Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
| Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
| Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)
In: Accounting
[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,072,000 | $ | 2,738,000 | $ | 2,849,000 | |||
| Estimated costs to complete as of year-end | 5,328,000 | 2,590,000 | 0 | ||||||
| Billings during the year | 2,160,000 | 2,650,000 | 5,190,000 | ||||||
| Cash collections during the year | 1,880,000 | 2,700,000 | 5,420,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Calculate the amount of revenue and gross profit (loss) to be
recognized in each of the three years. (Do not round
intermediate calculations. Loss amounts should be indicated with a
minus sign.)
|
In: Accounting
Required information
[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,291,000 | $ | 3,555,000 | $ | 2,259,400 | |||
| Estimated costs to complete as of year-end | 5,609,000 | 2,054,000 | 0 | ||||||
| Billings during the year | 2,110,000 | 3,736,000 | 4,154,000 | ||||||
| Cash collections during the year | 1,855,000 | 3,500,000 | 4,645,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
In: Accounting
The following information applies to the questions displayed
below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,604,000 | $ | 4,032,000 | $ | 1,940,400 | |||
| Estimated costs to complete as of year-end | 5,796,000 | 1,764,000 | 0 | ||||||
| Billings during the year | 2,040,000 | 4,596,000 | 3,364,000 | ||||||
| Cash collections during the year | 1,820,000 | 4,000,000 | 4,180,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)
2021. 2022. 2023
Revenue
Gross profit(loss)
In: Accounting
Required information
[The following
information applies to the questions displayed
below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
| Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
| Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. (Do not round intermediate calculations.)
In: Accounting
Required information
[The following
information applies to the questions displayed
below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
| Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
| Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
In: Accounting
Chapter 6, #5
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,542,000 | $ | 3,772,000 | $ | 2,074,600 | |||
| Estimated costs to complete as of year-end | 5,658,000 | 1,886,000 | 0 | ||||||
| Billings during the year | 2,020,000 | 4,294,000 | 3,686,000 | ||||||
| Cash collections during the year | 1,810,000 | 3,800,000 | 4,390,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
(Do not round intermediate calculations. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |
| Revenue | |||
| Gross profit(loss) |
In: Accounting
In: Accounting
Required information
[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,204,000 | $ | 3,192,000 | $ | 2,424,400 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 2,204,000 | 0 | ||||||
| Billings during the year | 2,140,000 | 3,256,000 | 4,604,000 | ||||||
| Cash collections during the year | 1,870,000 | 3,200,000 | 4,930,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)
In: Accounting
The accounting department at Weston Materials Inc., a national manufacturer of unattached garages, reports that it takes two construction workers a mean of 33 hours and a standard deviation of 5 hours to erect the Red Barn model. Assume the assembly times follow the normal distribution. Refer to the table in Appendix B.1.
a-1. Determine the z-values for 30 and 37 hours. (Negative answers should be indicated by a minus sign. Round the final answers to 1 decimal place.)
30 hours corresponds to z =
37 hours corresponds to z =
a-2. What percentage of the garages take between 33 hours and 37 hours to erect? (Round the final answer to 2 decimal places.)
Percentage %
b. What percentage of the garages take between 30 hours and 37 hours to erect? (Round the final answer to 2 decimal places.)
Percentage %
c. What percentage of the garages take 29.4 hours or less to erect? (Round the final answer to 2 decimal places.)
Percentage %
d. Of the garages, 2% take how many hours or more to erect? (Round the final answer to 1 decimal place.)
Hours
In: Statistics and Probability