Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period.

2020 2021 2022
Costs to date $848,000 $1,871,250 $2,428,000
Estimated costs to complete 1,802,000 623,750 0
Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000
Cash collected to date 748,000 2,271,000 2,900,000

Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.

CRANE CONSTRUCTION INC.
STATEMENT OF GROSS PROFIT
2020 2021 2022 Total
Revenue $928,000 $1,247,000 $725,000 $2,900,000
Costs ($848,000) ($1,023,250) ($556,750) ($2,428,000)
Gross profit $80,000 $223,750 $168,250 $472,000

Using the percentage-of-completion method, prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.)

For the Year 2020:

1-

2-

(To record Cost of Construction)

1-

2-

To record progress billings

1-

2-

To record collections

1-

2-

To record revenues

1-

2-

To record construction expenses

Same procedures for 2021:

In: Accounting

Question 8 Queens Construction Company commences construction of a harbour on 1 July 2020. It signs...

Question 8

Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project:

2021

2022

2023

($ M)

($ M)

($ M)

Costs for the year

90

110

120

Costs incurred to date

90

200

320

Estimated costs to complete

210

120

-

Progress billings during the year

100

120

180

Cash collected during the year

90

130

180

The contract is completed as expected on 30 June 2023. Queens Construction Company uses the percentage-of-completion method to account for its construction contract.

REQUIRED

Provide the numbers for the journal entries below. Assume the stage of completion can be reliably determined. Round the percentage complete (%) to one decimal place (i.e, 0.0%) if necessary.  Complete the six blanks below. (You don't need to provide the numbers for "?")

-------------------------------------

Journal entry to record periodic income recognised for 2021, 2022, 2022

In: Accounting

The article under required readings entitled “Progress, Pain for Vikings Stadium in 2015” describes the construction...

The article under required readings entitled “Progress, Pain for Vikings Stadium in 2015” describes the construction progress of the U.S. Bank Stadium in Minneapolis, Minnesota as of a point in time. One of the items highlighted in the article is the cost—there were some staggering numbers cited by the author in terms of cost overruns! For example, the author states in one year, the project costs had increased by $65 million for a total cost increase from $1.026 billion to $1.091 billion. Since there are public monies being utilized for approximately half of the cost of the facility, there is an entity overseeing the construction on behalf of the public.

The board of this entity approved budget increases at 10 out of 12 meetings in a 12-month span of time. The remaining cost is being funded by the NFL franchise, the Minnesota Vikings. Even though the Minnesota Vikings have absorbed a large amount of the cost overruns, it is likely possible that state and city taxpayers are concerned that such a large project with a relatively short construction window (31 months) given its size could have been under-budgeted to this degree.

This is a commonly debated issue in the media, so whether you are a sports fan/music lover/theater buff/monster truck-motocross muddy fan, it’s your turn to weigh in! Use this discussion board as a debate for one side or the other…does the Minnesota Sports Facility Authority (and any other jurisdiction’s construction oversight organization) have an ethical obligation to the taxpayers to keep the project on budget even if it means that the brand new publicly funded entertainment facility that would last 15-20 years have to go without or have lesser quality features, or should they strive for world class status with the anticipation of those features attracting larger and better future events to stimulate the local economy regardless of the current costs? Please be respectful with your comments. Everyone is entitled to their opinions!

Your initial posting should be 250-500 words

In: Economics

evolution of facility design in the 1930s-1940s evolution of design in the 1970's to 1980's facility...

evolution of facility design in the 1930s-1940s

evolution of design in the 1970's to 1980's

facility design **

In: Nursing

leadership: the "great man" traits that make an effective leader, this period range from Circa 450BC...

leadership: the "great man" traits that make an effective leader, this period range from Circa 450BC to the 1940s.

In: Operations Management

People have been using Cameras for private daily use since the 1880s and the first Kodak...

