In: Finance
Which of the following statements is (are) correct? (x) If the
cost of an investment is $20,000 and the annual sales from the
investment is 12.5 percent of the cost, then the payback period is
8.0 years.
(y) It is always possible to determine a payback period when the
cash inflows from the project are uneven as long as the cash
inflows exceed the cost of the project.
(z) If the discounted payback period for a given project is longer
than the payback benchmark then the firm will not pursue the
project even though it may have a NPV greater than zero.
A. (x), (y) and (z)
B. (x) and (y) only
C. (x) and (z) only
D. (y) and (z) only
E. (z) only
You are considering the purchase of an investment that would pay
you $2,450 per year for Years 1, 2 and 3, $2,225 per year for Years
4, 5, 6 and 7, and $1,850 per year for Years 8, 9 and 10. If you
require a 11.25% rate of return, and the cash flows occur at the
end of each year, then how much should you be willing to pay for
this investment?
A. more than $14,550
B. between $14,100 and $14,550
C. between $13,650 and $14,100
D. between $13,200 and $13,650
E. between $12,750 and $13,200
As a student of finance, you predict that the net present value
(NPV) of a proposed new $12.5 million warehouse is $1 million. You
determined that the firm’s cost of capital is 8.75%. How should
these findings be interpreted?
A. More information such as the payback period should be evaluated
since the reliance on only one capital budgeting technique should
be discouraged.
B. Although NPV is positive, its value is too low for such a large
expenditure and as a result, the project should be rejected.
C. The project should be rejected because the NPV is less than the
8.75% of the cost of the warehouse.
D. The project does not meet the acceptance criteria of the NPV
method and should be rejected.
E. The project should be accepted because it will add value to the
firm.
1. B. Only x and y (if revenue 12.5% of the cost, then payback period=1/12.5%=8. And even if cash flow is uneven, payback period can be determined, if NPV is zero then project can be accepted)
2.
Below is the calculation of the present value for such cash flow:
Year | Cashflow | Present Value @11.25% (i.e. Cashflow/1.1125^year) |
1 | 2,450.00 | 2,202.25 |
2 | 2,450.00 | 1,979.55 |
3 | 2,450.00 | 1,779.37 |
4 | 2,225.00 | 1,452.55 |
5 | 2,225.00 | 1,305.66 |
6 | 2,225.00 | 1,173.63 |
7 | 2,225.00 | 1,054.95 |
8 | 1,850.00 | 788.45 |
9 | 1,850.00 | 708.71 |
10 | 1,850.00 | 637.05 |
Total | 13,082.15 |
So, you need to invest $13082.15. Option E is correct.
3. E. The project should be accepted as the project will add value to the firm.