Questions
Property, plant, and equipment and intangible assets; comprehensive The Thompson Corporation, a manufacturer of steel products,...

Property, plant, and equipment and intangible assets; comprehensive

The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2014. The accounting department of Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing this schedule. In addition to ascertaining that the data already on the schedule are correct, you have obtained the following information from the company’s records and personnel:

a. Depreciation is computed from the first of the month of acquisition to the first of the month of disposition.

b. Land A and Building A were acquired from a predecessor corporation. Thompson paid $812,500 for the land and building together. At the time of acquisition, the land had a fair value of $72,000 and the building had a fair value of $828,000.

c. Land B was acquired on October 2, 2014, in exchange for 3,000 newly issued shares of Thompson’s common stock. At the date of acquisition, the stock had a par value of $5 per share and a fair value of $25 per share. During October 2014, Thompson paid $10,400 to demolish an existing building on this land so it could construct a new building.

d. Construction of Building B on the newly acquired land began on October 1, 2015. By September 30, 2016, Thompson had paid $210,000 of the estimated total construction costs of $300,000. Estimated completion and occupancy are July 2017.

e. Certain equipment was donated to the corporation by the city. An independent appraisal of the equipment when donated placed the fair value at $16,000 and the residual value at $2,000.

f. Machine A’s total cost of $110,000 includes installation charges of $550 and normal repairs and maintenance of $11,000. Residual value is estimated at $5,500. Machine A was sold on February 1, 2016.

g. On October 1, 2015, Machine B was acquired with a down payment of $4,000 and the remaining payments to be made in 10 annual installments of $4,000 each beginning October 1, 2016. The prevailing interest rate was 8%.

                                             THOMPSON CORPORATION   

                             Fixed Asset and Depreciation Schedule

For Fiscal Years Ended September 30, 2015 and September 30, 2016

                                                                                                            

Assets

Acquisition Date

Cost Residual Depreciation Method Estimated Life in Years

Depreciation

2015

for year ended 9/30

2016

Land A 10/1/14 $ (1) N/A N/A N/A N/A N/A
Building A 10/1/14 $ (2) $47,500 SL (3) $14,000 $ (4)
Land B 10/2/14 $ (5) N/A N/A N/A N/A N/A
Building B Under Construction

$210,000

to date

   ___ SL 30 ___ (6)
Donated Equipment 10/2/14 $ (7) $2,000 150% Declining Balance 10 (8) (9)
Machine A 10/2/14 $ (10) $5,500 Sum of the years' -digits 10 (11) (12)
Machine B 10/1/15 $ (13) ------- SL 15 -------- (14)
N/A = NOT APPLICABLE

Required:

Supply the correct amount for each numbered item on the schedule. Round each answer to the nearest dollar.(AICPA adapted)

   

In: Accounting

Property, plant, and equipment and intangible assets; comprehensive The Thompson Corporation, a manufacturer of steel products,...

Property, plant, and equipment and intangible assets; comprehensive

The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2014. The accounting department of Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing this schedule. In addition to ascertaining that the data already on the schedule are correct, you have obtained the following information from the company’s records and personnel:

a. Depreciation is computed from the first of the month of acquisition to the first of the month of disposition.

b. Land A and Building A were acquired from a predecessor corporation. Thompson paid $812,500 for the land and building together. At the time of acquisition, the land had a fair value of $72,000 and the building had a fair value of $828,000.

c. Land B was acquired on October 2, 2014, in exchange for 3,000 newly issued shares of Thompson’s common stock. At the date of acquisition, the stock had a par value of $5 per share and a fair value of $25 per share. During October 2014, Thompson paid $10,400 to demolish an existing building on this land so it could construct a new building.

d. Construction of Building B on the newly acquired land began on October 1, 2015. By September 30, 2016, Thompson had paid $210,000 of the estimated total construction costs of $300,000. Estimated completion and occupancy are July 2017.

e. Certain equipment was donated to the corporation by the city. An independent appraisal of the equipment when donated placed the fair value at $16,000 and the residual value at $2,000.

f. Machine A’s total cost of $110,000 includes installation charges of $550 and normal repairs and maintenance of $11,000. Residual value is estimated at $5,500. Machine A was sold on February 1, 2016.

g. On October 1, 2015, Machine B was acquired with a down payment of $4,000 and the remaining payments to be made in 10 annual installments of $4,000 each beginning October 1, 2016. The prevailing interest rate was 8%.

THOMPSON CORPORATION

Fixed Asset and Depreciation Schedule

For Fiscal Years Ended September 30, 2015 and September 30, 2016

Assets

Acquistion Date

Cost Residual Depreciation Method Estimated Life in Years

Depreciation

2015

for Year Ended 9/30

2016

Land A 10/1/14 $ (1)    N/A      N/A     N/A      N/A    N/A
Building A 10/1/14 (2) $47,500       SL      (3) $14,000 $ (4)
Land B 10/2/14 (5)    N/A     N/A    N/A     N/A N/A
Building B Under Construction 210,000 to date    -------       SL      30    -------- (6)
Donated Equipment    10/2/14    (7) 2,000 150% Declining Balance     10      (8)    (9)
Machine A    10/2/14    (10) 5,500 Sum of the years' digits      10      (11) (12)
Machine B    10/1/15    (13)   -------       SL      15     -------- (14)
N/A= not applicable

Required:

Supply the correct amount for each numbered item on the schedule. Round each answer to the nearest dollar.(AICPA adapted)

In: Accounting

XYZ Inc. sell Product Y at P5 per unit. The variable costs ofmaking and selling...

