Questions
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,520 2,190 960 3,150 960 — 2 1,520 960 2,480 3,150 2,480 — 3 1,520 2,190 1,760 3,150 1,660 — 4 520 3,020 1,040 3,640 885 — 5 520 3,020 1,440 3,640 1,660 — 6 520 3,020 2,000 4,800 1,880 — Required: Complete the following table.

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,680 2,670 1,440 4,110 1,440
2 1,680 1,440 3,120 4,110 3,120
3 1,680 2,670 3,040 4,110 2,940
4 680 3,180 1,360 4,760 965
5 680 3,180 2,560 4,760 2,940
6 680 3,180 3,600 6,355 3,320


Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Answer is not complete.

Gross Profit (Loss) Recognized
Revenue Recognized Over Time Revenue Recognized Upon Completion
Situation 2018 2019 2020 2018 2019 2020
1 $293,057selected answer correct $757,500selected answer incorrect $251,000selected answer incorrect 0selected answer correct 0selected answer correct not attempted
2 293,057selected answer correct (13)selected answer incorrect 280,000selected answer correct 0selected answer correct 0selected answer correct not attempted
3 293,057selected answer correct (783,000)selected answer incorrect (100,000)selected answer correct 0selected answer correct 0selected answer incorrect not attempted
4 170,000selected answer correct 1,410,000selected answer correct 0selected answer correct 0selected answer correct 0selected answer correct not attempted
5 170,000selected answer correct (170,000)selected answer correct (380,000)selected answer incorrect 0selected answer correct 0selected answer correct not attempted
6 (235,000)selected answer correct (145,000)selected answer correct (280,000)selected answer correct not attempted not attempted

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,690 2,700 1,470 4,170 1,470
2 1,690 1,470 3,160 4,170 3,160
3 1,690 2,700 3,120 4,170 3,020
4 690 3,190 1,380 4,830 970
5 690 3,190 2,630 4,830 3,020
6 690 3,190 3,700 6,455 3,410


Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Gross Profit (loss) Recogonized

Revenue Recogonized over time/Revenue Recogonized upon completed for situation 1-6 years 2018, 2019, 2020

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,630 2,520 1,290 3,810 1,290 — 2 1,630 1,290 2,920 3,810 2,920 — 3 1,630 2,520 2,640 3,810 2,540 — 4 630 3,130 1,260 4,410 940 — 5 630 3,130 2,210 4,410 2,540 — 6 630 3,130 3,100 5,855 2,870 — Required: Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,630 2,520 1,290 3,810 1,290
2 1,630 1,290 2,920 3,810 2,920
3 1,630 2,520 2,640 3,810 2,540
4 630 3,130 1,260 4,410 940
5 630 3,130 2,210 4,410 2,540
6 630 3,130 3,100 5,855 2,870

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1

1,640

2,550

1,320

3,870

1,320

2

1,640

1,320

2,960

3,870

2,960

3

1,640

2,550

2,720

3,870

2,620

4

640

3,140

1,280

4,480

945

5

640

3,140

2,280

4,480

2,620

6

640

3,140

3,200

5,955

2,960

Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Gross Profit (Loss) Recognized

Revenue Recognized over Time   Revenue Recognized Upon Completion

Situation

2018

2019

2020

2018

2019

2020

1

264900

411887

213213

0

0

890000

2

264900

-24900

240000

0

0

480000

3

264900

4

5

6

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1

1,640

2,550

1,320

3,870

1,320

2

1,640

1,320

2,960

3,870

2,960

3

1,640

2,550

2,720

3,870

2,620

4

640

3,140

1,280

4,480

945

5

640

3,140

2,280

4,480

2,620

6

640

3,140

3,200

5,955

2,960

Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Gross Profit (Loss) Recognized

Revenue Recognized over Time   Revenue Recognized Upon Completion

Situation

2018

2019

2020

2018

2019

2020

1

264900

411887

213213

0

0

890000

2

264900

-24900

240000

0

0

480000

3

264900

4

5

6

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $5,700,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $5,700,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,570 2,340 1,110 3,450 1,110
2 1,570 1,110 2,680 3,450 2,680
3 1,570 2,340 2,160 3,450 2,060
4 570 3,070 1,140 3,990 910
5 570 3,070 1,790 3,990 2,060
6 570 3,070 2,500 5,300 2,330

Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Revenue Recognized Over Time Revenue Recognized over time Revenue recognized over time Revenue recognized upon completion Upon Completion Upon Completion
Situation 2018 2019 2020 2018 2019 2020
1
2
3
4
5
6

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,520 2,190 960 3,150 960
2 1,520 960 2,480 3,150 2,480
3 1,520 2,190 1,760 3,150 1,660
4 520 3,020 1,040 3,640 885
5 520 3,020 1,440 3,640 1,660
6 520 3,020 2,000 4,800 1,880

Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)


In: Accounting

Entity A is a local construction company, which provides construction services to different types of customers....

Entity A is a local construction company, which provides construction services to different types of customers. On 16 December 2017, Entity A ordered a concrete plant from Entity B. The listed price of the plant is $650,000 for general customers. However, Entity B offers a 10% trade discount to Entity A because it is one of its loyal customers. The plant was delivered to Entity A on 1 January 2018. According to the contract, Entity B provides a 2-month credit period to Entity A. Finally, Entity A fully settled the outstanding amount on 1 February 2018.

Installation and testing services are required to make the plant ready for use. On 1 January 2018, Entity C, the installation and testing service provider completed the concrete plant installation and testing services and certified the plant was really for use by Entity A. The cost of installation and testing services are $5,000 and it was settled with Entity C by cheque on 1 January 2018. At the inception stage, Entity A expected the useful life of the concrete plant is 5 years.

