in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to percentage of completion.
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. ( Do not round intermediate calculation. Loss amounts should be indicated with a minus sign.)
In: Accounting
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
202120222023
Cost incurred during the year$2,204,000 $3,192,000 $2,424,400
Estimated costs to complete as of year-end 5,396,000 2,204,000 0
Billings during the year 2,140,000 3,256,000 4,604,000
Cash collections during the year 1,870,000 3,200,000 4,930,000
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be
recognized in each of the three years. (Do not round intermediate
calculations. Loss amounts should be indicated with a minus
sign.)
2-a. In the journal below, complete the
necessary journal entries for the year 2021 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3.Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,204,000 | $ | 3,870,000 | $ | 3,270,000 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 3,170,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,204,000 | $ | 3,870,000 | $ | 4,110,000 | |||
| Estimated costs to complete as of year-end | 5,396,000 | 4,240,000 | 0 | ||||||
In: Accounting
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,490,000 | $ | 3,984,000 | $ | 2,008,600 | |||
| Estimated costs to complete as of year-end | 5,810,000 | 1,826,000 | 0 | ||||||
| Billings during the year | 2,030,000 | 4,444,000 | 3,526,000 | ||||||
| Cash collections during the year | 1,815,000 | 3,900,000 | 4,285,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,490,000 | $ | 3,815,000 | $ | 3,945,000 | |||
| Estimated costs to complete as of year-end | 5,810,000 | 4,130,000 | 0 | ||||||
In: Accounting
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,490,000 | $ | 3,984,000 | $ | 2,008,600 | |||
| Estimated costs to complete as of year-end | 5,810,000 | 1,826,000 | 0 | ||||||
| Billings during the year | 2,030,000 | 4,444,000 | 3,526,000 | ||||||
| Cash collections during the year | 1,815,000 | 3,900,000 | 4,285,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,490,000 | $ | 3,815,000 | $ | 3,215,000 | |||
| Estimated costs to complete as of year-end | 5,810,000 | 3,115,000 | 0 | ||||||
In: Accounting
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,490,000 | $ | 3,984,000 | $ | 2,008,600 | |||
| Estimated costs to complete as of year-end | 5,810,000 | 1,826,000 | 0 | ||||||
| Billings during the year | 2,030,000 | 4,444,000 | 3,526,000 | ||||||
| Cash collections during the year | 1,815,000 | 3,900,000 | 4,285,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
3. Complete the information required below to
prepare a partial balance sheet for 2021 and 2022 showing any items
related to the contract. (Do not round intermediate
calculations.)
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
| Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
| Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 3,830,000 | $ | 3,230,000 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 3,130,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
| Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
| Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 3,830,000 | $ | 3,230,000 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 3,130,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion. rev: 09_15_2017_QC_CS-99734
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 3,830,000 $ 3,990,000 Estimated costs to complete as of year-end 6,020,000 4,160,000 0
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
| Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
| Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,400,000 | $ | 3,600,000 | $ | 2,200,000 | |||
| Estimated costs to complete as of year-end | 5,600,000 | 2,000,000 | 0 | ||||||
| Billings during the year | 2,000,000 | 4,000,000 | 4,000,000 | ||||||
| Cash collections during the year | 1,800,000 | 3,600,000 | 4,600,000 | ||||||
Westgate Construction uses the completed contract method of
accounting for long-term construction contracts.
Required:
1. Calculate the amount of revenue and gross profit (loss)
to be recognized in each of the three years.
2-a.In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b.In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,400,000 | $ | 3,800,000 | $ | 3,200,000 | |||
| Estimated costs to complete as of year-end | 5,600,000 | 3,100,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete
information.
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,400,000 | $ | 3,800,000 | $ | 3,900,000 | |||
| Estimated costs to complete as of year-end | 5,600,000 | 4,100,000 | 0 | ||||||
In: Accounting