XYZ Inc. sell Product Y at P5 per unit. The variable costs of making and selling each unit is P3 while the total fixed cost is P2,000. The company wants to earn a profit of P3,000. The company is subject to 40% tax rate.

  1. What is the break-even point in units and pesos?

  2. What should be the level of sales in units and pesos to earn the desired profit if it is before tax?

  3. What should be the level of sales in units and pesos to earn the desired profit if it is after tax?

  4. What is the Margin of Safety for the target sales computed in requirement 3 in units, pesos, and percentage?

In: Accounting

Adam Company uses the weighted-average method in its process costing system. The following information for the...

Adam Company uses the weighted-average method in its process costing system. The following information for the Assembly Department was obtained from the accounting records for September (all materials are added at the beginning of the process):

Number of Units Labour and overhead percentage complete
Work in process inventory, Sept. 1 60,000 15%
Transferred in the during the month 105,000
Work in process inventory, Sept. 30 40,000 20%
Transferred In Materials Labour and overhead
Beginning work-in-process inventory $30,000 $16,000
Cost added during the month $63,000 $320,000

What are the equivalent units of production for material for the month?

In: Accounting

A company has improved its production process. Under the old process, 19 workers could produce 4206...

A company has improved its production process. Under the old process, 19 workers could produce 4206 units per hours and the materials cost $53 per unit of output. Workers are paid $15 per hour and the finished product is sold for $126 per unit.

After the improvement, materials costs have been reduced by $12 per unit of output and it now takes 4 fewer workers to make the same amount of output.

What is the percentage change in multifactor productivity? (do not use a % sign, e.g. enter 50% as .5)

round to at least 5 decimal places

In: Operations Management

Your division is considering two inverstment projects, each of which required an upfront expenditure of $25million....

Your division is considering two inverstment projects, each of which required an upfront expenditure of $25million. You estimate that the cost of capital is 10 percent and that the investments will produce the following after-tax cash flows (in millions of dollars). I the firms WACC is 10 percent, and it uses a 2 percentage point (plus or minus) risk premium, and if project A is deemed riskier than usual project, what would its risk adjusted NPV be?

Year Project A project B

1 5 20

2 10 10

3 15 8

4 20 6

In: Finance

XYZ Inc. sell Product Y at P5 per unit. The variable costs of making and selling...

XYZ Inc. sell Product Y at P5 per unit. The variable costs of making and selling each unit is P3 while the total fixed cost is P2,000. The company wants to earn a profit of P3,000. The company is subject to 40% tax rate.

  1. What is the break-even point in units and pesos?
  2. What should be the level of sales in units and pesos to earn the desired profit if it is before tax?
  3. What should be the level of sales in units and pesos to earn the desired profit if it is after tax?
  4. What is the Margin of Safety for the target sales computed in requirement 3 in units, pesos, and percentage?

In: Accounting

Cantor Products Sells a product for $92. variable cost per unit or $36, and monthly fixed...

Cantor Products Sells a product for $92. variable cost per unit or $36, and monthly fixed costs are $212,800.

A. What is the break even point in units?

B. What unit sales would be required to earn a target profit of $403,200.

C. assumed he achieve the level of sales required and part B, what is the degree of operating leverage? (round your answer to three decimal places)

D. if sales decreased by 30% from that level, by what percentage of profits decrease? (Do not round intermediate calculation. Round your answer to two decimal places)

In: Accounting

77-78. Rocky bought 7-year class property on January 4, this year, for $120,000. Assume his business...

77-78. Rocky bought 7-year class property on January 4, this year, for $120,000. Assume his business income is $6,000 before the deduction for the Section 179 expense.

77.     The amount of the currently deductible 179 expense is:

a.

a.       $4,000

b.

b.       $6,000

c.

c.       $10,000

78. The MACRS table percentage (if the table is to be used) which would be applied to the remaining basis of the asset to calculate cost recovery in the first year (in addition to the 179 expense) is:

a.

a.       .1429

b.

b.       0

c.

c.       .20

d.

d.       None of the above

d.       None of the above

In: Accounting

please answer both parts Sofie Uretsky is buying a house that cost $225,000. She makes a...

please answer both parts

Sofie Uretsky is buying a house that cost $225,000. She makes a 15% down payment and she is expected to make monthly payments for the next 15 years on the balance of the loan which she is financing at 3.5% APR. With the given information, construct an amortization table and answer the following questions:

c) What will the remaining balance be on the loan after she makes the 60th payment?
d) What percentage of the total payments is paid to interest for the first three years (= total interest payments for the first 36 months / total payments for the first 36 months)?

In: Finance