Questions
The Starr Theater, owned by Meg Vargo, will begin operations in March. The Starr will be...

The Starr Theater, owned by Meg Vargo, will begin operations in March. The Starr will be unique in that it will show only triple features of sequential theme movies. As of March 1, the ledger of Starr showed: Cash $3,050, Land $23,000, Buildings (concession stand, projection room, ticket booth, and screen) $12,000, Equipment $12,000, Accounts Payable $6,300, and Owner’s Capital $43,750. During the month of March, the following events and transactions occurred.
Mar. 2 Rented the three Indiana Jones movies to be shown for the first 3 weeks of March. The film rental was $3,200; $1,500 was paid in cash and $1,700 will be paid on March 10.
3 Ordered the Lord of the Rings movies to be shown the last 10 days of March. It will cost $200 per night.
9 Received $4,100 cash from admissions.
10 Paid balance due on Indiana Jones movies rental and $2,100 on March 1 accounts payable.
11 Starr Theater contracted with Adam Ladd to operate the concession stand. Ladd is to pay 15% of gross concession receipts, payable monthly, for the rental of the concession stand.
12 Paid advertising expenses $900.
20 Received $5,500 cash from customers for admissions.
20 Received the Lord of the Rings movies and paid the rental fee of $2,000.
31 Paid salaries of $3,100.
31 Received statement from Adam Ladd showing gross receipts from concessions of $5,000 and the balance due to Starr Theater of $750 ($5,000 × 15%) for March. Ladd paid one-half the balance due and will remit the remainder on April 5.
31 Received $9,000 cash from customers for admissions.
1.) Enter the beginning balances in the ledger.

2.) Journalize the March transactions. Starr records admission revenue as service revenue, rental of the concession stand as rent revenue, and film rental expense as rent expense. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. Record journal entries in the order presented in the problem. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

3.)
Post the March journal entries to the ledger. (Post entries in the order of journal entries presented in the previous question.)

In: Accounting

Construction of a new building began on April 1 and was completed on October 29. Construction...

Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows:

May 1 $3,300,000
July 30 2,200,000
September 1 1,740,000
October 1 2,640,000

MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021.

Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar]

Date Expenditure Months financed (out of 7) WA Accum Exp
March 28** $ 998,600 7 998,600
April 30** 148,000 6 126,857
May 1 3,300,000
July 30 2,200,000
September 1 1,740,000
October 1 2,640,000
Total

Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows:

May 1 $3,300,000
July 30 2,200,000
September 1 1,740,000
October 1 2,640,000

MMI borrowed $5,000,000 at 6% on May 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021.

Avoidable interest on the building was:

WA Accum Expend 5,771,171 Avoidable Interest Actual Interest
construction loan 6%
note payable 8%
Total

[Hint: Lesser of Avoidable or Actual Interest is capitalized.]

The building would be recorded on the balance sheet as:

Total expenditures 9,880,000
Capitalized interest
Total historical cost

In: Accounting

4-2 Short Paper: Major Contributions of Minority Groups Assignment Task: Submit to complete this assignment Trace...

4-2 Short Paper: Major Contributions of Minority Groups Assignment Task: Submit to complete this assignment Trace some of the major contributions of an ethnic or "minority" group to U.S. culture, for example, to music, the arts, dance, or theater. There are many other possibilities! Develop your composition based on an area of interest to you in the arts.

In: Nursing

A Theater has n numbered seats, and n tickets are distributed among n persons. Compute the...

A Theater has n numbered seats, and n tickets are distributed among n persons. Compute the probability that

(a) exactly two persons will be seated at seats corresponding to their ticket numbers if all the seats are occupied at random.

(b) at least two persons will be seated at seats corresponding to their ticket numbers if all the seats are occupied at random.

In: Math

Indicate whether each of the following expenditures should be classified as Building, Land improvements or None...

Indicate whether each of the following expenditures should be classified as Building, Land improvements or None of these *

Construction Material

Closing Cost

Fences

Purchase Price

Annual Property Taxes

Driveway

In: Accounting

A flood control project has construction cost during the first year (i.e. at EOY 1) of...

