For the following, explain what each of them will do in MatLab by saying what the command does and what the result is. For example, if the command is >>x(2:end, 1:3) then your answer to this problem should be: This command retrieves the subset of x defined by rows 2 and 3 and columns 1-3. The result is a 2x3 matrix. Before you begin, run the command: x = [1 3 4 5 7; 5 6 10 9 11; 10 23 23 1 3];
a) x(:,5)
b) x(1,:)
c) x(2,3:4)
d) x(1:2,2:5)
e) length(x(1,:))
f) length(x(:,1))
g) sum(x(2,:))
h) mean(x(:,end))
i) max(x)
j) max(max(x))
k) round(3.75)
l) floor(3.75)
m) rem(150,100)
n) log(25)
In: Mechanical Engineering
Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past two decades. Jim Sager, president of the firm, is considering the development of a new manufacturing line to allow it to produce high-quality plastic toys at reasonable prices. The development process is long and complex. Jim estimates that there are five phases involved and multiple activities for each phase.
Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a probable completion time of 3 weeks, and a pessimistic completion time of 4 weeks. Activity B has estimated completion times of 5, 6, and 8 weeks; these represent optimistic, probable, and pessimistic time estimates. Similarly, activity C has estimated completion times of 1 week, 1 week, and 2 weeks; and activity D has expected completion times of 8 weeks, 9 weeks, and 11 weeks.
Phase 2 involves six separate activities. Activity E has activity A as an immediate predecessor. Time estimates are 1 week, 1 week, and 4 weeks. Activity F and activity G both have activity B as their immediate predecessor. For activity F, the time estimates are 3 weeks, 3 weeks, and 4 weeks. For activity G, the time estimates are 1 week, 2 weeks, and 2 weeks. The only immediate predecessor for activity H is activity C. Time estimates for activity H are 5 weeks, 5 weeks, and 6 weeks. Activity D must be performed before activity I and activity J can be started. Activity I has estimated completion times of 9 weeks, 10 weeks, and 11 weeks. Activity J has estimated completion times of 1 week, 2 weeks, and 2 weeks.
Phase 3 is the most difficult and complex of the entire development project. It also consists of six separate activities. Activity K has three time estimates of 2 weeks, 2 weeks, and 3 weeks. The immediate predecessor for this activity is activity E. The immediate predecessor for activity L is activity F. The time estimates for activity L are 3 weeks, 4 weeks, and 6 weeks. Activity M has 2 weeks, 2 weeks, and 4 weeks for the estimates of the optimistic, probable and pessimistic time estimates. The immediate predecessor for activity M is activity G. Activities N and O both have activity I as their immediate predecessor. Activity N has 8 weeks, 9 weeks, and 11 weeks for its three time estimates. Activity O has 1 week, 1 week, and 3 weeks as its time estimates. Finally, activity P has time estimates of 4 weeks, 4 weeks, and 8 weeks. Activity J is its only immediate predecessor.
Phase 4 involves five activities. Activity Q requires activity K to be completed before it can be started. The three time estimates for activity Q are 6 weeks, 6 weeks, and 7 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 4 weeks. Activity S requires activity N to be completed first. Its time estimates are 6 weeks, 6 weeks, and 7 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3 weeks, 3 weeks, and 4 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1 week, 2 weeks, and 3 weeks. Activity P must be completed before activity U can be started.
Phase 5 is the final phase of the development project. It consists of only two activities. Activity V requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9 weeks, 10 weeks, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started. These are activities S, T, and U. The estimated completion times for activity W are 2 weeks, 4 weeks, and 5 weeks.
In: Statistics and Probability
Sager Products has been in the business of manufacturing and marketing toys for toddlers for the past two decades. Jim Sager, president of the firm, is considering the development of a new manufacturing line to allow it to produce high-quality plastic toys at reasonable prices. The development process is long and complex. Jim estimates that there are five phases involved and multiple activities for each phase.
Phase 1 of the development process involves the completion of four activities. These activities have no immediate predecessors. Activity A has an optimistic completion time of 2 weeks, a probable completion time of 3 weeks, and a pessimistic completion time of 4 weeks. Activity B has estimated completion times of 5, 6, and 8 weeks; these represent optimistic, probable, and pessimistic time estimates. Similarly, activity C has estimated completion times of 1 week, 1 week, and 2 weeks; and activity D has expected completion times of 8 weeks, 9 weeks, and 11 weeks.
Phase 2 involves six separate activities. Activity E has activity A as an immediate predecessor. Time estimates are 1 week, 1 week, and 4 weeks. Activity F and activity G both have activity B as their immediate predecessor. For activity F, the time estimates are 3 weeks, 3 weeks, and 4 weeks. For activity G, the time estimates are 1 week, 2 weeks, and 2 weeks. The only immediate predecessor for activity H is activity C. Time estimates for activity H are 5 weeks, 5 weeks, and 6 weeks. Activity D must be performed before activity I and activity J can be started. Activity I has estimated completion times of 9 weeks, 10 weeks, and 11 weeks. Activity J has estimated completion times of 1 week, 2 weeks, and 2 weeks.
