| During 2015 Cambridge Co. started a construction job with a contract price of $2,000,000. | |||||
| The job was completed in 2017. The following information is available: | |||||
| 2015 | 2016 | 2017 | |||
| Costs incurred to date | 500,000 | 900,000 | 1,100,000 | ||
| Estimated costs to complete | 600,000 | 200,000 | 0 | ||
| Billings to date | 500,000 | 1,400,000 | 2,000,000 | ||
| Collections to date | 450,000 | 1,300,000 | 1,800,000 | ||
| Instructions: | |||||
| (a) Compute the amount of gross profit to be recognized each year assuming the percentage of | |||||
| completion method is used. | |||||
| (b) ****EXTRA CREDIT - Prepare all necessary journal entries for 2016. | |||||
| 2015 | 2016 | 2017 | |||
| 2,000,000 | 2,000,000 | 2,000,000 | |||
In: Accounting
Recent development near Eugene, Oregon, has identified a need for improved access to Interstate 5 at one location. Civil engineers and public planners are considering three alternative access plans. Benefits are estimated for the public in general; disbenefits primarily affect some local proprietors who will see traffic pattern changes as undesirable. Costs are monetary for construction and upkeep, and savings are a reduction in cost of those operations today that will not be necessary in the future. All figures are relative to the present situation, retention of which is still an alternative, and are annualized over the 20-year planning horizon.
|
Alternative |
A |
B |
C |
| Benefits | $240,000 | $370,000 | $470,000 |
| Disbenefits | $37,000 | $69,000 | $102,000 |
| Costs | $155,000 | $244,000 | $327,000 |
| Savings | $15,000 | $31,000 | $42,000 |
A)What is the B/C ratio for each of these alternatives?
Alternative A:
Alternative B:
Alternative C:
B) Using incremental B/C ratio analysis, which alternative should be selected?
a and b, or b and c, or a and c, or all , or a, or b, or c?
Please show the ratios used to make your decision:
Comparison 1: C-DN, or A-DN, or B-DN
Ratio:
Comparison 2: C-B, or, A-C or, DN-C or, B-A or, DN-B, or
DN-A Ratio:
Comparison 3: C-B or DN-C or A-DN or A-B or C-DN Ratio:
C)Determine the value of B – C for each alternative.
Alternative A: $
Alternative B: $
Alternative C: $
In: Finance
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows:
| May 1 | $3,300,000 |
| July 30 | 2,200,000 |
| September 1 | 1,740,000 |
| October 1 | 2,640,000 |
MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021.
Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar]
| Date | Expenditure | Months financed (out of 7) | WA Accum Exp |
| March 28** | $ 998,600 | 7 | 998,600 |
| April 30** | 148,000 | 6 | 126,857 |
| May 1 | 3,300,000 | ||
| July 30 | 2,200,000 | ||
| September 1 | 1,740,000 | ||
| October 1 | 2,640,000 | ||
| Total |
**According to ASC 835-20-15-8, “If activities are undertaken for
the purpose of developing land for a particular use, the
expenditures to acquire the land qualify for interest
capitalization while those activities are in progress. The interest
cost capitalized on those expenditures is a cost of acquiring the
asset that results from those activities. If the resulting asset is
a structure, such as a plant or a shopping center, interest
capitalized on the land expenditures is part of the acquisition
cost of the structure.”
In: Accounting
In a survey of 3,827 travelers, 1,459 said that location was very important for choosing a hotel and 1,175 said that reputation was very important in choosing an airline. Complete parts (a) through (c) below.
a. Construct a 95% confidence interval estimate for the population proportion of travelers who said that location was very important for choosing a hotel.
b. Construct a 95% confidence interval estimate for the population proportion of travelers who said that reputation was very important in choosing an airline.
c. Write a short summary of the information derived from (a) and (b) Which of the following is the best summary of the information derived from (a)?
A.One can be 95% confident that the sample proportion of all travelers who said that location was very important for choosing a hotel lies within the interval in (a).
B.One can be 95% confident that the population proportion of all travelers who said that location was very important for choosing a hotel lies within the interval in (a).
