In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 1,491,000 $ 3,195,000 $ 2,655,400 Estimated costs to complete as of year-end 5,609,000 2,414,000 0 Billings during the year 1,100,000 3,586,000 5,314,000 Cash collections during the year 900,000 2,700,000 6,400,000 Westgate Construction uses the completed contract method of accounting for long-term construction contracts. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,590,000 $ 3,895,000 $ 3,290,000 Estimated costs to complete as of year-end 5,790,000 3,290,000 0 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,590,000 $ 3,895,000 $ 4,185,000 Estimated costs to complete as of year-end 5,790,000 4,290,000 0
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,016,000 | $ | 2,808,000 | $ | 2,613,600 | |||
| Estimated costs to complete as of year-end | 5,184,000 | 2,376,000 | 0 | ||||||
| Billings during the year | 2,180,000 | 2,644,000 | 5,176,000 | ||||||
| Cash collections during the year | 1,890,000 | 2,500,000 | 5,610,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,016,000 | $ | 3,890,000 | $ | 3,290,000 | |||
| Estimated costs to complete as of year-end | 5,184,000 | 3,190,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,016,000 | $ | 3,890,000 | $ | 4,170,000 | |||
| Estimated costs to complete as of year-end | 5,184,000 | 4,280,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 3,820,000 $ 3,220,000 Estimated costs to complete as of year-end 5,796,000 3,120,000 0 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 3,820,000 $ 3,960,000 Estimated costs to complete as of year-end 5,796,000 4,140,000 0
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:
|
|
2018 |
2019 |
2020 |
|
Cost incurred during the year |
2,400,000 |
3,600,000 |
2,200,000 |
|
Estimated costs to complete as of year-end |
5,600,000 |
2,000,000 |
0 |
|
Billings during the year |
2,000,000 |
4,000,000 |
4,000,000 |
|
Cash collections during the year |
1,800,000 |
3,600,000 |
4,600,000 |
|
2-a. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2018 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2019 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries (construction costs, progress billings, cash collections, gross profit/loss) for the year 2020 (credit "Various accounts" for construction costs incurred). |
|
|
|
||||||
|
|
|||||||||
|
|
|||||||||
|
|
|||||||||
|
|
|||||||||
In: Accounting
in 2018 the westgate construction company entered into a contract to construct a road for Santa Clara County for 10,000,000 The road was completed in 2020. Calculate the amount of revenue and gross profit to be recognized in each of the 3 years assuming the following costs to incur and costs to complete information. ( Do not round intermediate calculations and round your final answers to the nearest whole dollar amount.
2018 2019 2020
Cost incurred during the year $2,016,000 3,890,000 3,290,000
Estimated cost to complete as of year end $5,184,000 3,190,000
In: Accounting
In: Accounting
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to percentage of completion. Required:
In: Accounting
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,550,000 | $ | 4,250,000 | $ | 1,870,000 | |||
| Estimated costs to complete as of year-end | 5,950,000 | 1,700,000 | 0 | ||||||
| Billings during the year | 2,050,000 | 4,750,000 | 3,200,000 | ||||||
| Cash collections during the year | 1,825,000 | 4,100,000 | 4,075,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________
2-a. In the journal below, complete the
necessary journal entries for the year 2021 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,550,000 | $ | 3,825,000 | $ | 3,225,000 | |||
| Estimated costs to complete as of year-end | 5,950,000 | 3,125,000 | 0 | ||||||
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,550,000 | $ | 3,825,000 | $ | 3,975,000 | |||
| Estimated costs to complete as of year-end | 5,950,000 | 4,150,000 | 0 | ||||||
2021 2022 2023
Revenue ______ _______ ________
Gross P _______ _______ ________