Phase 3 is the most difficult and complex of the entire development project. It also consists of six separate activities. Activity K has three time estimates of 2 weeks, 2 weeks, and 3 weeks. The immediate predecessor for this activity is activity E. The immediate predecessor for activity L is activity F. The time estimates for activity L are 3 weeks, 4 weeks, and 6 weeks. Activity M has 2 weeks, 2 weeks, and 4 weeks for the estimates of the optimistic, probable and pessimistic time estimates. The immediate predecessor for activity M is activity G. Activities N and O both have activity I as their immediate predecessor. Activity N has 8 weeks, 9 weeks, and 11 weeks for its three time estimates. Activity O has 1 week, 1 week, and 3 weeks as its time estimates. Finally, activity P has time estimates of 4 weeks, 4 weeks, and 8 weeks. Activity J is its only immediate predecessor.
Phase 4 involves five activities. Activity Q requires activity K to be completed before it can be started. The three time estimates for activity Q are 6 weeks, 6 weeks, and 7 weeks. Activity R requires that both activity L and activity M be completed first. The three time estimates for activity R are 1, 2, and 4 weeks. Activity S requires activity N to be completed first. Its time estimates are 6 weeks, 6 weeks, and 7 weeks. Activity T requires that activity O be completed. The time estimates for activity T are 3 weeks, 3 weeks, and 4 weeks. The final activity for phase 4 is activity U. The time estimates for this activity are 1 week, 2 weeks, and 3 weeks. Activity P must be completed before activity U can be started.
Phase 5 is the final phase of the development project. It consists of only two activities. Activity V requires that activity Q and activity R be completed before it can be started. Time estimates for this activity are 9 weeks, 10 weeks, and 11 weeks. Activity W is the final activity of the process. It requires three activities to be completed before it can be started. These are activities S, T, and U. The estimated completion times for activity W are 2 weeks, 4 weeks, and 5 weeks.
In: Statistics and Probability
Many regions in North and South Carolina and Georgia have experienced rapid population growth over the last 10 years. It is expected that the growth will continue over the next 10 years. This has motivated many of the large grocery store chains to build new stores in the region. The Kelley’s Super Grocery Stores Inc. chain is no exception. The director of planning for Kelley’s Super Grocery Stores wants to study adding more stores in this region. He believes there are two main factors that indicate the amount families spend on groceries. The first is their income and the other is the number of people in the family. The director gathered the following sample information.
| Family | Food | Income | Size | |||||
| 1 | $ | 4.14 | $ | 73.98 | 4 | |||
| 2 | 4.08 | 54.90 | 2 | |||||
| 3 | 5.76 | 138.86 | 4 | |||||
| 4 | 3.48 | 52.02 | 1 | |||||
| 5 | 4.20 | 65.70 | 2 | |||||
| 6 | 4.80 | 53.64 | 4 | |||||
| 7 | 4.32 | 79.74 | 3 | |||||
| 8 | 5.04 | 68.58 | 4 | |||||
| 9 | 6.12 | 165.60 | 5 | |||||
| 10 | 3.24 | 64.80 | 1 | |||||
| 11 | 4.80 | 138.42 | 3 | |||||
| 12 | 3.24 | 125.82 | 1 | |||||
| 13 | 7.17 | 77.58 | 7 | |||||
| 14 | 5.94 | 146.51 | 6 | |||||
| 15 | 6.60 | 162.69 | 8 | |||||
| 16 | 5.40 | 141.30 | 3 | |||||
| 17 | 6.00 | 36.90 | 5 | |||||
| 18 | 5.40 | 56.88 | 4 | |||||
| 19 | 3.36 | 71.82 | 1 | |||||
| 20 | 4.68 | 69.48 | 3 | |||||
| 21 | 4.32 | 54.36 | 2 | |||||
| 22 | 5.52 | 87.66 | 5 | |||||
| 23 | 4.56 | 38.16 | 3 | |||||
| 24 | 5.40 | 43.74 | 7 | |||||
| 25 | 6.71 | 59.83 | 5 | |||||
Complete the ANOVA (Leave no cells blank - be certain to enter "0" wherever required. Round SS, MSto 4 decimal places and F to 2 decimal places.)
|
State the decision rule for 0.05 significance level. H0: = β1 = β2 = 0; H1: Not all βi's = 0
Complete the table given below. (Leave no cells blank - be certain to enter "0" wherever required. Round Coefficient, SE Coefficient, P to 4 decimal places and T to 2 decimal places.)
|
In: Statistics and Probability
Do the seven steps for each word problem
Step 1: Establish null and alternate hypotheses
State the null and alternative hypothesis (as a sentence and formula).
Step 2: Calculate the degrees of freedom
Step 3: Calculate t critical using critical t – table
Step 4: Calculate the Sum of Square deviation (SSD)
Step 5: Calculate t obtained
Step 6: Specify the critical value and the obtained value on a t-distribution curve
Step 7: Decision and Conclusion
Write a clear and concise conclusion.
A Pullman local sports store is interested in consumer purchasing likelihood of WSU gear (1=not at all to 7=very much) before and after a win in football. A researcher picks 10 WSU students as the participants of the study. The data are shown below. Use alpha = .01 to see whether a win in football increases consumers’ likelihood of buying WSU gear.