According to the local environmental protection regulation, Entity A is required to remove the concrete plant at the end of the reporting period in the Year 2022. The removal cost of $5,100 and the plant residual value of $4,013 was estimated at the inception of the contract respectively.

Finally, on 31 December 2022, the removal cost incurred was the same as the estimated amount and it will be paid in the first week of the Year 2023. However, the residual of the concrete plant can be sold by $1,900 only. A cheque was received on the same date.

Entity A always applies to discount with a rate of 8.05%.

REQUIRED:

According to relevant accounting standards, prepare journal entries to record the transactions of Entity A on 16 December 2017, 31 December 2017, 1 January 2018, 1 February 2018, 31 December 2018, 1 January 2020 and 31 December 2020, 1 January 2022 and 31 December 2022.

ACCOUNT NAMES FOR INPUT:

| PPE | Bank | Inventory | Revenue | Cost of sales | Payable | Receivable |

| Restoration liability | Interest expense | Interest revenue | Depreciation | Accum. depreciation |

| Loss on disposal | Gain on disposal | Share capital | Retained earnings | No entry |

ANSWERS:

Journal Entries:

Date Account Name Debit ($) Credit ($) Hints For Items If Necessary
16-Dec-17
31-Dec-17
1-Jan-18
Purchase price.   Judge Dr/Cr side.
Directly attributable cost. Judge Dr/Cr side.
Dismantling cost. Judge Dr/Cr side.
1-Feb-18
31-Dec-18 An interest created due to the dismantling cost.
31-Dec-18
1-Jan-20
31-Dec-20 An interest created due to the dismantling cost.
31- Dec-20
1-Jan-22
31-Dec-22 An interest created due to the dismantling cost.
31-Dec-22
31-Dec-22 The settlement of dismantling cost.
31-Dec-22 The disposal of the concrete plant.
The gain or loss on disposal.  Judge Dr/Cr side.

In: Accounting

Entity A is a local construction company, which provides construction services to different types of customers....

  1. Entity A is a local construction company, which provides construction services to different types of customers. On 16 December 2017, Entity A ordered a concrete plant from Entity B. The listed price of the plant is $650,000 for general customers. However, Entity B offers a 10% trade discount to Entity A because it is one of its loyal customers. The plant was delivered to Entity A on 1 January 2018. According to the contract, Entity B provides a 2-month credit period to Entity A. Finally, Entity A fully settled the outstanding amount on 1 February 2018.

    Installation and testing services are required to make the plant ready for use. On 1 January 2018, Entity C, the installation and testing service provider completed the concrete plant installation and testing services and certified the plant was really for use by Entity A. The cost of installation and testing services are $5,000 and it was settled with Entity C by cheque on 1 January 2018. At the inception stage, Entity A expected the useful life of the concrete plant is 5 years.

    According to the local environmental protection regulation, Entity A is required to remove the concrete plant at the end of the reporting period in the Year 2022. The removal cost of $5,100 and the plant residual value of $4,013 was estimated at the inception of the contract respectively.

    Finally, on 31 December 2022, the removal cost incurred was the same as the estimated amount and it will be paid in the first week of the Year 2023. However, the residual of the concrete plant can be sold by $1,900 only. A cheque was received on the same date.

    Entity A always applies to discount with a rate of 8.05%.

    REQUIRED:

    According to relevant accounting standards, prepare journal entries to record the transactions of Entity A on 16 December 2017, 31 December 2017, 1 January 2018, 1 February 2018, 31 December 2018, 1 January 2020 and 31 December 2020, 1 January 2022 and 31 December 2022.

    ACCOUNT NAMES FOR INPUT:

    | PPE | Bank | Inventory | Revenue | Cost of sales | Payable | Receivable |

    | Restoration liability | Interest expense | Interest revenue | Depreciation | Accum. depreciation |

    | Loss on disposal | Gain on disposal | Share capital | Retained earnings | No entry |

    ANSWERS:

    Journal Entries:

    Date Account Name Debit ($) Credit ($) Hints For Items If Necessary
    16-Dec-17 Blank 1 Blank 2
    Blank 3 Blank 4
    31-Dec-17 Blank 5 Blank 6
    Blank 7 Blank 8
    1-Jan-18 Blank 9 Blank 10
    Blank 11 Blank 12 Purchase price. Judge Dr/Cr side.
    Blank 13 Blank 14 Directly attributable cost. Judge Dr/Cr side.
    Blank 15 Blank 16 Dismantling cost. Judge Dr/Cr side.
    1-Feb-18 Blank 17 Blank 18
    Blank 19 Blank 20
    31-Dec-18 Blank 21 Blank 22 An interest created due to the dismantling cost.
    Blank 23 Blank 24
    31-Dec-18 Blank 25 Blank 26
    Blank 27 Blank 28
    1-Jan-20 Blank 29 Blank 30
    Blank 31 Blank 32
    31-Dec-20 Blank 33 Blank 34 An interest created due to the dismantling cost.
    Blank 35 Blank 36
    31- Dec-20 Blank 37 Blank 38
    Blank 39 Blank 40
    1-Jan-22 Blank 41 Blank 42
    Blank 43 Blank 44
    31-Dec-22 Blank 45 Blank 46 An interest created due to the dismantling cost.
    Blank 47 Blank 48
    31-Dec-22 Blank 49 Blank 50
    Blank 51 Blank 52
    31-Dec-22 Blank 53 Blank 54 The settlement of dismantling cost.
    Blank 55 Blank 56
    31-Dec-22 Blank 57 Blank 58 The disposal of the concrete plant.
    Blank 59 Blank 60
    Blank 61 Blank 62
    Blank 63 Blank 64 The gain or loss on disposal.  Judge Dr/Cr side.

In: Accounting