n February 2020, Oriole Construction signed a contract and
commenced construction on a parking garage. The total contract
price was $91.0 million and was expected to be completed in July
2022 at a total estimated cost of $82.4 million. Payment by the
customer was to be made in several stages, based on significant
events and dates throughout the construction timeline. Based on the
terms of the contract with the customer, control over the parking
garage (i.e. ownership) does not transfer to the customer until
completion. Oriole’s year-end was September 30 and follows
ASPE.
By the end of September, 2020, Oriole had incurred $8,240,000 in
costs and had invoiced $10,600,000 in progress billings. $8,200,000
of the progress billings had been collected.
By September 30, 2021, Oriole had incurred $43,230,000 in total
costs and had invoiced $45,400,000 in progress billings, including
the progress billings in 2020. Of the total billings, $30,600,000
in total had been collected. Also, Oriole reviewed its cost
estimates on the project, and now believed the parking garage would
cost $78.6 million in total to complete.
Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2020. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
| No | Account title | Debit | Credit |
| 1 | |||
| (to record 2020 cost of construction | |||
| 2 | |||
| to record the 2020 progress billings | |||
| 3 | |||
| to record the 2020 cash collection |
Using the completed-contract method, prepare all journal entries required for the year ended September 30, 2021. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
|
No. |
Account Titles and Explanation |
Debit |
Credit |
|
1. |
|||
|
(To record the 2021 cost of construction) |
|||
|
2. |
|||
|
(To record the 2021 progress billings) |
|||
|
3. |
|||
|
(To record the 2021 cash collections) |
Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2021 estimate. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
|
Account Titles and Explanation |
Debit |
Credit |
|
(To record the 2022 cost of construction) |
||
|
(To record the 2022 progress billings) |
||
|
(To record the 2022 cash collections) |
||
|
(To record revenue, costs and gross profit of construction of parking garage) |
In: Accounting
In: Psychology
Scenario Suppose that a movie theater faces a downward sloping demand curve for popcorn and it increases the price of a container of popcorn from $4.00 to $4.80, which causes the count of containers sold to fall from 100 to 90.
Questions 1. What is the elasticity coefficient?
2. Is the demand relatively elastic or relatively inelastic?
3. Should the theater consider raising the price of popcorn further?
4. When a firm faces a downward sloping demand curve, should it ever price its product in the inelastic range of the demand curve (if it has such a range)? Explain why or why not.
5. When a firm is a monopolist (or the only seller of a product), should it price its product in the elastic or inelastic range of its demand curve? Explain.
In: Economics
Arlington, Texas wants to build a new recreation center. The estimated cost of construction cost us $14 million with annual staffing and maintenance costs of $520,000 per year over the twenty-year life of the center. At the end of the life of the center, Arlington expects to sell the land for $5 million, though that figure might be as low as $1 million and as high $ 9 million. City staff estimate first year benefits to be $2.1 million (accruing at the end of the first year). Staff expect annual benefits to grow in real terms at 4 percent, though this could be as low as 1 percent and as high as 6 percent. They assume that the real discount rate for use in Arlington should be 7 percent, thought it might be a percentage point higher or lower
a) What is the present value of net benefits for the recreation project using staff predictions?
b) What is the sensivity of the present value of net benefits to alternative predictions about land price, growth rate of annual benefits and the real discount rate.
In: Finance
Bargain Rental Car offers rental cars in an off-airport location near a major tourist destination in California. Management would like to better understand the variable and fixed portions of it car washing costs. The company operates its own car wash facility in which each rental car that is returned is thoroughly cleaned before being released for rental to another customer. Management believes that the variable portion of its car washing costs relates to the number of rental returns. Accordingly, the following data have been compiled: Month Rental Returns Car Wash Costs January 2,500 $ 12,100 February 2,600 $ 13,700 March 2,800 $ 12,900 April 3,200 $ 15,900 May 3,700 $ 17,300 June 5,300 $ 25,500 July 5,600 $ 23,300 August 5,800 $ 24,900 September 4,800 $ 23,900 October 5,200 $ 24,400 November 2,300 $ 11,800 December 3,200 $ 18,100 2. Using least-squares regression, estimate the variable cost per rental return and the monthly fixed cost incurred to wash cars. What is the R2 rounded to the nearest whole percentage? (Round Fixed cost to the nearest whole dollar amount and the Variable cost per unit to 2 decimal places.) fixed cost per month= variable cost per rental return= r-square=
In: Accounting
Exercise 10-1
The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses.