C.There is a 95% probability that the sample proportion of all travelers who said that location was very important for choosing a hotel lies within the interval in (a).
D.There is a 95% probability that the population proportion of all travelers who said that location was very important for choosing a hotel lies within the interval in (a).
Which of the following is the best summary of the information derived from (b)?
A.One can be 95% confident that the population proportion of all travelers who said that reputation was very important in choosing an airline lies within the interval in (b).
B.One can be 95% confident that the sample proportion of all travelers who said that reputation was very important in choosing an airline lies within the interval in (b).
C.There is a 95% probability that the sample proportion of all travelers who said that reputation was very important in choosing an airline lies within the interval in (b).
D.There is a 95% probability that the population proportion of all travelers who said that reputation was very important in choosing an airline lies within the interval in (b).
In: Statistics and Probability
In a surface condenser a section of the tubes near to
the air pump suction is
screened off so that the air is cooled to a temperature below that
of the condensate, separate extraction
pumps being provided to deal with air and condensate respectively.
5448 kg of steam are condensed
per hour and the air leakage is 4.54 kg/h. The temperature of the
exhaust steam is 31°C, the temperature
of the condensate is 27°C, and the temperature at the air pump
suction is 21.1°C. Assuming a constant
vacuum throughout the condenser, find
() The mass of steam condensed per hour in the air cooler;
(i) The volume of air in m3/h to be dealt with by the air
pump;
(ii) The percentage reduction in necessary air pump capacity
following the cooling of the air..
In: Mechanical Engineering
1. Sources of monopoly power
A monopolist, unlike a competitive firm, has some market power. It can raise its price, within limits, without the quantity demanded falling to zero. The main way it retains its market power is through barriers to entry—that is, other companies cannot enter the market to create competition in that particular industry.
Complete the following table by indicating which barrier to entry appropriately explains why a monopoly exists in each scenario.
|
Scenario |
Barriers to Entry |
|||
|---|---|---|---|---|
|
Exclusive Ownership of a Key Resource |
Government-Created Monopolies |
Economies of Scale |
||
| The Aluminum Company of America (Alcoa) formerly controlled all U.S. sources of bauxite, a key component in the production of aluminum. Given that Alcoa did not sell bauxite to any other companies, Alcoa was a monopolist in the U.S. aluminum industry from the late 19th century until the 1940s. | ||||
| In order to own and operate a taxi, drivers are required to obtain a taxi medallion. | ||||
| In the natural gas industry, low average total costs are obtained only through large-scale production. In other words, the initial cost of setting up all the necessary pipes and hoses makes it risky and, most likely, unprofitable for competitors to enter the market. | ||||
Grade It Now
In: Economics
Mini case study – Scottish Parliament: the £431m question
Scotland’s new parliament building cost more than 10 times the original estimate and opened three years behind schedule.
Official cost estimates changed 10 times and ballooned from the initial £40 million estimate to a final £431 million.
The procurement model chosen for Holyrood in early 1998 has emerged as the root of the problem. A fast-track contracting method known as construction management was used to build the parliament. It works by splitting a large building job into numerous smaller packages that are designed, tendered and let independently of one another.
Its main advantage is to speed up construction, because the overall design does not have to be complete before basic building work can begin.
It does not allow a client to know the total cost of a project until well after work has begun. It is considered risky for the client, which is responsible for running each individual package – in this case more than 60.
The project cost escalated from about £40 million in 1997 to £109 million in 1999, £241 million in 2001 and £294 million in 2002, and finally £431 million in February 2004. There were 18,000 design change orders over the five years of construction, combining
to form a three-year delay. Requests for design freezes on three occasions were ignored. The reality is that construction management was the only contract option for a client
wanting to make an early start on a project that was still at
the design concept stage.
It is also clear that this was a classic case of procurement
expertise being bypassed. The procurement department at the
Scottish Office was not involved in the project. It was
not consulted over the procurement model.
There is nothing wrong with construction management as a
procurement route. It is
best suited to high-quality, potentially high-cost projects, where the client is fully engaged, has a clear goal and works closely with the supply side team.
Some estimates put the money lost to delays and backtracking over design changes at as much as £100 million. If one trade contractor has a problem, it tends to ripple through all the others and cause delay and changes. The contracts are with the client, so the client picks up the cost of that.