After: 4 5 5 6 5 7 5 6 3 4
Before: 3 5 4 4 5 6 5 4 3 3
A marketing researcher has heard that when kids are anonymous, they'll take more candy. To test this hypothesis, she brings 6 kids into a specially-constructed Halloween Lab with two rooms. Each room is identically decorated and contains a decorated front porch, a front door, and a doorbell. Behind the door is a confederate who will answer the door and offer a bowl of candy. The two rooms differ only in their lighting conditions. One room is light; one room is dark, the latter presumably leading to greater anonymity. She says, ok kids, I want you to go into each room and interact with the person behind the door as you would normally interact during Halloween. Ring the doorbell, say trick or treat, and then take some candy. So, the kids do this and the researcher measures how many pieces of candy they take. The data are shown below. Do kids take more candy under conditions that make them feel anonymous? Use alpha = .10.
Light Room: 1 2 1 1 2 2
Dark Room: 2 2 3 4 4 3
In: Statistics and Probability
In: Computer Science
| 4)Consider two $27,000 face value corporate bonds. Bond A is | |||||||||||||||
| currently selling for $26,946 and matures in 18 years. | |||||||||||||||
| Bond B sells for $25,245 and matures in 3 years. Calculate | |||||||||||||||
| the current yield for both bonds if both have a coupon rate | |||||||||||||||
|
equal to 4%. (Assume a yearly coupon payment). 1)Current yield Bond A to 2 decimal places 2)Current yield Bond B to 2 decimal places 3)YTM Bond A to 2 decimal places 4)YTM Bond B to 2 decimal places
|
|||||||||||||||
In: Finance
The following stem-and-leaf diagram gives the
distances (in thousands of
miles) driven during the past year by a sample of 15 drivers.
0 3 6 9
1 2 8 5 1 0 5
2 5 1 6
3 8
4 1
5
6 2
(a) (1 point) Rank the data on a single line.
(b) (1 point) Compute the mode.
(c) (2 points) Compute the first and third quartiles.
(d) (1 point) Compute the interquartile range.
(e) (2 points) Compute the lower and upper inner fences.
(f) (3 points) Compute the 83rd percentile.
In: Statistics and Probability
Sketch the following regions:
In: Advanced Math
QUESTION 1
Which one of the following types of costs is excluded from the cost of inventory that is routinely manufactured?
|
interest |
||
|
raw materials |
||
|
normal spoilage |
||
|
insurance |
QUESTION 2
On July 1, Maxwell Company had 40 units of inventory at a cost of $6 per unit. July purchases and sales were as follows:
|
Purchases |
Sales |
|||
|
July 5 |
10 units @ $8 |
July 4 |
20 units |
|
|
12 |
20 units @ $10 |
20 |
12 units |
|
|
25 |
10 units @ $16 |
|||
The cost of goods sold during July was $272. Maxwell must use:
|
FIFO |
||
|
LIFO perpetual |
||
|
weighted average |
||
|
LIFO periodic |
QUESTION 3
Exhibit 7-1
Edwards Co. purchased raw materials with a cost of $95,000 on March
2, 2014. Credit terms of 3/20, n/60 applied. If Edwards pays for
the purchase on March 18, 2014, calculate the amount recorded for
inventory on March 2, 2014, using the method given.
Refer to Exhibit 7-1. Edwards uses a perpetual inventory system and
the net price method.
|
$42,000 |
||
|
$76,000 |
||
|
$92,150 |
||
|
$95,000 |
QUESTION 4
Eller Company uses a periodic inventory system. Relevant inventory information for the year follows:
|
1-Jan |
Beginning inventory | 20 units @ $170 per unit |
|
23-May |
Purchased | 20 units @ $135 per unit |
|
5-Nov |
Purchased | 400 units @ $185 per unit |
|
18-Nov |
Purchased | 100 units @ $195 per unit |
At year-end, 50 units remain in inventory. What is the cost of the
ending inventory on a LIFO basis?
|
$7,950 |
||
|
$7,100 |
||
|
$8,750 |
||
|
$8,450 |
QUESTION 5
Near the end of 2015, Spruce Co. made the following purchases. The months involved in all cases are December 2015 and January 2016.
|
Date |
Date |
Date |
Date |
||
|
Goods |
Invoice |
Goods |
Invoice |
||
|
Amount |
FOB |
Shipped |
Mailed |
Rec'd |
Rec'd |
|
$1,575 |
Destination |
12/29 |
1/2 |
1/5 |
1/4 |
|
2,430 |
Shipping Point |
1/2 |
12/29 |
1/4 |
12/30 |
|
1,890 |
Shipping Point |
12/28 |
1/2 |
1/3 |
1/4 |
|
2,700 |
Destination |
12/29 |
12/27 |
1/2 |
12/28 |
What amount of the above purchases should be included in Spruce’s
inventory at December 31, 2015?
|
$1,575 |
||
|
$1,890 |
||
|
$4,320 |
||
|
$4,575 |
In: Accounting