| (a) | Money borrowed to pay building contractor (signed a note) | $(276,500 | ) | ||
| (b) | Payment for construction from note proceeds | 276,500 | |||
| (c) | Cost of land fill and clearing | 11,220 | |||
| (d) | Delinquent real estate taxes on property assumed by purchaser | 8,340 | |||
| (e) | Premium on 6-month insurance policy during construction | 12,060 | |||
| (f) | Refund of 1-month insurance premium because construction completed early | (2,010 | ) | ||
| (g) | Architect’s fee on building | 27,040 | |||
| (h) | Cost of real estate purchased as a plant site (land $206,800 and building $55,900) | 262,700 | |||
| (i) | Commission fee paid to real estate agency | 9,620 | |||
| (j) | Installation of fences around property | 4,030 | |||
| (k) | Cost of razing and removing building | 10,130 | |||
| (l) | Proceeds from salvage of demolished building | (4,910 | ) | ||
| (m) | Interest paid during construction on money borrowed for construction | 13,700 | |||
| (n) | Cost of parking lots and driveways | 17,690 | |||
| (o) | Cost of trees and shrubbery planted (permanent in nature) | 14,080 | |||
| (p) | Excavation costs for new building | 2,950 |
Identify each item by letter and list the items in columnar form,
using the headings shown below. All receipt amounts should be
reported in parentheses. For any amounts entered in the Other
Accounts column, also indicate the account title.
(Enter receipt amounts using either a negative sign
preceding the number e.g. -45 or parentheses e.g. (45). If no entry
is required in other accounts, select "No Entry" for the account
titles.)
| Item | Land | Land Improvements |
Building | Other Accounts | ||||||
In: Accounting
Exercise 10-1
The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses.
| (a) | Money borrowed to pay building contractor (signed a note) | $(276,500 | ) | ||
| (b) | Payment for construction from note proceeds | 276,500 | |||
| (c) | Cost of land fill and clearing | 11,220 | |||
| (d) | Delinquent real estate taxes on property assumed by purchaser | 8,340 | |||
| (e) | Premium on 6-month insurance policy during construction | 12,060 | |||
| (f) | Refund of 1-month insurance premium because construction completed early | (2,010 | ) | ||
| (g) | Architect’s fee on building | 27,040 | |||
| (h) | Cost of real estate purchased as a plant site (land $206,800 and building $55,900) | 262,700 | |||
| (i) | Commission fee paid to real estate agency | 9,620 | |||
| (j) | Installation of fences around property | 4,030 | |||
| (k) | Cost of razing and removing building | 10,130 | |||
| (l) | Proceeds from salvage of demolished building | (4,910 | ) | ||
| (m) | Interest paid during construction on money borrowed for construction | 13,700 | |||
| (n) | Cost of parking lots and driveways | 17,690 | |||
| (o) | Cost of trees and shrubbery planted (permanent in nature) | 14,080 | |||
| (p) | Excavation costs for new building | 2,950 |
Identify each item by letter and list the items in columnar form,
using the headings shown below. All receipt amounts should be
reported in parentheses. For any amounts entered in the Other
Accounts column, also indicate the account title.
(Enter receipt amounts using either a negative sign
preceding the number e.g. -45 or parentheses e.g. (45). If no entry
is required in other accounts, select "No Entry" for the account
titles.)
| Item | Land | Land Improvements |
Building | Other Accounts | ||||||
In: Accounting
A construction project is carried out by a general contractor with the following descriptions:
| Month | May | June | July | |
| Cost-Loaded Schedule | Materials | 20,713 | 30,081 | 50,630 |
| Labor | 40,978 | 60,886 | 70,089 | |
| Subcontractor | 30,500 | 100,165 | 152,181 | |
| Bill to Owner | 100,936 | 200,081 | 300,685 | |
What is the amount of cash to maintain a positive cash flow in this project?