However, between the extremes of fixed speedy construction management, a host of options exist under the heading of ‘conventional’ procurement. Their structures affect the risk and control over the final design that falls to the client.
The ‘design and build’ route would have seen the project management team drawing up a detailed design brief, which the main contractor then builds. It leaves the contractor footing the bill for cost overruns, but freezes the design as well.
A middle-of-the-road option, prime contracting, keeps design more open, but cuts the risk of costs going up if things go wrong. This is because a contractor joins the client’s project management team, and brings its entire supply chain of proven builders and suppliers along.
Then there is management contracting, where the client retains the design brief fully and splits up the project into small packages to be individually let, as in construction management. However, a professional intermediary runs all of the contractors on a daily basis, although they are still contracted to the client, which pays for design alterations.
Management contracting may, it seems, have given a more stable framework to the project by introducing an industry expert to run the many contractors.
Construction management was not the most suitable procurement vehicle. Sir Michael Latham, whose influential 1994 report, ‘Constructing the Team’, called on the construction industry to move towards partnering in the supply chain, says that full partnering should have been used to share the risk between client and contractor.
Discussion Question:
1. What was the nature of the procurement including the organization that conducted it and Who was involved in the procurement?
2. What was the process followed (briefly)?
3. Critique the procedure indicating what went wrong and how costly it was.
4. Suggest necessary improvements.
In: Operations Management
You are tasked with estimating the cost of capital for a firm. The risk-free rate is 3.2%, the expected rate of return on the market is 17.9%. Now, another similar company (similar unlevered cost of capital) has a debt-to-equity ratio of 1 to 5. It has a debt beta near zero and an equity market-beta of 1.1. Your own firm has more debt, for a debt-to-equity ratio of 1 to 1, with a debt beta of 0.5. What is a good estimate for your equity cost of capital?
In: Finance
Citation Builders, Inc., builds office buildings and single-family
homes. The office buildings are constructed under contract with
reputable buyers. The homes are constructed in developments ranging
from 10–20 homes and are typically sold during construction or soon
after. To secure the home upon completion, buyers must pay a
deposit of 10% of the price of the home with the remaining balance
due upon completion of the house and transfer of title. Failure to
pay the full amount results in forfeiture of the down payment.
Occasionally, homes remain unsold for as long as three months after
construction. In these situations, sales price reductions are used
to promote the sale.
During 2018, Citation began construction of an office building for
Altamont Corporation. The total contract price is $29 million.
Costs incurred, estimated costs to complete at year-end, billings,
and cash collections for the life of the contract are as
follows:
| 2018 | 2019 | 2020 | |||||||||
| Costs incurred during the year | $ | 5,800,000 | $ | 13,775,000 | $ | 6,525,000 | |||||
| Estimated costs to complete as of year-end | 17,400,000 | 6,525,000 | — | ||||||||
| Billings during the year | 2,900,000 | 14,500,000 | 11,600,000 | ||||||||
| Cash collections during the year | 2,610,000 | 13,190,000 | 13,200,000 | ||||||||
|
|
|||||||||||
Also during 2018, Citation began a development consisting of 12
identical homes. Citation estimated that each home will sell for
$980,000, but individual sales prices are negotiated with buyers.
Deposits were received for eight of the homes, three of which were
completed during 2018 and paid for in full for $980,000 each by the
buyers. The completed homes cost $735,000 each to construct. The
construction costs incurred during 2018 for the nine uncompleted
homes totaled $4,410,000.
Required:
1. Which method is most equivalent to recognizing revenue
at the point of delivery?
2. Answer the following questions assuming that Citation
uses the completed contract method for its office building
contracts:
2-a. How much revenue related to this contract will
Citation report in its 2018 and 2019 income statements?
2-b. What is the amount of gross profit or loss to be
recognized for the Altamont contract during 2018 and 2019?
2-c. What will Citation report in its December 31, 2018,
balance sheet related to this contract? (Ignore cash.)
3. Answer the following questions assuming that Citation
uses the percentage-of-completion method for its office building
contracts.
