Baird Bros. Construction is considering the purchase of a machine at a cost of $203,000. The machine is expected to generate cash flows of $38,000 per year for 10 years and can be sold at the end of 10 years for $28,000. Interest is at 12%. Assume the machine purchase would be paid for on the first day of year one, but that all other cash flows occur at the end of the year. Ignore income tax considerations. (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.)
Required: a. What is the net present value of the cash flows?
b. Determine if Baird should purchase the machine. Yes No
In: Accounting
In 1990, Flounder Company completed the construction of a
building at a cost of $2,300,000 and first occupied it in January
1991. It was estimated that the building will have a useful life of
40 years and a salvage value of $69,000 at the end of that
time.
Early in 2001, an addition to the building was constructed at a
cost of $575,000. At that time, it was estimated that the remaining
life of the building would be, as originally estimated, an
additional 30 years, and that the addition would have a life of 30
years and a salvage value of $23,000.
In 2019, it is determined that the probable life of the building
and addition will extend to the end of 2050, or 20 years beyond the
original estimate.
a) Using the straight-line method, compute the annual depreciation that would have been charged from 1991 through 2000.
| Annual depreciation from 1991 through 2000 |
b) Compute the annual depreciation that would have been charged from 2001 through 2018.
| Annual depreciation from 2001 through 2018 |
c) Prepare the entry, if necessary, to adjust the account balances because of the revision of the estimated life in 2019.
d) Compute the annual depreciation to be charged, beginning with 2019. (Round answer to 0 decimal places, e.g. 45,892.)
| Annual depreciation expense—building |
In: Accounting
In 1993, Novak Company completed the construction of a building
at a cost of $2,500,000 and first occupied it in January 1994. It
was estimated that the building will have a useful life of 40 years
and a salvage value of $76,000 at the end of that time.
Early in 2004, an addition to the building was constructed at a
cost of $625,000. At that time, it was estimated that the remaining
life of the building would be, as originally estimated, an
additional 30 years, and that the addition would have a life of 30
years and a salvage value of $25,000.
In 2022, it is determined that the probable life of the building
and addition will extend to the end of 2053, or 20 years beyond the
original estimate.
(a)
Correct answer iconYour answer is correct.
Using the straight-line method, compute the annual depreciation that would have been charged from 1994 through 2003.
| Annual depreciation from 1994 through 2003 |
$ |
/ yr. |
eTextbook and Media
List of Accounts
Attempts: 1 of 3 used
(b)
Compute the annual depreciation that would have been charged from 2004 through 2022.
| Annual depreciation from 2004 through 2021 |
$ |
/ yr. |
(c)
Correct answer iconYour answer is correct.
Prepare the entry, if necessary, to adjust the account balances because of the revision of the estimated life in 2021. (If no entry is required, select "No entry" for the account titles and enter 0 for the amounts. Credit account titles are automatically indented when amount is entered. Do not indent manually.)
|
Account Titles and Explanation |
Debit |
Credit |
eTextbook and Media
List of Accounts
Attempts: 1 of 3 used
(d)
Compute the annual depreciation to be charged, beginning with
2022. (Round answer to 0 decimal places, e.g.
45,892.)
| Annual depreciation expense—building |
?
In: Accounting
In 1993, Skysong Company completed the construction of a building at a cost of $2,120,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $64,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $530,000. At that time, it was estimated that the remaining life of the building would be, as originally estimated, an additional 30 years, and that the addition would have a life of 30 years and a salvage value of $21,200. In 2022, it is determined that the probable life of the building and addition will extend to the end of 2053, or 20 years beyond the original estimate.
Compute the annual depreciation to be charged, beginning with 2022. (Round answer to 0 decimal places, e.g. 45,892.)
| Annual depreciation expense—building |
In: Accounting
|
|
In: Accounting
In February 2020, Cullumber Construction signed a contract and
commenced construction on a parking garage. The total contract
price was $89.4 million and was expected to be completed in July
2024 at a total estimated cost of $82.1 million. Payment by the
customer was to be made in several stages, based on significant
events and dates throughout the construction timeline. The customer
was to have control over the parking garage and was able to make
major changes to the project during the construction process.