People have been using Cameras for private daily use since the 1880s and the first Kodak camera cost a lot of money in those days. Today we wish to see if the size of the camera can be used to predict the cost. The data is given below:

Y = cost in dollars X = weight in ounces y {300, 250, 350, 400, 150, 180, 140, 300, 300, 200} X {6, 5, 7, 5, 6, 6, 4, 6, 6, 5} The following information is available for you to use in the analysis of this topic. n=10 x̄= 5.6 ȳ= 257 SSxy = 248 SSxx = 6.4 SSyy = 69010

Find the least squares prediction equation. a)Ŷ = -300 + 100X1 b)Ŷ = 0 + 50X1 c)Ŷ = 40 + 38.75X1 d)none of these

In: Math

Instructions: A movie theater only keeps a percentage of the revenue earned from ticket sales. The...

Instructions: A movie theater only keeps a percentage of the revenue earned from ticket sales. The remainder goes to the movie distributor. Write a program that calculates a theater’s gross and net box office profit for a night. The program should ask for the name of the movie, and how many adults and child tickets were sold. The price of an adult ticket is $10.00 ad a child ticket is $6.00.) It should display a report similar to


Movie Name: “Wheels of Fury”

Adult Tickets Sold: 382

Child Tickets Sold: 127

Gross Box Office Profit: $4582.00

Net Box Office Profit: $916.40

Amount Paid to Distributor: $3665.60


program used is c++

In: Computer Science

Q = A university is hiring new construction company and need to come with a blueprint....

Q = A university is hiring new construction company and need to come with a blueprint. They are debating on how much distance/km belonging to a forested park can be preserved. Within this region, there are 250 residents and each have an identical inverse dmnd function where P = 20 - Q. Here, Q represents the amount of distance/km preserved. P is the representing per distance cost; that an individual is willing to pay for the amount of distance (Q).

Note: Margnal cost value is $800 per distnce/km

1. To support this question, Incorporate the marginal cost curve/, marginal benefit curve and write aggregate demand and plot these into graph

2.How much km is required fro be preserve in the context of efficient allocation,

In: Economics

5. The Gardner Theater, a community playhouse, needs to determine the lowest-cost production budget for an...

5. The Gardner Theater, a community playhouse, needs to determine the lowest-cost production budget for an upcoming show. Specifically, they have to determine which set pieces to construct and which, if any, set pieces to rent from another local theater at a predetermined fee. However, the organization has only two weeks to fully construct the set before the play goes into technical rehearsals. The theater has two part-time carpenters who work up to 12 hours a week, each at $10 an hour. Additionally, the theater has a part-time scenic artist who can work 15 hours per week to paint the set and props as needed at a rate of $15 per hour. The set design requires 20 flats (walls), two hanging drops with painted scenery, and three large wooden tables (props). The number of hours required for each piece for carpentry and painting is shown below:

Carpentry

Painting

Flats

0.5

  2.0

Hanging drops

2.0

12.0

Props

3.0

  4.0

Flats, hanging drops, and props can also be rented at a cost of $75, $500, and $350 each, respectively. How many of each unit should be built by the theater and how many should be rented to minimize total costs?

Gardner Theater
Hours Required/Piece Carpentry Painting
Flats 0.5 2.0
Hanging Drops 2.0 12.0
Props 3.0 4.0
Hours Available 48.0 30.0
Labor Rate/hour $10.00 $15.00

In: Statistics and Probability

The Gardner Theater, a community playhouse, needs to determine the lowest-cost production budget for an upcoming...

The Gardner Theater, a community playhouse, needs to determine the lowest-cost production budget for an upcoming show. Specifically, they have to determine which set pieces to construct and which, if any, set pieces to rent from another local theater at a predetermined fee. However, the organization has only two weeks to fully construct the set before the play goes into technical rehearsals. The theater has two part-time carpenters who work up to 12 hours a week, each at $10 an hour. Additionally, the theater has a part-time scenic artist who can work 15 hours per week to paint the set and props as needed at a rate of $15 per hour. The set design requires 20 flats (walls), two hanging drops with painted scenery, and three large wooden tables (props). The number of hours required for each piece for carpentry and painting is shown below:

Carpentry Painting
Flats 0.5   2.0
Hanging drops 2 12
Props 3

  4.0

Flats, hanging drops, and props can also be rented at a cost of $75, $500, and $350 each, respectively. How many of each unit should be built by the theater and how many should be rented to minimize total costs?

In: Accounting