
The project was grossly mismanaged and the loses accumulated to 15
billion dollars.
1. One major reason why the Taurus project failed was due to the
miscalculation in creation of the centralized data hub which would
act as the repository for all data transactions. Such a change
would have resulted in loss of jobs to large number of middlemen
who were making huge profits using the manual methods. There was
huge resistance to the new technology adoptment from the parties
involved. Also the system was designed based on a model implemented
in US. The engineers envisaged that the change from US model to UK
model by swift adopting the regulatory and policy changes would be
an easy task but it was not so. The major reasons for the big dig
to fail were the following:
• Tunnel leaks
• Collapse of infrastructure
• Higher operational and overhead costs
The tunnel which was being dug faced lot of water leakage issues.
The construction team tried to rectify them by using short term
methods but it was not successful. During the construction of the
tunnel, there was a fatal collapse of the ceiling too which was due
to usage of substandard materials.
Looking at both the cases, there are few glaring issues which
caused the problems. One of them was that the project team did not
do a thorough study of the proposed solution. Also the vendors who
were involved were not critically analyzed to check the materials
and solutions being deployed.
2. One reason the project managers could not manage the issues was
down to not planning the projects well enough, not anticipating the
risks and proactively take risk mitigation approaches. For any
project to succeed, there are two major areas the project teams
should focus on.
• Identify possible risks and plan mitigation strategies
• Track all issues and take corrective actions as soon as
possible
It is often the case that in spite of huge amount of time being
invested for project planning, there will be deviations from the
actual plan during execution. In reality, most of the projects
globally tend to move away from the project baseline easily. While
moving away from the planned due date may not be a great concern,
additional resources being put to rectify the solution might cause
major concerns for the project sponsors and leaders. It could be
the same issue in case of Taurus and Big Dig. Someone rom project
team might have identified the problems but the leadership might
not have taken adequate actions to help in the issue. Also it could
be possible that no one could anticipate such issues that arose
during the project execution. Another reason which could have
contributed to the failure of project was vendor mismanagement. The
vendors and the materials should always be audited and should pass
through quality checks to ensure operational issues do not
rise.
3. Few major causes of the project failure for Taurus and Bid Dig
are as given below:
• Lack of adequate project planning
• Lack of audit checks for vendors and materials
• No risk assessment or identification done to reduce risks
• No mitigation strategies prepared to tackle risks
• No tracking of critical issues during project execution
• There was no proper governance from experts who were involved in
the project
• Underlying issues which were not rectified before initiation of
project
• Lack of change management approach to ensure all stakeholders are
on the same page