A flood control project has construction cost during the first year (i.e. at EOY 1) of $10 million, during the second year of $7 million, and during the third year of $4 million, It is completed at the end of the third year and thereafter incurs an annual operating cost of $170,000 per year. Benefits from the project begin during the fourth year and are valued at $1,300,000 in that year, growing at a 2% rate of increase out to the end of the project life, which is 50 years (i.e., three years of construction, 47 years of operation). Assuming an interest rate of 7%, determine if this is a viable project, that is do the capitalized benefits exceed the capitalized costs?

In: Accounting

(Please be accurate) 1. A concrete to concrete joint made in such a manner that the...

(Please be accurate)

1. A concrete to concrete joint made in such a manner that the faces of the new and old concrete adhere sufficiently to prevent any relative movement across the joint; it creates some weakness in the concrete structure so care must be taken to where they are to be placed. These joints are called:

Select one:

a. Metal joint

b. Construction joint

c. Stop joint

2.

Piles may be made from all the following except one:

Select one:

a. Steel

b. Precast concrete

c. Brick

d. Timbe

3.

Reinforcing Steel is placed in the bottom of the footing to:

Select one:

a. Carry compression

b. Reduce shrinkage

c. Carry tension

d. Increase permeability

4.

The process of regularly spraying water or covering the concrete with moisture-retaining materials, or using chemical surface sealer in order to protect the exposed surfaces of newly poured concrete from evaporation and drying is known as:

Select one:

a. Consolidation

b. Hydration

c. Curing

d. Segregation

5.

A mat foundation placed at a depth such that the weight of the soil removed from the excavation is equal to the weight of the building above, so the stress in the soil beneath the building is the same after construction as it was before is known as:

Select one:

a. Pad (Spread) Footings

b. Strip Footings

c. Floating foundation

6.

When steel strands are tensioned before concrete is casted and requires heavy abutments to restrain the strands and is normally only done with concrete in precast plants, but not on the construction site is known as:

Select one:

a. Pre-tensioning

b. Post-tensioning

7.

When the column is located at or near a property line the following shallow foundation is used.

Select one:

a. Caissons

b. Combined footing or cantilever footing

c. Piles

d. Pad footings

In: Civil Engineering

On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct...

On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct a municipal office complex. The three-year a to receive 10 million in cash payments from the city in three installments: 25% when the project was 30% complete; 25% when the project was 60% complete; and50% when the project was fully complete. The contract required that Frog's completion estimates be certified by an independent consultant before payments were made.

During the first year of the contract, Frog completed 30% of the contract and incurred costs of 2,490,000. During the second year, the project was certified as being 60% complete and Frog incurred costs of 3,100,000.
During the third year, Frog completed the project and incurred costs of 3,110,000.

Assuming Frog had no other revenues or expenses, determine the profit on construction for 2018, 2019, and 2020 under the following methods:

  1. Percentage of Completion'

  2. Completed Contract

  3. Which method best represents the profitability of Frog from 2018 to 2020.

In: Accounting

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

Required information

[The following information applies to the questions displayed below.]

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,640,000 $ 2,300,000 $ 2,926,000
Estimated costs to complete as of year-end 6,160,000 2,660,000 0
Billings during the year 2,080,000 2,860,000 5,060,000
Cash collections during the year 1,840,000 2,800,000 5,360,000


Westgate recognizes revenue over time according to percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,640,000 $ 3,840,000 $ 3,240,000
Estimated costs to complete as of year-end 6,160,000 3,140,000 0

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,640,000 $ 3,840,000 $ 4,020,000
Estimated costs to complete as of year-end 6,160,000 4,180,000 0

In: Accounting

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

202120222023

Cost incurred during the year$2,204,000 $3,192,000 $2,424,400

Estimated costs to complete as of year-end 5,396,000  2,204,000  0

Billings during the year 2,140,000  3,256,000  4,604,000

Cash collections during the year 1,870,000  3,200,000  4,930,000


Westgate recognizes revenue over time according to percentage of completion.

Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

3.Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,204,000 $ 3,870,000 $ 3,270,000
Estimated costs to complete as of year-end 5,396,000 3,170,000 0

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2021 2022 2023
Costs incurred during the year $ 2,204,000 $ 3,870,000 $ 4,110,000
Estimated costs to complete as of year-end 5,396,000 4,240,000 0

In: Accounting