3-a. How much revenue related to this contract will
Citation report in its 2018 and 2019 income statements?
3-b. What is the amount of gross profit or loss to be
recognized for the Altamont contract during 2018 and 2019?
3-c. What will Citation report in its December 31, 2018,
balance sheet related to this contract? (Ignore cash.)
4. Assume the same information for 2018 and 2019, but that
as of year-end 2019 the estimated cost to complete the office
building is $13,050,000. Citation uses the percentage-of-completion
method for its office building contracts.
4-a. How much revenue related to this contract will
Citation report in the 2019 income statement?
4-b. What is the amount of gross profit or loss to be
recognized for the Altamont contract during 2019?
4-c. What will Citation report in its 2019 balance sheet
related to this contract? (Ignore cash.)
5. Which method of accounting should Citation Builders,
Inc adopt for its single-family houses?
6. What will Citation report in its 2018 income statement
and 2018 balance sheet related to the single-family home business
(ignore cash in the balance sheet)?
In: Accounting
Citation Builders,
Inc., builds office buildings and single-family homes. The office
buildings are constructed under contract with reputable buyers. The
homes are constructed in developments ranging from 10–20 homes and
are typically sold during construction or soon after. To secure the
home upon completion, buyers must pay a deposit of 10% of the price
of the home with the remaining balance due upon completion of the
house and transfer of title. Failure to pay the full amount results
in forfeiture of the down payment. Occasionally, homes remain
unsold for as long as three months after construction. In these
situations, sales price reductions are used to promote the
sale.
During 2018, Citation began construction of an office building for
Altamont Corporation. The total contract price is $25 million.
Costs incurred, estimated costs to complete at year-end, billings,
and cash collections for the life of the contract are as
follows:
| 2018 | 2019 | 2020 | |||||||||
| Costs incurred during the year | $ | 5,000,000 | $ | 11,875,000 | $ | 5,625,000 | |||||
| Estimated costs to complete as of year-end | 15,000,000 | 5,625,000 | — | ||||||||
| Billings during the year | 2,500,000 | 12,500,000 | 10,000,000 | ||||||||
| Cash collections during the year | 2,250,000 | 11,150,000 | 11,600,000 | ||||||||
Also during 2018, Citation began a development consisting of 12
identical homes. Citation estimated that each home will sell for
$900,000, but individual sales prices are negotiated with buyers.
Deposits were received for eight of the homes, three of which were
completed during 2018 and paid for in full for $900,000 each by the
buyers. The completed homes cost $675,000 each to construct. The
construction costs incurred during 2018 for the nine uncompleted
homes totaled $4,050,000.
Required:
1.
Which method is most equivalent to recognizing revenue at the point
of delivery?
2. Answer the following questions assuming that
Citation uses the completed contract method for its office building
contracts:
2-a. How much revenue related to this contract
will Citation report in its 2018 and 2019 income statements?
2-b. What is the amount of gross profit or loss to
be recognized for the Altamont contract during 2018 and 2019?
2-c. What will Citation report in its December 31,
2018, balance sheet related to this contract? (Ignore cash.)
3. Answer the following questions assuming that
Citation uses the percentage-of-completion method for its office
building contracts.
3-a. How much revenue related to this contract
will Citation report in its 2018 and 2019 income statements?
3-b. What is the amount of gross profit or loss to
be recognized for the Altamont contract during 2018 and 2019?
3-c. What will Citation report in its December 31,
2018, balance sheet related to this contract? (Ignore cash.)
4. Assume the same information for 2018 and 2019,
but that as of year-end 2019 the estimated cost to complete the
office building is $11,250,000. Citation uses the
percentage-of-completion method for its office building
contracts.
4-a. How much revenue related to this contract
will Citation report in the 2019 income statement?
4-b. What is the amount of gross profit or loss to
be recognized for the Altamont contract during 2019?
4-c. What will Citation report in its 2019 balance
sheet related to this contract? (Ignore cash.)
5. Which method of accounting should Citation
Builders, Inc adopt for its single-family houses?
6. What will Citation report in its 2018 income
statement and 2018 balance sheet related to the single-family home
business (ignore cash in the balance sheet)?
I am interested in 4 c
In: Accounting