In: Finance
PART A
GanJee Pty Limited (GanJee) owns and develops properties in the Gosford CBD on the Central Coast of NSW. Upon completion of construction the company leases the apartments and retail space and provides tennants services including waste removal, maintenance and shared facilities like airconditioning. All leases are signed for a period of less than 5 years and are then reviewed before renewal or extension. You wish to establish the fair value of one of GanJee’s Gosford properties using AASB 13/IFRS 13. GanJee purchased the property in 2001 when the Gosford CBD was in decline. At the time, GanJee was able to snap up the property for $0.5 million. In 2015, existing property was demolished and GanJee constructed two impressive tower block buildings with retail space below. The property also includes a hotel, office space and apartments. Construction was expensive, costing $400 million. You have ascertained the following information for your assessment: • The company commissioned the expert opinion of two reputable independent expert appraisers. These appraisers delivered valuation A and valuation B. Valuation A contained the appraiser’s opinion that the property value for GanJee’s Gosford holding had a fair value of $1.3 billion based upon earnings before interest and tax multiplied by a conservative earnings multiple of 6 which is more likely to be considered fair by a potential buyer for the properties. The second valuer in providing valuation B expressed the opinion that the properties had a fair value of $2.75 billion based upon earnings before interest and tax multiplied by an earnings multiple of 8 which is more likely to be considered fair by a potential seller of the property. Both appraisers acknowledged that valuing the property in the current economic climate was difficult as generally there are very few sales of comparable properties. The appraisers communicated that they used their experience in observing valuations of residential rather than commercial and residential properties. The directors estimate that the current cost of replacing the property would be $1.8 billion based on the current design with today’s construction costs, including labour, materials and overheads. Property prices in the Gosford CBD have increased substantially since 2001. The CBD went through a rapid growth phase in 2017 but there is currently a lull as the City Council does not wish to have new development. The GanJee property is surrounded by fairly derelict buildings which makes valuation difficult. • Present value of future cash flows: The directors have calculated net cash inflows over the next 20 years estimated to be $300 million per year, based on projected cash flows from rental income, tax savings and expenditures. The directors expect that the building will need substantial renovation in 20 years’ time. The directors based their valuation on the following factors: ✓ discount rate of 11.5% to 14.5%; ✓ average subsequent tenure period of ten years for retail units (ILU) and four years for serviced apartments (SA).
Required
Discuss each of the above four values as a basis for establishing a fair value for the property. In accordance with AASB 13/IFRS 13 which methodology do you believe is most appropriate? What additional information if any would you wish to obtain to make a better estimate?
PART B
Walkabout Park wants to determine fair value of the animals in their zoo. They hold the animals primarily for breeding and preservation of native species but also for the benefit of the local population and school group visits.
Required
Provide your recommendation for how the entity should go about measuring the biological assets’ fair value. In your response provide an explanation of possible alternatives and justify your recommendation.
In: Accounting
Bliesmer Electronics incurred the following costs.
| 1. | Sales tax on factory machinery purchased | € 5,000 |
| 2. | Painting of and lettering on truck immediately upon purchase | 700 |
| 3. | Installation and testing of factory machinery | 2,000 |
| 4. | Real estate broker's commission on land purchased | 3,500 |
| 5. | Insurance premium paid for first year's insurance on new truck | 1,100 |
| 6. | Cost of landscaping on property purchased | 7,200 |
| 7. | Cost of paving parking lot for new building constructed | 17,900 |
| 8. | Cost of clearing, draining, and filling land | 12,600 |
| 9. | Architect's fees on self‐constructed building | 10,000 |
Instructions
- Determine property, plant, and equipment costs.
- Indicate to which account Bliesmer would debit each of the costsAssume a monthly accounting period.
- The following accounts are available in the general ledger: Prepaid Insurance; GST Clearing; Land; Buildings; Equipment; Land Improvements; Interest Expense; Other Expense.
- Assume the “sales tax” of €5,000 in the first item is GST. All of the other figures given, beginning with Cost 2., are net of GST.
- Add the following cost #10: €30,000 of interest incurred on borrowings to finance construction of the building, where €2,000 was incurred prior to construction, $24,000 was incurred during the nine-month construction period, and €4,000 was incurred after construction was completed.
In: Accounting