Cullumber’s year-end was September 30.
By the end of September, 2020, Cullumber had incurred $20,525,000
in costs and had invoiced $10,000,000 in progress billings.
$7,700,000 of the progress billings had been collected.
By September 30, 2021, Cullumber had incurred $35,190,000 in total costs and had invoiced $45,900,000 in progress billings, including the progress billings in 2020. Of the total billings, $30,700,000 in total had been collected. Also, Cullumber reviewed its cost estimates on the project, and now believed the parking garage would cost $78.2 million in total to complete.
Prepare all journal entries required for the year ended
September 30, 2020. Use Materials, Cash, Payables for costs
incurred to date. (Credit account titles are
automatically indented when the amount is entered. Do not indent
manually. If no entry is required, select "No Entry" for the
account titles and enter 0 for the
amounts.)
|
No. |
Account Titles and Explanation |
Debit |
Credit |
|
1. |
|||
|
(To record the 2020 cost of construction) |
|||
|
2. |
|||
|
(To record the 2020 progress billings) |
|||
|
3. |
|||
|
(To record the 2020 cash collections) |
|||
|
4. |
|||
|
(To record the 2020 revenue) |
|||
|
5. |
|||
|
(To record the construction expenses) |
Prepare all journal entries required for the year ended
September 30, 2021. Use Materials, Cash, Payables for costs
incurred to date. (Credit account titles are
automatically indented when the amount is entered. Do not indent
manually. If no entry is required, select "No Entry" for the
account titles and enter 0 for the
amounts.)
|
No |
Account Titles and Explanation |
Debit |
Credit |
|
1. |
|||
|
(To record the 2021 cost of construction) |
|||
|
2. |
|||
|
(To record the 2021 progress billings) |
|||
|
3. |
|||
|
(To record the 2021 cash collections) |
|||
|
4. |
|||
|
(To record the 2021 revenue) |
|||
|
5. |
|||
|
(To record the 2021 expenses) |
In: Accounting
ABC Construction Co. signed a $2,000,000 contract to construct an office building for the State of Arizona. The project will begin in 2017 and be completed in 2018. The cost of construction is expected to be $1,875,000.
Below is a summary of events for 2017 and 2018:
|
2017 |
2018 |
||
|
Costs incurred during the year |
$ 712,500 |
$1,138,250 |
|
|
Estimated costs to complete |
1,037,500 |
0 |
|
|
Billings during the year |
850,000 |
1,150,000 |
|
|
Cash collections during the year |
750,000 |
1,000,000 |
ABC Construction Co. recognizes revenue upon completion when accounting for long-term contracts.
a. Prepare all journal entries to record costs, billings, collections, and any profit recognition for ABC Construction Co. activities for 2017 only.
b. Prepare any journal entry needed for profit recognition only for ABC Construction Co. activities for 2018.
In: Accounting
On January 1, 2017, Spartan Company signed a $240 million contract with the City of Amherst to construct a new city hall. Spartan expects to construct the building within two years and incur total expenses of $180 million. Spartan incurred $72 million in construction costs during 2017 and the remaining $108 million in 2018. Using the percentage-of-completion method, how much revenue should Spartan recognize in 2017?
In: Accounting
A quality control activity analysis indicated the following four
activity costs of a hotel:
| Inspecting cleanliness of rooms | $108,000 |
| Processing lost customer reservations | 450,000 |
| Rework incorrectly prepared room service meal | 54,000 |
| Employee training | 288,000 |
| Total | $900,000 |
Sales are $3,000,000. Prepare a cost of quality report. Round percent of sales to one decimal place.
| Cost of Quality Report | |||
| Quality Cost Classification | Quality Cost | Percent of Total Quality Cost | Percent of Total Sales |
| Prevention | $ | % | % |
| Appraisal | % | % | |
| Internal failure | % | % | |
| External failure | % | % | |
| Total | $ | % | % |
In: Operations Management
Describe ( in details) 5 cost control techniques used by contractors in construction projects.
In: Civil Engineering